The British Aluminium Company identified Foyers as a possible site to build a hydropower scheme to produce electricity for an aluminium smelter. The scheme takes water from the River Foyers above the Falls of Foyers, it is diverted via a tunnel and cast iron penstocks to the generating station and smelter located on the shore of Loch Ness. The power station originally had five Girard turbines on vertical shafts with Oerlikon direct current generators To provide a more continuous flow of water, a reservoir was constructed upstream of the intake. This combined Loch Garth and Loch Faraline just upstream, into a new reservoir named
Loch Mhòr, raising the water level of Loch Faraline by . A bathymetrical survey in 1903 noted that in the summer, the reservoir level may drop back to the original level. The company identified the Falls of Foyers as a possible site, and bought the Lower Foyers estate, covering some , together with water rights from neighbouring areas. This allowed them to create a hydro-electric scheme without needing to obtain Parliamentary approval, and to ignore public opposition to the effects it would have on local amenities. The River Foyers ran through a gorge to the almost vertical Lower Falls, which was a beauty spot, and was a stopping point for tourists using the MacBrayne pleasure steamers running along the
Caledonian Canal from
Fort William to
Inverness.
Construction Construction began in 1895. Loch Garth was modified by a concrete and masonry dam at its south-western end, together with an earth embankment. The concrete section is long and around tall, or possibly long and around tall. The dam raised the water level of Loch Garth by , resulting in it joining Loch Farraline, and the combined storage reservoir, which was long, was renamed
Loch Mhòr. Water from the reservoir was conveyed along the original course of the River Foyers to the top of the Upper Falls of Foyers. From there a tunnel was cut through solid rock for and the water continued through cast iron pipes to the generating station. The pipes were in diameter, and were laid in a trench, to be covered with sand. This provided a head of to the turbines, and although there was some debate as to whether cast iron pipes could withstand such pressure, no issues were experienced. The water drove five Girard turbines connected to Oerlikon direct current generators, which could produce a total of 3.75 MW.
Aluminium smelting Aluminium was first recognised in the early 1800s, and processes for extracting it from
Bauxite ore were developed during the nineteenth century. The most promising was the Heroult-Hall process, separately developed by P T L Heroult in France and C M Hall in America in 1886-1887, but it required large amounts of electricity. The rights to using the process in Britain were obtained by the British Aluminium Company, which was formed in 1894. To produce a ton of aluminium required around 24 MWh of power, and the idea of obtaining cheap hydro-electricity to produce it was suggested. The electricity from the hydropower was more than sufficient for the production of aluminium, and some 200 tons per year were produced from June 1896. It was a new product, and with production exceeding demand, the power was also used to produce calcium carbide, and experiments were carried out to manufacture ferro-silicon, carborundum, cerium, magnesium, and precious stones. The plant at Foyers steadily improved in efficiency, as the Heroult-Hall process was refined, and by 1904, world demand for aluminium had increased sufficiently that production of calcium carbide ceased, and the plant only produced aluminium. However, larger plants built subsequently at Kinlochleven and Fort William were more efficient, and from 1954, the plant was used to refine aluminium produced at those sites, by remelting it and removing impurities, to produce "super purity" aluminium. This eventually became uneconomic, and the plant shut in 1967. The Girard vertical shaft Pelton wheels, which had been installed in 1896 to provide power at 65 volts and 8000 amps, were used until the plant closed.
Acquisition by the Hydro Board (later SSE) The site was acquired by the
North of Scotland Hydro Electric Board soon after the aluminium plant closed in 1967. The Girard turbines were replaced by a single 5 MW turbine and generator located in the main building. , this continues to operate, although now owned by SSE, generating around 8 million units (GWh) per year. == Foyers pumped storage scheme ==