Electrical energy generated The amount of electrical energy generated E_t or estimated to be generated is dependent upon a large number of factors including: •
Natural resource economics and the availability of economically viable resources required for generator operation is variable per generation technology. For
variable renewable energy generators,
wind resource assessment and
solar potential assessment are examples of methods used to assess the availability of resources required for wind turbines and solar panels to generate energy. For non-renewable generators, fuel availability over the lifespan of a generator may be temporarily impacted by geopolitical factors (an example being the
1970s energy crisis) or impacted by gradual depletion of and discovery of new non-renewable resource reserves.
Oil and gas reserves and resource quantification is an example of a method used to assess long term availability of economically viable fuel resources for non-renewable generators. • Electricity market effects of
grid balancing may require a
load-following power plant to curtail generation of energy if the grid does not demand energy (negative
spot prices) or allow a generator with high variable costs to be brought online to dispatch into a grid with significant unmet demand and high spot prices. Battery,
run-of-the-river hydroelectricity with
pondage,
variable renewable energy and natural gas turbine generators are examples of
dispatchable generators. Seasonal
diurnal cycles and climatology, as well as short term meteorological events have significant impacts to grid balancing from both supply and demand perspectives. The geographical region within which LCOE is being assessed, the mix of generators in a grid, the proportion of
demand flexibility (or conversely
firm power demand) within a grid and transmission capacity limits within a grid also significantly influence required generation curtailment. • The cost of
operational availability A_o (known as
availability factor for electricity generators) is variable per generation technology. Different generator technologies require differing levels of planned and unplanned maintenance preventing
nameplate capacity output being achieved continuously for the lifespan of the generator. As an additional external influence, governments differ in their willingness to accept risks of
power outages and lack of
resilience against natural disasters and military attack on electricity grids. Examples of historical events impacting grid resilience are the
1991 Gulf War air campaign against civilian infrastructure,
2015 Ukraine power grid hack,
2021 Texas power crisis and
Russian strikes against Ukrainian infrastructure (2022–present). Low risk tolerance may require electricity grids to be more significantly overbuilt to mitigate the potential costs of electricity grid interruptions and outages, impacting on a technology-by-technology basis the amount of generation curtailment necessary under normal grid conditions. For a proposed generator with only the proposed nameplate capacity known, observed
capacity factor data available for similar existing generators can be used to estimate the electrical energy generated for the proposed new generator.
Expenditures Investment expenditures I_t, operations and maintenance expenditures M_t and fuel expenditures F_t are influenced by a variety of
taxes commonly imposed by governments including
tariffs impacting the cost of importing generation equipment and fuels,
excises impacting the cost of production of fuels,
carbon taxes for offsetting the
social cost of carbon and other taxes for recouping shared industry costs of
electric power transmission and
research and development of energy technologies. Expenditures can also be influenced by a variety of
energy subsidies. Assumptions are required to be made due to the subjective nature of prediction of future levels of taxation and subsidies and influence of the
politics of climate change.
Discount rate Cost of capital expressed as the discount rate r is one of the most controversial inputs into the LCOE equation, as it significantly impacts the outcome and a number of comparisons assume arbitrary discount rate values with little transparency of why a specific value was selected. Comparisons that assume public funding, subsidies, and
social cost of capital tend to choose low discount rates (3%), while comparisons prepared by private investment banks tend to assume high discount rates (7–15%) associated with commercial for-profit funding. Assuming a low discount rate favours nuclear and sustainable energy projects, which require a high initial investment but then have low operational costs. In a 2020 analysis by
Lazard, sensitivity to discount factor changes in the range of 6–16% results in different LCOE values but the identical ordering of different types of power plants if the discount rates are the same for all technologies. ==See also==