MarketHurontario LRT
Company Profile

Hurontario LRT

The Hurontario LRT, officially named the Hazel McCallion Line, is an 18-kilometre (11 mi) light rail line under construction in Mississauga and Brampton, Ontario, Canada. The line runs along Hurontario Street from Port Credit GO Station north to Steeles Avenue in Brampton. It is being built under a public-private partnership by Mobilinx, a consortium that includes Transdev, Hitachi, Astaldi, John Laing Group, and Amico. Provincial transit agency Metrolinx retains ownership. It will be the only street railway operating in the Greater Toronto Area outside Toronto proper.

History
Background Mississauga and Brampton identified a need for rapid transit along Hurontario Street due to overcrowding on the corridor's bus routes, which carried more than 25,000 passengers per day. Three options were evaluated: light rail for the full corridor, bus rapid transit for the full corridor, or a combination of the two. After public consultation sessions in 2008 and 2010, residents of both cities favoured full-corridor light rail. Funding In 2016, the capital cost was projected at $1.4 billion. On April 21, 2015, the Government of Ontario announced it would fully fund the line's capital costs, excluding local expenses such as utility relocations, surface upgrades, and landscaping. When Mobilinx was awarded the contract in October 2019, the total value was $4.6 billion to design, build, and finance the line, plus approximately $1 billion for 30 years of operation and maintenance. The City of Mississauga is expected to cover a share of ongoing operating costs. In November 2024, Mayor Parrish wrote to Premier Ford requesting the province subsidize the city's estimated $65 million in annual operating costs for at least the first three years, citing similar provincial commitments to Toronto and Ottawa. The Ministry of Transportation said the province was "considering" the request. Main Street extension The original plan called for the LRT to continue north of Steeles Avenue along Main Street to Brampton GO Station. On October 28, 2015, Brampton City Council voted 7 to 4 against allowing the LRT to run along Main Street through its heritage downtown area. Opponents cited low ridership projections (an average of 200 riders per hour per direction on weekdays), concerns about the impact on the area's heritage character, and potential costs of up to $100 million for utility relocation, road resurfacing, and landscaping. The province proceeded with the project terminating at Steeles Avenue. Metrolinx CEO Bruce McCuaig said the allocated funding would be made available for other transit projects. By January 2022, Brampton staff were evaluating two alternatives: a surface extension at an estimated cost of $500 million, and a mostly underground alignment at $1.7 billion. By February 2023, inflation and design changes had increased the estimates to $933 million (surface) and $2.8 billion (underground). Brampton's preferred underground option would include a surface stop at Charolais Boulevard and underground stops at Nanwood Drive and Brampton GO Station. On February 8, 2024, the Ontario government approved both the Main Street extension and the City Centre loop, without specifying stop locations or whether the extension would be tunnelled or at grade. On January 24, 2025, Premier Ford announced at Brampton City Hall that the extension would be mostly tunnelled, but did not commit funding in the provincial budget. The tunnel alignment faces unresolved engineering challenges related to the Etobicoke Creek flood plain in Brampton's downtown. No environmental assessment specific to the tunnel has been completed. On February 14, 2022, Premier Ford offered to reinstate the loop at a press conference renaming the line, without specifying a timeline. The province formally approved the loop on February 8, 2024. Other design changes On March 21, 2019, in addition to cancelling the City Centre loop, Metrolinx cancelled a stop at Highway 407 and a pedestrian bridge at Cooksville GO Station to reduce costs. Between the Robert Speck stop and Highway 403, a 2017 design placed the LRT in the centre median crossing over Highway 403 on a bridge. On June 6, 2017, three consortia were shortlisted: Hurontario Light Rail Connection Partners (led by Cintra, Colas, and Acciona), Mobilinx (led by Astaldi, John Laing Group, Hitachi, Transdev, and Amico), and Trillium Transit Partners (led by Kiewit, Meridiam, and Keolis). On December 1, 2017, Metrolinx announced the line would use 44 Citadis Spirit vehicles from Alstom, to be manufactured at a plant in Brampton. Metrolinx later reduced the initial order to 28 vehicles. Only Mobilinx and Trillium Transit Partners submitted proposals. On October 21, 2019, Mobilinx was awarded the contract for 30 years, with a design-build-finance value of $4.6 billion and a contractual completion date of fall 2024. Construction in December 2022 Construction started in spring 2020 with work on the Operations, Maintenance and Storage Facility (OMSF) south of Highway 407. By January 2021, excavation had started for the below-grade Port Credit station. Mobilinx used the Verona System to construct a passage under the Lakeshore West line tracks, pushing a hollow concrete "push box" structure beneath the railway using hydraulic jacks without disrupting rail traffic. This work was completed by June 2023. The same push box technique was used at the Queen Elizabeth Way to create new northbound traffic lanes under the highway, freeing the existing lane space for the LRT. Metrolinx reported this underpass was completed in late December 2025. Track construction on Hurontario Street began in mid-2022, starting northbound from Matheson Boulevard toward Britannia Road. The first of 13 traction substations was installed in March 2023 at Skyway Drive and Hurontario Street. By February 2026, Metrolinx reported track work completed at 36 of 55 intersections, with 45 percent of rails laid in both directions. Eleven of 19 stops had their platform bases finished and six had canopies installed. Four Citadis Spirit vehicles had completed testing in Kingston, with nine more delivered for testing. == Delays and disputes ==
