Orders •
First Tejas Mk1 contract (total 20 jets): •
31 March 2006 — Indian Government on behalf of the Indian Air Force placed an initial order for 20 LCA Tejas, from HAL, for delivery by December 2011. The order comprised 4 twin seat trainers, and 16 single seat Tejas IOC II. •
September 2024 — The delivery, scheduled for completion in 2011, was finally completed. •
Second Tejas Mk1 contract (total 20 jets): •
23 December 2010 — Indian Government ordered 20 additional LCA Tejas, comprising 4 twin seat trainers, and 16 single seat Tejas FOC bringing the total aircraft to 40. It was to be delivered by December 2016. •
10 January 2025 — 38 of the 40 aircraft have been delivered and the last two trainers would be delivered soon. •
First Tejas Mk 1A 2021 contract (total 83 jets): •
August 2018 — The Defence Acquisition Council accorded Acceptance of Necessity for procurement of 73 Tejas Mk 1A aircraft with
active electronically scanned array radar,
beyond-visual-range missile, self-protection jammer, and
aerial refueling capabilities. The rest of 10 trainer aircraft would be of Tejas Mk1 standard. •
13 January 2021 —
Cabinet Committee on Security cleared the procurement of 73 single seater Tejas Mk 1A and 10 twin seater trainer Tejas Mk1 at the cost of with additional funds for Design & Development and Infrastructure worth . •
3 February 2021 —
Ministry of Defence signed the contract with HAL on the inaugural day of
Aero India 2021 at a cost of almost . •
17 August 2021 — HAL signed a contract with GE worth to supply 99 F404 engines and service support by 2029. •
Second Tejas Mk 1A contract (total 97 jets): •
16 September 2023 —
Air Chief Marshal VR Chaudhari stated that the IAF has decided to order 97 more Mark 1A fighter jets including 29 Tejas Mk 1A standard trainer jets. •
12 April 2024 — MoD issued tender to HAL for 97 Tejas Mark 1A fighter jets. Clearance for the deal expected to be received from
CCS in December 2024 and deal to be signed by year-end. •
August 2025 — Negotiations for additional F404 engines is expected to be completed this month, while the contract for 97 Tejas Mark 1A was cleared by the CCS on 19 August 2025 for . •
25 September 2025 — The agreement was signed one day prior to the
retirement of MiG-21 on September 26 and was valued at . Along with related equipment, the 97 jets would consist of 29 twin-seaters and 68 fighters. The delivery is expected to start in 2027–2028 and conclude in the next six years. In comparison to the 2021 deal, this order will include 67 additional items and more than 64% indigenous content. These jets will incorporate control surface
actuators,
Swayam Raksha Kavach EW Suite, and
Uttam AESA Radar. •
October 2025 — HAL is expected to place an additional order for 113 F404 engines worth $1 billion this month. The contract signing was earlier expected in September. •
7 November 2025 — A contract for 113 F404 engines and the related support package, valued at about , was signed. Delivery are scheduled to start in 2027 and will conclude by 2032. •
Delivery schedule — As per a report by
Moneycontrol on 19 November 2025, the first batch of eight Mark 1A aircraft is expected to be delivered within the next 24–36 months. Additionally, HAL plans to deliver three major
tranche of 24 aircraft to be delivered following months 37, 49 and 61 with the final batch of 12 aircraft to be delivered between month 73 and 84. Hence, the delivery timeline is expected to end in late 2032.
Production lines •
Bengaluru Plant I: HAL's first Tejas production line is situated at
Bangalore near
HAL Airport. The production line was set up at a cost of , with HAL holding 50% stake and the rest held by IAF and Navy. First serial production aircraft delivered in 2015 with production rate of 8 per year. •
Bengaluru Plant II: In March 2017, Government of India sanctioned for setting up an additional production line under Aircraft Division, HAL. This would increase the production capacity from 8 to 16. Production of sub-components like Front Fuselage, Centre Fuselage, Rear Fuselage, Wings were outsourced to private partners. with the first example then expected by the end of April 2025. The first Tejas Mk 1A took its first flight on 17 October 2024 after being inaugurated by the Defence Minister, Rajnath Singh. • The facility is spread on and employs 30 structural assembly jigs for all major aircraft modules like the centre fuselage, front fuselage, rear fuselage, wings and air intake. The facility outsources 40% of its workshare to private firms and plans to enhance annual aircraft output to 10 in two years. •
Nashik Plant II: HAL also plans to setup another production line at Nashik to ramp up production capacity from 24 to 32 as reported on 10 January 2025. The line can start production within one and a half years of sanction. The establishment of the plant is subject to a regular supply of GE engines.
