Initial proposal By 2011, Hudson River Pier 55 was deteriorating, a situation that was worsened by
Hurricane Sandy in New York the next year. and $160 million. Diller's foundation, headed jointly by his wife
Diane von Fürstenberg, contributed $100 million The city and state promised to give $17 million and $18 million, respectively. The park was to float completely above the water, resting on 300 concrete pillars. Diller had cold-called Heatherwick to design a park at the site. According to Diller, the first plan was "completely unbuildable" and resembled "Noah's Ark in stainless steel". The plans received final approval in March 2016. The next month, a judge for the
New York Supreme Court dismissed the case. The City Club filed an appeal, and a hearing was scheduled for September 2016. In the meantime, an appellate court placed an injunction in June 2016, temporarily stopping any further work from proceeding. Less than a month later, the injunction was partially lifted, allowing work on nine pilings to proceed. At the appellate hearing, representatives of Pier 55's developers argued that the trust had performed a proper environmental review. The court rejected the City Club's appeal. The suit was escalated to the
New York Court of Appeals, which also rejected the appeal. By November 2016, construction of concrete footings was underway. While appealing the City Club's lawsuit, Diller claimed that developer
Douglas Durst was financing the lawsuit against Pier 55. Early in 2017, Durst confirmed that he had funded the City Club's suit against the project, though he said he had not been involved with the lawsuits for half a year. At the time, Robert Durst had been accused of murder, and Diller subsequently apologized for the comments. In June 2017, the USACE issued a permit for the park's construction after plans were slightly modified. The City Club filed a complaint the next month, opposing the changes to the permit.
Cancellation and revival Plans for the park were scrapped in September 2017 due to continuing legal disputes. The park also experienced cost overruns as its budget had exceeded $200 million by then. According to Diller, he had already invested $45 million of his foundation's money. On the day the project was canceled, he was scheduled to order $80 million in cement. After his lawyers advised him that the City Club's lawyers may request an injunction on the project, von Fürstenberg and the couple's children advised Diller to stop the project and "go where you're wanted". Cuomo also promised the ecology of the Hudson River estuary would not be adversely affected by the construction of Pier 55.
Completion Cuomo provided $50 million for the park in April 2018, but with the condition that the city raise a matching amount. Construction of the structure began the same month, with the construction of walkways from the Hudson River Park esplanade to the future park site. The new estimate for the project was $250 million. By that August, the pilings were being installed. A symbolic cornerstone was laid in December 2018. and the Pier 55 project was renamed
Little Island in November. The first trees at Little Island were installed in March 2020. All the piles and pots had been installed by the next month, and the layers of soil supporting the vegetation were being planted. == Operation ==