MarketCaltrain Modernization Program
Company Profile

Caltrain Modernization Program

The Caltrain Modernization Program (CalMod), sometimes referred to as the Caltrain Electrification Project, was a $2.44 billion project which added a positive train control (PTC) system and electrified the main line of the U.S. commuter railroad Caltrain, which serves cities in the San Francisco Peninsula and Silicon Valley. The electrification included installation of a 25 kilovolt (kV) alternating current (AC) catenary system over the double-tracked line from San Francisco to San Jose, and acquisition of new rolling stock, consisting of Stadler KISS double-decker electric multiple units (EMU). Caltrain has transitioned from its legacy push-pull trains hauled by diesel-electric locomotives, most of which have been in service since 1985.

History
Background pictured above) since the early 1950s; they were replaced with electric train sets in the 2020s.|alt=An image of Caltrain's diesel locomotive, an EMD F40PH model. Commuter railroad service on the San Francisco Peninsula was inaugurated in 1863 as the San Francisco and San Jose Railroad and purchased by Southern Pacific (SP) in 1870. SP announced that it would investigate the electrification of its line in September 1921, promising better and more frequent service. However, SP cited excessive post-war inflation, taxation, and competition from publicly funded highways as factors making electrification neither "practicable or desirable". In the early 1950s, SP began introducing diesel locomotives on the route. By 1977, Southern Pacific were facing rapidly declining ridership and petitioned the state Public Utilities Commission to allow them to discontinue the commuter rail operation. From 1980 until 1992, the California Department of Transportation (Caltrans) and the three service counties, San Francisco, San Mateo, and Santa Clara, subsidized Southern Pacific operations on the railway until the local Peninsula Corridor Joint Powers Board (PCJPB) acquired the right-of-way in 1991. Early electrification proposals In 1992, Caltrans released the first feasibility study detailing the possibility of electrifying the railroad between San Francisco and San Jose. The 1992 Feasibility Study proposed replacing the existing diesel-electric locomotives with either a fleet of EMD AEM-7 electric locomotives to move the existing gallery passenger cars or Metro North Budd M-2/M-4 EMUs. The primary benefits of an electrified railway would be improvements in air quality, noise, and acceleration, but would also save on other ancillary costs, such as lubricating oil, cooling water, maintenance, and refueling. Because of the relatively close spacing between stops, the improved acceleration using electric locomotives compared to the existing diesel-electric locomotives would cut transit time between San Francisco and San Jose by up to twelve minutes, and using EMUs would cut the time over the same distance by up to 23 minutes, assuming the use of ten-car trainsets. electric locomotive, part of the equipment proposed in the 1992 Feasibility Study to electrify Caltrain. This AEM-7 is in revenue service with SEPTA.|alt=An image of an electric locomotive, an AEM-7 model, that was proposed in a 1992 study. Due to funding shortages, the project was postponed for the next two decades. In 1997, Mayor Willie Brown canceled the appropriation for San Francisco's share of costs to extend rail service to downtown, saying Peninsula residents "ought to fund the whole project" since it would mainly benefit their commute. San Francisco instead applied the money to the Third Street Light Rail Project. Mike Nevin, PCJPB member from San Mateo County noted that while the downtown extension "would have enhanced particularly the electrification of the system", lack of it would not cause Caltrain to collapse. Instead, Caltrain studied a list of potential upgrades and went on to publish a draft Rapid Rail Study on October 1, 1998, which prioritized capital improvements to the physical infrastructure with the overarching goal of expanding rail service. At that time, Caltrain was reporting daily ridership of approximately 25,000 passengers, a 40-year high. The study concluded that in order to meet the five goals presented in the 20-Year Strategic Plan of 1997, Caltrain should first rehabilitate and enhance the line, then electrify it. By itself, electrification was not projected to significantly improve service, and the high estimated cost of electrification and its lower priority meant electrification would be deferred. Some of the money to accomplish the rehabilitation and enhancement of existing track came from funds that had been intended for the downtown extension. Steve Schmidt, a councilman from Menlo Park, argued that electrification instead should be the top priority to make the rail line more palatable to neighbors, citing improvements in noise and pollution. Other