The building of Flaming Gorge Dam started just a few months after the CRSP was approved in Congress, when
President Dwight D. Eisenhower pressed a button on his desk in the
White House and set off the first blast in Red Canyon. Site preparations and geologic inspections continued as
Dutch John, the
company town that provided housing for the workers, was completed just northeast of the dam site by 1958. More than 3000 people would inhabit Dutch John at the peak of construction. The main contract for dam construction was awarded to Arch Dam Constructors, a conglomerate of
Peter Kiewit Sons,
Morrison-Knudsen Company, Mid-Valley Utility Constructors Inc. and Coker Construction Company. Actual construction at the dam site did not begin until late 1958 when work began on the diversion tunnel that would send the Green River around the dam site in order to clear it. By April 1959, excavation of the diversion tunnel had been completed, and the concrete lining was finished on August 17. Work on a pair of earthen cofferdams above and below the dam site commenced when the tunnel was ready, and the river was channeled around the dam site on November 19 with the completion of the upper cofferdam. Keyway (foundation) excavations for the dam on the right abutment and construction of the spillway inlet works in the left abutment were begun in September, and all preliminary canyon wall structures were completed by early 1960. The lower cofferdam was finished in February, allowing workers to pump water from the space between the two barriers. The silt and sediment that comprised the riverbed had to be removed in order to reach a solid rock where foundations could be drilled; this was completed in August 1960, allowing work on the main dam foundations to begin. Flaming Gorge was built in block-shaped stages of concrete called "forms". The first concrete for the powerhouse was placed on September 8, and construction of the main dam wall began ten days later. In order to accelerate hardening of the concrete, cold water was pumped through metal tubing, or "coils", embedded in the structure. Concrete placement continued until November 15, 1962, when workers topped out the dam. By the end of 1962, both the river
outlet works and the spillway tunnel were completed, and the diversion tunnel was closed, allowing water to begin rising behind the dam. The dam's hydroelectric generators were installed by mid–August 1963 and the first unit went into operation on September 27 at the press of a switch by President
John F. Kennedy. The dam was officially dedicated by
Lady Bird Johnson on August 17 of the following year. ==Dimensions and operations==