Pre-Construction The Drakelow power stations were built on the site of Drakelow Hall, a stately home on the south bank of the River Trent. Twenty eight generations of the
Gresley family had considered the estate as their ancestral home. It had appeared in the
Domesday Book and the family could trace its history back to the time of the
Norse Vikings. A book that was published in 1899, "
The Gresleys of Drakelowe", is the accepted history of the family. The hall was demolished in 1934 and its site then earmarked for development in the early 1940s. The remains of the
Elizabethan hall occupied part of the site even after the power station was built. The site was chosen for the construction of a power station because it was around in size and was in close proximity to the River Trent as well as the main
Leicester to Burton railway to the north, the Burton to Tamworth road to the south-east, and was close to the
East Midlands coalfields. The £23 million project was considered a great technological advancement in its day. Rapid progress was being made with the development of larger
boilers and
generator units. Drakelow A Power Station was commissioned in 1955 and had 2 × 60 MW and 2 × 62 MW
English Electric turbo-alternators giving a total capacity of 240
megawatts (MW). Each turbine was fed from a Internal Combustion Ltd 515,000 lb/hr 1500 lb/sq inch boiler using pulverised fuel firing and six stages feed heating. Both the A and B stations were
brick built. The A station had two chimneys each at 360 ft high initially with two
cooling towers each 300 ft high. By the time of its opening, work had already started on its larger 480 MW sister Drakelow B.
Drakelow B The contract for site clearance and the main foundations was placed in January 1955 with work beginning in April 1955 and the first unit commissioned in April 1959 and final unit in 1960. There were four single-drum reheat boilers with a maximum continuous evaporative capacity of 860,000 lb/hr one from
International Combustion Ltd and three from
Foster Wheeler Ltd feeding four 120 MW
C.A. Parsons turbo alternators. The turbines are of the three-cylinder (High, Intermediate & Low) impulse reaction type running at 3,000 r.p.m. after passing through the high pressure cylinder the steam is returned to the boiler for reheating before entering the intermediate cylinder. The steam conditions at the turbine stop valve were 1,500 psi. at 1,000°F, with single stage reheating to 1,005°F at 367 psi at the reheater outlet and a final feed temperature of 435°F at the economiser inlet. Like the “A” station, the “B” station has two brick chimneys 400 ft high and two ferroconcrete cooling towers, each 307 ft high and with throat diameters of 132 ft. These towers are used in common with the “A” station. All coal is delivered to site by rail at an average rate of 5,600 tons/day. Three side discharge tipplers unload the coal, which can then be taken either directly to the boiler bunkers by 1,000 ton/hr belt conveyors or to the 540,000 ton capacity store area. It was officially opened on Friday 21 October 1955 by Mr J Eccles, the deputy chairman of the Central Electricity Authority. It was the first of its kind.
Drakelow C The third, final and largest stage of the build was then underway with the construction of Drakelow C Power Station. Work began in 1960, and the station beginning generating in 1964. With six larger, cooling towers, two chimneys and two 350MW and two 375MW generators (the CEGB Statistical Yearbook 1980-81 says there were two 326 MW and one 325 MW generators), The cooling towers were arranged in two groups of three, and one tower in each group was coloured a warm red to bring them visually forward, as had been done at West Burton power station. The total generation capacity was 2170 MW over the three stations, making it the largest electricity generation site in Europe for a time. ==Operations==