advocates for electrification of Caltrain noted the $1.2 billion BART extension to San Francisco International Airport may have revived the decades-old dream of BART around the Bay, which would render an electrified Caltrain redundant. The electrification of Caltrain was assigned a higher priority than a future expansion of the system, which included proposals to bring service to Union City across the Dumbarton Rail Bridge as well as increased service to Gilroy and Salinas. Under the latest proposal to revive rail service over the Dumbarton Rail Corridor, diesel multiple units would first be used to establish Dumbarton Rail service as a rail shuttle between a new rail station in Newark and Caltrain's Redwood City station, later extending service from Newark to Union City, and finally followed by a commuter rail operation running from Union City to San Francisco and San Jose using EMUs. In 2003, The San Francisco County Transit Authority proposed Proposition K in San Francisco, a local transportation sales tax. Voters were given an expenditure plan estimating the total cost of Caltrain electrification as $183.5 Million with San Francisco's share costing $20.5M, met with Proposition K, which passed. Caltrain/HSR blended system project includes funding for public transit systems along its route, including Caltrain.|alt=A map detailing California high-speed rail's "bookend projects", or projects at the tail end of high-speed rail route to improve public transportation and access to high-speed rail stations. Despite increasing ridership, Caltrain experienced a budget crisis in 2011 that nearly forced it to cut service to peak commute hours only, while funding sources for electrification remained unidentified. At the same time, the California High-Speed Rail Authority (CHSRA) was having trouble identifying a route from San Jose to San Francisco in the face of local opposition. In response, U.S. Representative Anna Eshoo, State Senator Joe Simitian, and Assemblymember Rich Gordon announced a "blended" plan to partially fund electrification with high-speed rail money in return for allowing high-speed rail trains to share tracks in the future. Later, Caltrain announced that it had studied the plan and believed it to be feasible. Under a proposed agreement between Caltrain and the CHSRA, details of which were leaked in February 2012, up to $1 billion could be available from the high-speed rail project to help fund the CalMod project, including the positive train control system (dubbed "CBOSS"), electrification of the infrastructure, and elimination of some grade crossings. Under the agreement, the Peninsula Corridor would become eligible for high-speed rail money because the planned routing to San Francisco would use the same lines. This was one of two investments in "bookend" electrification projects, which were intended to upgrade existing passenger rail services near the planned CHSRA San Francisco and Los Angeles terminals to allow high-speed rail to share infrastructure. which received approval from the Metropolitan Transportation Commission a week later. Under the memorandum, $706 million from the high-speed rail bond would be matched by state, regional, and local transportation funds to pay for the estimated $1.5 billion needed for CalMod. In September 2012, the California Transportation Commission released $39.8 million to modernize CBOSS. A month later, the expected funding from high-speed rail bonds rose to $1.5 billion, which alongside electrification provided funding for the planned Downtown Extension (DTX), which would move the northern terminus of the Caltrain line from 4th and King to the Salesforce Transit Center. CHSRA approved the issue of bonds in December 2016. Critics of high-speed rail felt the slower trips and reduced service caused by "blending" the two systems over the Peninsula Corridor did not meet the original voter-approved vision of a quad-track line between San Francisco and Los Angeles, and ridership would never meet projections. Lawsuits . The town of Atherton has backed litigation against Caltrain's electrification plans.|alt=An image of a train station, including tracks, platforms, and a shelter. The town of Atherton, which lies on the tracks, was an early and vocal opponent of electrification. Residents opposed electrification and the proposed high-speed rail route because the overhead electrical lines would require tree removal and the town could potentially be divided in two by permanently closing the two grade crossings at Fair Oaks Lane and Watkins Avenue. In February 2015, shortly after the project received environmental clearance from the state, Atherton sued Caltrain, alleging the agency's environmental impact review was inadequate and that its collaboration with the CHSRA should be further vetted. In July 2015, the suit proceeded after Caltrain's request to the Surface Transportation Board to exempt it from California Environmental Quality