Delivery Mark 1 contracts On 1 October 2014, LCA-SP1 aircraft took the first flight. On 17 January 2015 the aircraft was delivered to the Indian Air Force. Left head till then flow on 5 sorties to test various equipment. Due to delays in production the cost per aircraft rose from in 2006 to in 2015. However, the aircraft was not inducted into a squadron till 2016 until sufficient numbers were delivered by HAL. The aircraft would also require additional flight hours before induction. Expected delivery timeline was as follows: SP-2 in March, up to SP-5 by June, up to SP-8 by March 2016; completing a total of 8 aircraft. When the first order was placed in 2006, it was expected that ADA would receive Initial Operational Clearance (IOC) by 2008. Induction was scheduled by December 2011. However, IOC was originally received in December 2013 and the first IOC variant was delivered in FY2016-17. The first front fuselage of Tejas Mk1 FOC aircraft for the second order was delivered by Dynamatic Technologies on 2 November 2020. By August 2023, the delivery of all 32 single-seat Tejas Mk 1 aircraft (IOC and FOC) were completed. IAF has received first LCA Tejas twin seater aircraft from HAL on 4 October 2023. Next trainer variant delivery expected by 31 March. As of 18 September 2024, 4 trainer aircraft have been delivered to IAF while the rest of 4 are to be delivered by March 2025. As of 5 February 2025, the final two trainer aircraft remains undelivered since they are yet to meet the Air Service Qualitative Requirements (ASQRs) of the IAF. In December 2023, it was reported that the IAF has plans to raise the first squadron of Tejas Mark 1A at
Nal Air Force Station. Later in June 2024, it was confirmed that
No. 3 Squadron and
No. 23 Squadron would be the first units to operate the Mk 1A variant replacing their in-service
MiG 21s. The delivery of the first aircraft itself was shifted to the end of March 2024. By then, the IAF's latest requests for software upgrades and minor design changes caused the delay in delivery timeline, according to sources within the military and defence establishment. Also, a number of certifications were pending. The delivery of essential components that were ordered from Israel, Russia and Ukraine have also been delayed due to the
Russian invasion of Ukraine. All of which is impacting the production and delivery schedule. In May 2024, the
MoD asked HAL in May to deliver at least 18 Tejas Mk 1A by March 2025 and the entire 180 jets (including later 97 Tejas Mk 1A order) within 10 years. Subsequently, the delivery dates were shifted several times from February 2024 to July-end (as of May), to 15 August (as of July) and again to November (as of August). In August, the first aircraft was undergoing critical flight tests with weapons trials to be expected soon while the second was in high speed taxi trials phase. The next 4 units were in advanced stages of production. HAL then planned to manufacture at least 14 airframes in "ready-to-go state" by the
fiscal year in order to ensure swift engine integration and aircraft deliveries within few weeks after arrival of new engines. The same month, a report suggested that the fighter aircraft's Israeli software integration being finished and is undergoing final trials and deliveries could begin from October 2024. The delivery could begin with Category B engines, referring to the engines previously used or procured from GE. The F404-IN20 engine delivery had been shifted to arrive in November 2024. There was an additional problem for the delivery.
