Sep 2015: Construction work of expressway divided by NHAI into 6 packages and awarded to 5 private firms. •
Nov 2015: Foundation stone of 135-km long expressway laid by
PM of India Narendra Modi. •
Feb 2016: Construction work started on expressway. •
Apr 2017: An estimated 60% of the work has been completed. It is expected to be completed by August 2017. •
Jul 2017: Around 70% of the work has been completed. It is expected to be completed by March 2018, 3 months ahead of the deadline of July 2018 set by the
Supreme Court of India. •
Oct 2017: Few farmers agitating against land acquisition in Greater Noida area and who forced stop the road construction work were arrested in Sep 2017 and police force are deployed to give cover to road workers so that work can proceed. •
Dec 2017: 85% work completed. Land acquisition related issue is there at two places in
Greater Noida impacting length of about 1 kilometre each, which delayed the project completion. •
Apr 2018: The expressway was scheduled to be inaugurated by Indian Prime Minister Narendra Modi on 29 April 2018 but was cancelled due to
elections in Karnataka. •
May 2018: The
Supreme Court of India has directed the
National Highways Authority of India (NHAI) to open the expressway before 31 May 2018. •
May 2018: KGP Expressway is inaugurated by PM
Narendra Modi in
Baghpat on 27 May 2018. ==See also==