Act (CEQA) guidelines was denied. Atherton reiterated its opposition to electrification on the basis that overhead wires would require removing a significant number of heritage trees, and city representatives asserted that "newer, cleaner, more efficient diesel trains" should supplant plans for "century-old catenary electrical line technology". Atherton mayor Rick De Golia was quoted as saying "Caltrain is locked into an old technology and 20th century thinking". After Caltrain issued infrastructure and rolling stock contracts in July 2016, Atherton representatives did not file a temporary restraining order to halt those contracts, preferring to let the suit proceed to a hearing. In September 2016, Contra Costa County Superior Court Judge Barry Goode sided with Caltrain, ruling that the electrification project did not hinge on the high-speed rail project's success, and was thus independent from the latter. Atherton sued CHSRA again in December 2016, stating that using bond money intended for high-speed rail for CalMod was a material change in usage and therefore was unconstitutional because such a change would require voter approval first. Mullin noted "this entire Caltrain corridor is the epicenter of the innovation economy and it's a job creation and economic engine. This electrification project, I would argue, is monumental with regard to dealing with [increased traffic and environmental impacts] effectively and efficiently." Parsons began physical work on CBOSS in September 2013, starting with the installation of a fiber optic line along the Caltrain right-of-way. The Federal Railroad Administration (FRA) approved Caltrain's plans in 2014 and Caltrain noted that CBOSS was due to enter revenue service by the end of 2015. Because Caltrain had multiple goals for CBOSS, including increased safety, improved operational efficiency, and ensured interoperability with other rail providers (Caltrain shares tracks with Union Pacific, Altamont Corridor Express, and Amtrak), The Peninsula Corridor Electrification Project (PCEP) draft environmental impact report was released in February 2014. After addressing comments received, PCJPB certified the final environmental impact report in January 2015. A pre-qualification survey was sent out in May 2014, and six firms were pre-qualified to bid on PCEP construction, which was eventually awarded to Balfour Beatty Construction. In July 2016, Caltrain's Board of Directors awarded contracts to Balfour Beatty and Stadler Rail to construct infrastructure for the electric trains and the electric trains themselves, respectively. Balfour Beatty was awarded a $697 million contract, its largest contract in the United States, to electrify the line at 25 kV AC, replace signaling systems, construct two traction power substations, one switching substation, and seven paralleling substations. The Swiss firm Stadler was awarded a $551 million contract to deliver 96 of their "KISS" bilevel electric multiple unit cars, formed into 16 six-car trains. Under the contract, Caltrain holds an option to increase the order with an additional 96 cars in the future. The contract also marks the first American design win for the Stadler KISS. The first trains are scheduled for delivery in August 2019. In April 2016, after missing the initial October 2015 deadline, Caltrain requested a third party review of the CBOSS project from the American Public Transportation Association (APTA). APTA noted that Caltrain was not effectively managing the project schedule and cost because of generally poor communication between Caltrain's project management and Parsons, and Caltrain's project manager did not have the technical experience or authority to resolve technical and contractual issues with Parsons. In February 2017, Caltrain terminated its contract with Parsons for failure to perform on time and budget and announced potential litigation. Parsons filed suit on February 22, saying delays were due to changing client requirements and circumstances beyond their control. Caltrain filed suit a week later, seeking $98 million in damages; although the system has been mostly installed, testing is still incomplete. The plan to complete the installation of positive train control (PTC) was presented to PCJPB in early 2018. At the March 1, 2018 meeting, the PCJPB awarded the $49.5 million contract to complete PTC to Wabtec. The switch to Wabtec implements I-ETMS technology, which was evaluated to be "the only technically and financially viable" solution to completing PTC before the FRA's deadline of December 31, 2018. Approximately 80% of the equipment for CBOSS that had already been installed was able to be reused, and FRA approved a revised schedule in January 2019 to implement PTC by December 2020. By February 2017, the electrification project had secured $1.3 billion in state, local, and regional funding, with the remaining funding gap to be closed by a $647 million grant from