General Electric had closed down the production line of F404-IN20 at
Lynn, Massachusetts engines earlier without further prospects of orders from India and the first engine was yet to be delivered even in October 2024. First engine delivery dates were delayed to September 2024 as of then and followed by a production rate of two per month. By November, engine deliveries was delayed by 10 months. Engine deliveries were again shifted to April 2025 though uncertainties remained. The reason for delay was cited as supply chain issues since a South Korean firm with financial issues failed to deliver certain components of the engine. HAL had 5-6 aircraft ready for delivery. The Mk 1A is in the final stages of trials before delivery. Following the orders, a lengthy process of sorting out supply chain problems was undertaken and the F404 production line at
Boston restarted by late 2024 to enable deliveries after a stagnation of 5 years. As of 10 January 2025, GE had a backlog of 26 engines. Secretary of Defence Production Sanjeev Kumar stated during
Aero India's
2025 edition that Tejas' production line was stabilized, both with HAL and GE engines, and that Tejas' supply will follow the original plan starting in 2025–2026 when 16 to 24 jets would be delivered. On 9 March 2025, the first rear
fuselage for Tejas Mk 1A was delivered to HAL by Alpha Tocol Engineering Services. Also, 12 rear fuselages manufactured by HAL was also ready on production line. As of 16 March 2025, the first Tejas Mk 1A from the Nashik (Ozar) production line is expected to be rolled out in April. After a two-year delay from the anticipated timeframes, the first of 99 F404-IN20 engines was rolled out from GE's factory on 25 March 2025, signaling the start of deliveries. The engine will be further tested at the HAL plant when it arrives in India in April. HAL produced three aircraft in 2025, will receive twelve engines from GE, and plans to produce eleven more aircraft by the end of 2025. As of 30 March, Tejas Mk 1A was undergoing extra firing and EW trials. Also, the first Tejas Mk 1A is expected to be delivered from Nashik facility in the first quarter of FY 2025–26 after the HAL gets physical possession of the first engine in India in early April. Tejas Mk 1A failed an Astra Mk1 trial during the trials. This was followed by the delivery of second centre fuselage on 4 September 2025. Each unit needs a total of 1,595 parts to be manufactured before they are assembled. HAL officials inspect every component at every stage of their production. The firm is scheduled to deliver a total of five fuselage units by year-end. As of June 2025, the first aircraft is now expected to be delivered by the end of the month from the Nashik plant. Further, HAL chief revealed that the company has six jets ready on the production line, all of which are to be delivered to IAF by March 2026. Also, 12 engines in addition to the one delivered so far are expected to be delivered by General Electric to HAL within the same timeframe while the latter also expects to deliver 16 jets in fiscal year 2026-27 given that there is a steady engine supply from GE. On 8 July, PK Mishra, principal secretary to the Prime Minister, visited the HAL's LCA Tejas Assembly Hangar and Aerospace Division to review the progress of the programme. Mishra was shown that six Tejas Mk 1A single-seat and two twin-seat trainer variants on the assembly line fitted with "some other test engines" which would be replaced by GE F404-IN20 engines when delivered. Additionally, the two new engines will reportedly arrive in the same month, as per reports. Meanwhile,
Defence Secretary Rajesh Kumar Singh also confirmed that GE will deliver two engines per month from July 2025 to March 2026. The next engine is to be delivered by the end of the month. While HAL has limited Category B engines, these available engines are being rotated among new aircraft to conduct test flights. On 13 July, it was reported that the second engine had been dispatched for delivery to HAL. The unit reached India on 14 July. Additionally,
Larsen & Toubro (L&T) completed the construction of the first pair of private sector-manufactured wings. Reportedly, the official delivery was undertaken with a ceremony on 17 July at Precision Engineering & Systems Complex of
Coimbatore,
Tamil Nadu. Meanwhile, the three sections of the fuselage have been already delivered by the respective private sector counterparts. With almost the entire aero structure produced by private sector companies, HAL will remain the final integrator and will ensure the assembly, testing, and certification of Tejas at its Final Assembly Lines at Nashik and Bangalore. As reported on 28 July, the aircraft were moving towards its "next phase" and is ready to "roll out". The testing of
Astra Mk1 BVRAAM is scheduled for early August 2025. On 11 August, the Directorate General of Aeronautical Quality Assurance (DGAQA) approved the flight clearance for the Tejas Mk 1A aircraft produced by HAL's Nashik division. The Additional Director General, AQA, also formally handed over the Flight Clearance Document to the executive director of the Nashik division. The Office of the Additional Director General (OADG), a field establishment of DGAQA, in Nashik was also responsible for the
Transfer of Technology of LCA Mk 1A to the Nashik division. As of 19 August, the first two of the jets were "fully ready" and their final weapons trial was due by September. As of 30 August, 10 airframes of Tejas Mk 1A are ready with 2 of them equipped with newly delivered engines, including one from the Nashik plant. In early September, the dates were again pushed to October, still subject to the jets' weapons trials, including Astra missile,
