The following dates represent the dates the section opened to the public, not the private inauguration.
Planning The
Government of Maharashtra issued a
gazette notification on the proposed Navi Mumbai Metro project on 28 April 2010, requesting comments from the public. No objections or suggestions on the proposed project were received by 28 May, the final date to submit comments. The
City and Industrial Development Corporation (CIDCO) was named as the implementing agency for the proposed Belapur–Pendhar–Kalamboli–Khandeshwar line, under the
Indian Tramway Act 1886, by the Government of Maharashtra on 30 September 2010. The state government later asked CIDCO to implement the Navi Mumbai Metro project under the Central Metro Act. The
Delhi Metro Rail Corporation submitted the final detailed project report for the Navi Mumbai Metro project in October 2011. CIDCO appointed the
Louis Berger Group and Balaji Rail Road Systems as general consultants for the project. The proposed route would link Belapur, Kharghar, Taloje, MIDC, Kalamboli and Khandeshwar, before terminating at the proposed
Navi Mumbai International Airport. In September 2013, CIDCO proposed extending Line 1 up to
Kalyan–
Ulhasnagar–
Murbad. Line 1 is being developed in 3 phases. Phase I is an section from Belapur to Pendhar with 11 stations.
Construction The metro's foundation stone was laid on 1 May 2011 by Chief Minister
Prithviraj Chavan, and general foundation work on the system's first phase commenced on 28 October 2011. CIDCO awarded the contract for civil works in Phase I to six firms. J Kumar Infraprojects Ltd was awarded a contract to design and build the depot at Taloja in February 2013. The original deadline to commission Line 1 was 2016. This was later extended to mid-2017, and then mid-2018. By January 2017, only 60% of the work on Phase I stations had been completed. Finding the progress of work to be unsatisfactory, CIDCO sent a notice terminating the contract to the San José-Mahavira-Supreme consortium on 11 January 2017. On 1 March 2017, CIDCO floated new tenders to complete the remaining 40% work on the Belapur-Pendhar section. The new contract was estimated to be worth . The consortium appealed the termination of the contract in the
Bombay High Court in February 2017. In September 2017, the Court permitted the consortium to proceed with civil works on 5 stations and permitted CIDCO to re-tender the remaining 6 stations.
Nashik-based Prakash Constrowell Limited was awarded the contract to complete work on the 6 stations. In December 2018, Navi Mumbai Metro's superintending engineer Deepak Hartalkar stated that "work on the elevated corridor is almost complete" with 68% of the stations and 50% work on the signal system having been completed. In September 2019, a CIDCO official stated that around 83% of work on stations had been completed. The official also stated that a metro train had been run on the section of track connecting Pendhar station with the depot at Taloja. Prakash Constrowell was unable to carry out any work for several months due to the pending court case filed by the previous contractors. In 2020, Prakash Constrowell requested CIDCO to terminate its contract. In March 2020, the
Comptroller and Auditor General of India's report on state
public sector undertakings accused CIDCO of “inadequate planning for the execution of individual projects” including the Navi Mumbai Metro project. In January 2021, CIDCO issued a press statement declaring that development work of six stations "had not been executed at the expected speed" due to the
COVID-19 pandemic and some technical issues. It also announced that it had appointed
Maharashtra Metro Rail Corporation Limited (Maha Metro) to complete the work on Phase I at a cost of . In July, CIDCO appointed Mahametro to operate and maintain Line 1 for 10 years, for which CIDCO will pay Mahametro plus taxes. The
Research Design and Standards Organisation (RDSO) began oscillation and emergency breaking distance trials on 28 August. The RDSO also tested rolling stock on different parameters including speed weight and breaking. Oscillation trials were completed on the section from Pendhar to Central Park station on 14 September. The RDSO granted Interim Speed Certificate for the section from Central Park to Pendhar station in October. In the same month, the Commissioner of Metro Railway Safety (CMRS) required the replacement of the bearings on most of the pillars on the stretch between Belapur and Kharghar. Mahametro awarded a contract to J Kumar Infraprojects Ltd to complete the remaining work in November 2021. The CMRS began conducting safety inspections on the stretch between Pendhar and Central Park stations on 17 January 2022. The section received approval from the CMRS in April 2022. In April 2023, CIDCO responded to a
Right to Information query filed by activist Anil Galgali stating that only 5 of the 11 stations were complete and ready for service, while work was still ongoing at the remaining stations. The CMRS completed its final safety inspection of Phase I on 25 April, and issued the final safety certification for Phase I on 21 June 2023. Operation projected to commence in 23.11.2023. ==Funding==