the FTA's Core Capacity program. The grant had undergone a two-year review process starting in November 2015 under the Obama Administration and received a "medium-high" rating from the FTA in August 2016, However, during the review period, the fourteen Republican party U.S. House representatives from California sent a letter to Secretary Chao, urging her to deny funding due to the project's ties with high-speed rail, which they opposed. The letter went on to call the project "an irresponsible use of taxpayer dollars". The Sacramento Bee pointed out that despite regularly soliciting campaign funds from Silicon Valley business leaders, Representative and House Majority Leader Kevin McCarthy, the author of the Republican letter to Secretary Chao, was targeting a project that benefited the region directly. Another Republican signatory, Representative Devin Nunes, was unmoved by arguments on infrastructure benefits, saying in late February that he would not "feel too bad about one of the richest places on the planet not having a train." Fellow Republican Representative Jeff Denham defended the letter, saying Caltrain's electrification project and CHSRA were closely intertwined because the former derived some funding under the "blended plan" agreement. Representative Tom McClintock reiterated his opposition to high-speed rail without addressing Caltrain: "I have never supported a dollar of state funding going for [high-speed rail], and would never support a dollar of federal funding". Representative Mimi Walters also made a statement that she was not opposed to electrification, but instead held "serious concerns about the use of taxpayer funds for a project that is tied to high speed rail". The Democratic letter went on to note the infrastructure benefits of the project and the creation of 9,600 jobs, including 550 jobs at a new Stadler USA plant in Salt Lake City. In the end, Secretary Chao heeded the Republican letter's arguments, and deferred the grant in a letter written by FTA Executive Director Matthew Welbes to Caltrain which stated the FTA needed "additional time to complete review of this significant commitment of Federal resources". Caltrain had expected Secretary Chao to approve the grant and sign the grant agreement by March 1, which is normally a pro forma step performed after the thirty-day comment period for a highly rated project, and had already awarded construction contracts. Balfour Beatty Construction and Stadler Rail had already begun preparations to upgrade the existing tracks and build electrical trainsets, respectively. Caltrain negotiated an emergency four-month contract extension at a potential cost of $20 million. Under the preliminary budget proposal released in mid-March 2017, the United States Department of Transportation's Capital Investment Grant Program would be eliminated, although approved projects would continue to be funded. the East Bay Times, a noted CHSRA detractor, and The New York Times, which called the delay "counter to Mr. Trump's campaign promises of increased infrastructure spending." Henry Grabar noted the grant deferral could be "an early test of a simmering fear that the state's outspoken political opposition to the Trump administration might come with a price". San Jose Mayor Sam Liccardo met with Department of Transportation officials, urging them to upgrade a system that "was built under the presidency of Abraham Lincoln". Additionally, more than 120 Silicon Valley business leaders sent a letter to Secretary Chao, asking her to explain "the last-minute attempt to derail two decades of work". and subsequently met with Secretary Chao and Representative McCarthy, urging them to reconsider the funding deferral, saying afterward that he was "cautiously optimistic" that the money would be released. On April 30, legislators in the U.S. Congress released the proposed 2017 federal budget, which included partial funding for the electrification project, but restricts its distribution unless Secretary Chao signs off on the grant. The proposed budget includes $100 million of the $647 million grant, with the balance expected in future years. Secretary Chao claimed she could not sign the grant without the full grant being budgeted, which was disputed by Caltrain and both California Senators Dianne Feinstein and Kamala Harris. On May 22, the FTA announced its intent to sign the funding grant, restoring the final piece of funding for the electrification project. The official grant was finally signed on May 23. Construction and testing A new weekday schedule designed to allow time for construction became effective on April 10, 2017. The weekend schedule was revised on July 15, 2017, which decreased frequency from 60 minutes to 90 minutes between trains and eliminated eight trains per weekend day. , Cal. Sen. Scott Wiener, San Francisco Mayor Ed Lee, Gov. Jerry Brown, and Rep. Nancy Pelosi at the July 21, 2017 groundbreaking ceremony An