Delays and disputes
Timeline The project has experienced escalating delays. The original contractual completion was fall 2024. Metrolinx has stated it will provide a date only "when construction nears completion and we move into the testing and commissioning phase." On April 22, 2026, Metrolinx CEO Michael Lindsay and other officials met with Mississauga council in a closed session. Neither Metrolinx nor the city disclosed what was discussed. A city spokesperson said the information was "explicitly supplied in confidence to the municipality" and "protected by law." Credit downgrade In October 2024, S&P Global Ratings downgraded Mobilinx's credit rating to BBB and placed the consortium on negative credit watch. S&P cited "newly reported delays" including track tolerance issues on already-installed sections that were "out of compliance with specifications," requiring design changes and the reprocurement of special tracks. The report noted the project was "incurring concurrent delays on multiple other fronts" and that Metrolinx was working with Mobilinx on "pending claims through a global settlement." It was the second time S&P had scrutinized Mobilinx; the agency had placed the consortium on credit watch in April 2022 amid permitting and material supply issues, before lifting the watch in April 2023. Legal disputes Mobilinx has faced multiple lawsuits from subcontractors. In late 2023, Barricade Traffic & Services filed a claim alleging Mobilinx owed more than $300,000 for traffic control equipment that was not returned after the rental period ended and was used without payment. Separately, Vaughan Paving filed a claim alleging it was owed approximately $2.7 million for concrete work on inlaid rail. Impact on businesses Multiple councillors and local media have reported that prolonged construction has had a significant financial impact on businesses along Hurontario Street. The Cooksville Business Improvement Area, representing more than 600 businesses, reported that at least one restaurant was forced to permanently close after failing to recover from construction-related revenue losses. Ward 5 Councillor Hart reported that one hotel in her ward had seen revenue decline by more than 50 percent. Councillor Dipika Damerla criticized Metrolinx for declining to hold public town halls, calling the agency's posture "arrogant." Metrolinx declined invitations to Damerla's ward town hall and the Cooksville BIA's annual general meeting, citing preparations for the spring council presentation. Transit advocacy group CodeRedTO's executive director Cameron MacLeod attributed Metrolinx's refusal to provide timeline information to reputation management. "They know that by scheduling anything they're increasing risk to the project, and it's not about risk to the actual project completion ... but it's risk to their reputation," MacLeod told The Pointer. == Route ==
Route
Description The line has a dedicated right-of-way throughout the corridor. For most of the route, the LRT runs in a reserved centre median on Hurontario Street with two general traffic lanes in each direction. General traffic crosses the tracks only at signalized intersections. After passing under the Lakeshore West line tracks, the LRT continues north on the west side of Hurontario before crossing to the centre median. The line then enters Brampton, with stops at Ray Lawson Drive and County Court Boulevard before terminating at the Brampton Gateway Terminal on Steeles Avenue. Operations The LRT is planned to run every 7.5 minutes during peak hours and every 10 to 12 minutes at other times. Service hours are planned for 5:00 a.m. to 1:30 a.m. Monday through Saturday and 7:00 a.m. to midnight on Sundays and holidays, with bus service supplementing overnight hours. End-to-end travel time is projected at 40 minutes. == Rolling stock ==
Rolling stock
The line will be served by 28 Alstom Citadis Spirit low-floor light rail vehicles, each long with a capacity of up to 292 passengers. The vehicles are assembled at an Alstom plant in Brampton. ==Gallery==
Gallery
File:Courtneypark Station Construction Progress May 2021.jpg|Early progress and fence area at Courtneypark Stop in May 2021 File:Hurontario St construction works in 202203.jpg|Early LRT construction works in March 2022 File:Courtneypark Station Construction Progress August 2022.jpg|Construction progress of Courtneypark Stop in August 2022 File:Hurontario LRT Track UC Traders Blvd.jpg|Early track construction at Traders Boulevard/ Aldridge Street in December 2022 File:Port Credit Hurontario constuction.jpg|alt=Photo of a concrete guideway under construction|Port Credit construction February 2023 File:Courtneypark Station Construction Progress May 2023.jpg|Construction of Courtneypark Stop in May 2023 File:Hurontario LRT Construction Traffic.jpg|LRT tracks laid at Sandstone Drive/ Brunel Road in August 2023 File:Courtneypark Station Construction Progress July 2024.jpg|Construction progress of Courtneypark Stop in July 2024 == See also ==
tickerdossier.comtickerdossier.substack.com