ASRAAM and
laser-guided bomb trials, which is underway As of 16 September, there are overall 24 airframes in the production lines combined of which eight are ready for delivery while two have been integrated with the new engines. Seven further engines would be delivered to HAL this year followed by 20 units next year. The two aircraft began their weapons trials involving ASRAAM missiles in the country's eastern sector which will be followed by Astra trials. After the Astra firing from Tejas Mk 1A in late March failed, the
DRDL was compelled to undertake certain software tweaks to address the shortcomings and HAL is now awaiting approval from
CEMILAC's safety review board to continue with its trials. On 1 October, the fourth engine was delivered to HAL. By 3 October, the weapons firing trials of the first two aircraft was completed, which included Astra and ASRAAM missiles trials, and were ready to be delivered following necessary certifications. The third production line of Tejas Mk1A along with the second production line of
HTT-40 at HAL's Nashik facility was inaugurated by the Defence Minister on 17 October, from the Nashik plant conducted its maiden flight and had already completed its assembly and pre-flight trials. Although HAL was scheduled to deliver 10 Tejas Mk 1A aircraft to the Indian Air Force in FY2025-26, the numbers were revised to five in December 2025. The second set of wings from Larsen & Toubro was delivered on 31 December 2025. The firm will supply four wing sets per annum which can be enhanced to 12 sets subject to demand. The missile and firing trials are completed according to HAL chief as of 28 January 2026. The trials included two missile launches and release of a
laser-guided bomb. The Air Staff Qualitative Requirements (ASQR) certification and operational clearances, which are mandatory before formal induction, are still due. The SQRs include flight envelope validation, avionics and sensor integration, electronic warfare performance, reliability and maintainability parameters and operational suitability checks. HAL will approach IAF to take the deliveries within the fiscal year. Thereafter, IAF will decide on its acceptance and handover details. As of 4 February, 15 airframes are in ready configuration state and will be joined by 5 more within this fiscal year. However, the Indian Air Force will reportedly review the Tejas Mk 1A programme in May before deciding on the acceptance of delivery of these planes. A detailed discussion on the same was done in December 2025. On 5 February, HAL further clarified through a
press release that while five aircraft, "incorporating major contracted capabilities" as per the ASQR, are ready for deliveries, nine more have completed their first flights and awaits GE engine deliveries. Only five engines have been received as per the release and the design and development issues are being resolved in an "expedited manner". However,
Business Standard reported that the firm has sought some relaxations on the ASQR to meet the March 2026 deadline for five jets. Hence, even if the jets are delivered within the deadline, they will lack full operational capabilities. If the requests are partially agreed to the delays might extend to May, or even June–July if all the ASQR are to be met. The IAF has raised a list of operational and safety issues that needs to be sorted before acceptance of deliveries. One of the operational issue was the simultaneous functioning of the radar with the other systems including the electronic warfare suite. On the first week of February, reports emerged revealing the post-coupling of 19th LCA Mk1A (LA-5051) have been completed and the airframe has been rolled out. As reported on 21 February, the IAF has laid down a list of essentials before accepting the aircraft, however, it has agreed to some exemption of the contractual obligations after consulting with the defence ministry. The delivery is now expected the new
fiscal year. This implies that the jets will incorporate some systems even after delivery. The essentials include the final missile firing trial, certification, full integration of radar and EW systems and the complete weapons package. HAL received the list of essential tasks in a meeting with HAL and IAF which it agreed to complete by April and followed by a few weeks-long acceptance trial by the IAF. On 1 April 2026, it was reported that a critical programme review would be undertaken by the IAF and HAL. Following the review, the IAF will take an update of the progress and finalise a revised delivery schedule. Officials from HAL and the IAF would meet in
New Delhi, According to a source cited by
The New Indian Express, the outcome of the review would be critical. If the programme was "sufficiently on track" the deliveries would be taken within two to three months, otherwise further slippages could be seen. The five aircraft deemed to be ready by HAL had only "major" contracted capabilities incorporated and multiple contractored capabilities, including the mandatory ones, are yet to be certified. Meanwhile, GE is expected to deliver the sixth engine, which is ready, to HAL by month-end and another 20 units between June and December 2026. Hence, there would be six Tejas Mk1A with Cat-A engines by April-end. Twenty Tejas Mk1A airframes has also kept ready. Delivery is good begin when
ASRAAM trials are completed in the required configuration and some radar software upgrades. HAL is also implementing the contractual penalties on GE, in the form of
liquidated damages, for every delay in engine deliveries under a provision stated in the contract. GE has also reportedly assured deliveries of over 20 engines from 2027. ==Operational history==