official groundbreaking ceremony was held on July 21, 2017, at the Millbrae station. , 149 poles had been erected in San Bruno and South San Francisco. In December 2018, Caltrain was carrying 65,000 passengers a day, and expected to carry four times that amount by 2040. Accordingly, Caltrain announced plans to increase its electric train order by a third. After funding was received from the California State Transportation Agency's Transit and Intercity Rail Capital Program, Caltrain's board unanimously approved the purchase of additional cars from Stadler to increase the fleet from 16 six-car sets to 19 seven-car sets. Balfour Beatty reported in 2019 the completion of construction could be delayed to April 2022 in a report to the San Francisco County Transportation Authority (SFCTA); the projected 12-month delay was blamed on the unexpected presence of underground utilities. In June 2021, Caltrain announced that electric service would be delayed to late 2024 due to supply chain disruptions during the COVID-19 pandemic, issues with the signal system, and "unforeseen conditions under Caltrain's tracks". In February 2022, the last foundation required for the new overhead catenary system was completed, with the entire line planned to be energised by summer 2022. Testing of the line would then begin using an AEM-7 electric locomotive, with revenue service planned for 2024. To expedite construction, the weekday train schedule was reduced and fewer stops were planned north of Hillsdale temporarily in the second half of March 2022. However, construction was suspended temporarily that month after a southbound train collided with work equipment at milepost 11.6 in San Bruno on Thursday, March 10. The train came to rest near San Felipe Avenue, and spilled fuel caused a fire, which damaged the tracks, locomotive, and passenger car. The work crew had contacted the train dispatcher at 9:50 a.m. (local) to establish exclusive occupancy on track 2 for the three hi-rail work vehicles, then released the exclusive occupancy at 9:58; the collision occurred at 10:33. According to the locomotive's event data recorder, the last recorded speed of the southbound train was , but the engineer had pulled the emergency brake upon sighting the work vehicles. The reduced schedule was implemented again starting in May to accommodate construction activities in San Mateo and Burlingame. Clearance testing of the first electric trainset on the Caltrain corridor began in July 2022. The southern Traction Power Substation was energized that August. Initial testing of the overhead catenary system and trains began along the Santa Clara Drill Track in June 2023, between the Santa Clara and College Park stations. The electrification of the line was completed in April 2024. Caltrain Board Chair Dev Davis, Governor Gavin Newsom, Federal Railroad Administration chair Amit Bose, U.S. Senator Alex Padilla, U.S. Representatives Nancy Pelosi, Kevin Mullin and Anna Eshoo, California State Transportation Agency chief Toks Omishakin, noted transit advocates and state legislators Phil Ting and Scott Wiener, and the mayors of San Francisco and San Jose, London Breed and Matt Mahan, respectively, were among the passengers. Revenue service began the next day, and was scheduled to ramp up to its highest frequency by September 21. On that date, Caltrain held a celebration to mark the launch of the new schedule, and offered free rides throughout the day. Trip times were shortened thanks to the faster acceleration of the new electric multiple-unit trains. A scheduled local train trip from San Jose Tamien to San Francisco 4th and King was shortened from 115 minutes with a diesel train to 83 minutes with electric service, an improvement of 32 minutes. Electric express trains improved trip times despite adding more stops - a 7-stop diesel express train from San Jose Diridon to San Francisco 4th and King was scheduled at 66 minutes, while a 10-stop electric express train went down to 59 minutes despite making more stops. Environmental effects Replacing the diesel locomotives with electric multiple units was expected to reduce air pollution and noise. A UC Berkeley study conducted in 2024, before and after complete electrification of San Francisco to San Jose service, found substantial reduction in black carbon particulates, a major component of diesel exhaust. Black carbon measurements onboard trains fell by an average of 89% after electrification. The study estimated that this reduction in diesel particulate exposure would reduce excess cancer risk by 51 cases per million people among daily train commuters, and 330 cases per million people among train conductors. Ambient black carbon particulate measurements at the station platform and concourse at 4th and King station fell significantly, by as much as 1.9 micrograms per cubic meter - reductions equivalent in magnitude to what took three decades of environmental intervention to achieve in California at the end of the 20th century. The reduced air pollution is expected to improve the health of El Palo Alto, a coastal redwood tree and historical landmark which stands about away from the Caltrain tracks and lends its name to Palo Alto. Coal soot and diesel exhaust are presumed to have killed parts of the tree's crown since the 19th century. The lack of exhaust emissions will benefit air quality throughout the railway corridor, and the new units are significantly quieter than the previous stock. However, the lower noise levels have resulted in Caltrain warning the public to take extra care at crossings. The new electric trains are more efficient than originally expected. Electricity costs were originally expected at $19.5 million per year, but were revised down to $16.5 million after several months of service, and later to $15.3 million. After $6 million in state energy credits, the first year of electric service will have lower costs than the previous diesel service. Approximately 23% of the electricity consumed by trains is recaptured and returned to the grid thanks to regenerative braking. Caltrain was originally not compensated for energy returned to the grid, but successful negotiations with utilities in October 2025 results in an estimated $1 million per year compensation for returned energy. ==Funding==
Funding
Funding for the originally-$1.9 billion project comes from a mix of funds contributed by the California Department of Transportation, California High-Speed Rail Authority, California cap and trade revenue, Bay Area Air Quality Management District, Metropolitan Transportation Commission, the city and county of San Francisco, SamTrans, and Santa Clara Valley Transportation Authority. 32% of the funding, or $647 million, will come from Federal Transit Administration's Core Capacity grant, with the funding agreement approved on May 22, 2017, after a three-month delay. An additional $600 million comes from Proposition 1A funds that authorized the construction of high-speed rail, $113 million from cap and trade revenue, and the rest coming from local and regional sources. The delays announced in June 2021 will add $333 million to the cost for a total of $2.3 billion. Of the increase, $161 million is known and allocated costs with a funding plan, while $172 million is unallocated costs. ==Design==
Design
The Peninsula Corridor Electrification Project (PCEP) electrified the entire right-of-way owned by the Peninsula Corridor Joint Powers Board (PCJPB), which extends from the San Francisco terminus at 4th and King to a power substation south of Tamien Station. New electrical infrastructure includes installation of approximately of 25 kV 60 Hz single-phase AC overhead contact lines and ten new power stations (two traction power stations, a switching station approximately halfway along the line, and seven paralleling stations). Land totaling was acquired from private property owners along the Peninsula Corridor in order to set up safety buffer zones between the overhead contact system and public property; PCJPB authorized eminent domain proceedings in July 2017 in case negotiations broke down. Barriers were installed where road and pedestrian bridges cross over tracks to prevent damage to the electrical wires. New electric trainsets were purchased for use on the new electrified segment, while service from Tamien to Gilroy, which is not planned to be electrified due to ownership by Union Pacific Railroad instead, continue to be served with existing diesel locomotives. The second part of the CalMod project is a positive train control system, "CBOSS" (Communications Based Overlay Signal System), which is designed to meet federal safety requirements and as a condition set by the FRA to allow mixed traffic on the corridor. Key decisions in the development of CalMod can be traced back to the 1992 Feasibility Study, which recommended 25 kV AC overhead lines; the 2009 FRA waiver, which imposed certain conditions on mixed traffic; and the 2012 memorandum of understanding with CHSRA, which resulted in a "blended" system to use the existing twin-track line as much as possible. The 2012 Blended Operations report concluded a new quad-track overtake section would allow Caltrain and CHSRA to coexist on the Peninsula Corridor with up to ten trains per peak hour: six Caltrain and four high-speed rail trains. Peak load on the system assuming twelve eight-EMU consists in each direction per hour was estimated to be approximately 75 MW, with the load generally remaining under 40-50 MW at any point. According to Caltrain, the electrification project will bring multiple benefits to the corridor. Firstly, electric trains can accelerate and decelerate more quickly than the existing diesel locomotives, resulting in faster and more frequent service. They will also replace Caltrain's current diesel locomotives and passenger cars, a significant portion of which are nearing the end of their lives. Additionally, electric trainsets are quieter and produce less air pollution than diesel locomotives, and the use of electric trains will lower Caltrain's fuel costs while increasing passenger revenue, due to an expected increase in ridership. Once complete, Caltrain expects to annually reduce carbon dioxide emissions by 176,000 metric tons and increase daily ridership by 21% by 2040. Restoring daily service to Atherton and Broadway stations was considered, although with the permanent closure of Atherton station, only Broadway station will receive restored daily service. Under the original schedule, Caltrain planned to complete the project by the end of 2021. The feeder wire is electrified at the same voltage and frequency, but is shifted 180° out of phase so the voltage difference between the contact wire and the feeder wire is always 50kV. The choice of a 2×25 kV autotransformer system means more traction power facilities are required in total, but also requires fewer traction power substations. Based on resident objections to the new site, however, the City of Burlingame offered an alternative site east of the tracks at 1369 North Carolan adjacent to the city-owned Corporation Yard. Construction plans The PCJPB-owned right-of-way has been divided into four construction segments. From the north, the segments are arranged as: • , , • (, ); (, , ); (, , ); (, ); (, ) • , , , , , , , • (, , , ) Segments are further divided into work areas, indicated by brackets in the list above. Work began in Segments 2 and 4 and proceeded from north to south within each segment before moving on to Segments 1 and 3. The first work area was in the cities of South San Francisco and San Bruno. In Atherton, 18 trees were planned to be removed with an additional 63 trees pruned more than 25%. 83 trees would be replaced as a result, per the Atherton Tree Replacement Plan. Atherton residents objected to the plans in November 2017, stating the five planned double-cantilever side poles (spanning both tracks from one side) were taller than expected, and asked PCJPB to redesign the OCS support to use ten shorter single-cantilever side poles (spanning one track each). In their response, PCJPB stated it would cost an additional $200,000 to redesign and would require more extensive tree removal; a later response asked that Atherton pay the difference and indemnify Caltrain from further lawsuits related to PCEP, which Atherton rejected. Specific modifications The Santa Clara Drill track, an existing maintenance track approximately long from CEMOF to Santa Clara station, was converted to an electrified test track. Testing is anticipated to take place during the daytime between late 2019 and spring 2022. The rehabilitation of Santa Clara Drill track began in February 2018. In April 2019, the anticipated completion date for the test track was in May 2020, with testing scheduled to start in late 2021. By January 2024, three trains had successfully completed over of test runs, and six trains had been delivered. The four tunnels originally constructed for the Bayshore Cutoff were modified to accommodate overhead wires. The tunnel notching work was performed during weekends, so service between Bayshore and 4th and King was replaced by buses starting on October 6, 2018, with a planned "late Spring 2019" resumption. CEMOF was modified to accommodate the new EMUs. An existing inspection pit was extended by , allowing work over the entire length of a seven-car EMU train. In addition, a rolling maintenance platform was added to the building to allow work on the top of the train cars, and a permanent tent was erected for parts storage. FRA waiver and I-ETMS PTC belonging to Luxembourg's CFL are not allowed to share rail lines with heavy freight trains.|alt=An image of a Stadler "KISS" electric train. As a result of the blended plan, PCJPB mandated that Peninsula Corridor infrastructure and equipment should be compatible with future California High-Speed Rail Authority (CHSRA) trains. CHSRA had proposed that mandated speeds and transit times could be met by using lighter-weight vehicles that did not comply with Federal requirements. and structural strength. Caltrain saw this as an opportunity to apply for an FRA waiver to run lighter-weight EMUs, which could accelerate faster and provide headways as low as five minutes. The December 2009 FRA waiver application detailed Caltrain's plans to prevent collisions: first, reduce the probability of collisions to nearly zero by employing temporal and spatial separation from freight rail and restricting freight traffic to the non-revenue hours, then mitigate the impact of a collision by deploying vehicles with crash energy management (CEM) structures, and then deployment of an enhanced positive train control system, designed to check for speeding trains and protect rail workers. Positive train control became a Federal mandate with the passing of the Rail Safety Improvement Act of 2008. The grant was conditioned on meeting nine additional requirements, including demonstrating minimum crashworthiness, seating, improving grade crossing, meeting FRA positive train control standards in Title 49 of the Code of Federal Regulations, part 236 with CBOSS, formalizing the temporal separation plan, and issuing a safety system program. Originally, Caltrain employed Parsons Transportation to develop a custom PTC system, called CBOSS, for CalMod, but due to delays, Caltrain switched to Wabtec and their I-ETMS system. Caltrain announced the Federal Railroad Administration had certified its PTC implementation in December 2020. Rolling stock ;Notes Stadler EMU The Stadler KISS double-decker EMU that Caltrain ordered are compliant with the FRA alternative Tier-I crash-worthiness standard. Under the alternative standard, it has Crash Energy Management (CEM) features which allow parts of the EMU to collapse whilst keeping the passenger seating area intact in the event of collision, instead of relying on pure structural strength as in the traditional Tier-I standard. The implementation of the alternative Tier-I standard results in a lighter train that will save energy and track maintenance cost. Coupled with the positive train control system that is being installed on the Caltrain line, Caltrain KISS trains will be allowed to operate in mixed traffic with heavier trains, such as Amtrak passenger trains and Union Pacific freight trains, instead of the temporal separation required in the 2009 waiver. Because the existing Caltrain platforms are at a different height compared to proposed high-speed rail vehicles, the EMU trains will be equipped with doors at two heights, at and above-top-of-rail, allowing Caltrain to eventually transition from the existing low platforms to CHSRA-compatible high platforms, enabling unassisted boarding of all passengers as specified by the Americans with Disabilities Act of 1990. The updated EMU consist configuration, according to Stadler brochures released in 2021 and 2023, adds a seventh car, which is a passenger trailer with two powered trucks, giving the EMU a total of eight powered trucks. , an option has been exercised to expand the order to 133 cars using Transit and Intercity Rail Capital Program funding, to be delivered as 19 trainsets, each consisting of 7 railcars. The first seven-car trainset was moved to Stadler's onsite test track in Salt Lake City for static testing in May 2020; it was completed in July 2020 and began low-speed initial type testing in November 2020. It was shipped to the Transportation Technology Center in Pueblo, Colorado for dynamic type testing in February 2021, and arrived in March 2021. At the same time, one car was sent to Elmira, New York for environmental testing. Two trainsets were displayed at the 4th and King station during a ceremony attended by politicians on September 24, 2022. In August 2023, Caltrain exercised an option to order four additional seven-car EMU trainsets ($220 million) and a single four-car battery electric multiple unit (BEMU) trainset ($80 million). This will result in a fleet of 23 EMU trainsets, six diesel-hauled trainsets, and one BEMU trainset by 2030, with over 90% of service using electric trains. The BEMU trainset will be used on the non-electrified portion of the corridor between San Jose and Gilroy. EMD AEM-7AC Since Amtrak has replaced its fleet of EMD AEM-7 locomotives with Siemens ACS-64, PCJPB entered discussions to purchase retired AEM-7s to test the electrification system and to serve as reserve locomotives in the event of EMU unavailability. Because of the delay in delivering ACS-64s, the target sale date for the AEM-7s was moved out to June 2016. Although procuring an ACS-64 for testing was considered, Siemens stated no locomotives were available for lease, and the cost to purchase a new ACS-64 exceeded the budget allowance for testing. By October 2017, the work in progress had identified two vendors: Mitsui for purchase, and Amtrak for refurbishment; in January 2018, contracts were ready to be awarded to those vendors. Mitsui owns several ex-Amtrak AEM-7 locomotives. On June 7, 2018, Caltrain staff recommended that two contracts be awarded for a total of approximately $610,000: one to purchase two AEM-7ACs from Mitsui & Co, and the other to Amtrak for refurbishment, training, and transportation to the Caltrain Centralized Equipment Maintenance and Operations Facility (CEMOF), which passed unanimously. The AEM-7AC locomotives were scheduled to arrive in February 2019, but were still at Amtrak's Ivy City facility (near Washington D.C.) in April 2019 and did not arrive in California until June 28. They were moved to CEMOF in early August and by September, were being stored at the San Francisco Rail Yard. After testing is completed, the used locomotives will be disposed. ==Footnotes==
tickerdossier.comtickerdossier.substack.com