Background The
Government of Maharashtra through the MMRDA, in order to improve the traffic and transportation scenario in Mumbai and to cater to the future travel needs in the next 2-3 decades began exploring the viability of various alternative mass transit systems which are efficient, economically viable and environment friendly. In this context, a detailed feasibility study was carried out under Indo-German technical co-operation by entrusting the consultancy work to Tewet in association with DE-Consult GmbH and
Tata Consultancy Services, during 1997–2000. The study recommended a mass transit corridor from
Andheri to
Ghatkopar as potentially bankable and economically viable, after examining a number of alternative corridors and alignments. This study was updated by the MMRDA in May 2004. Meanwhile, the
Delhi Metro Rail Corporation (DMRC) prepared the master plan for Mumbai Metro, wherein they recommended extending the Andheri-Ghatkopar section to
Versova as part of the master plan and identified it as a priority corridor for implementation. The State Government declared the project as a "public vital infrastructure project" and designated the MMRDA as the Project Implementation Agency (PIA). The Versova-Andheri-Ghatkopar corridor was chosen as the first line in the master plan to be implemented. The
Mumbai Suburban Railway connects Mumbai from north to south. However, east–west connectivity is poor. The Versova-Ghatkopar route had no suburban rail link and was serviced by either BEST buses, autos or taxis. Blue Line provides east–west rail connectivity between the
Eastern and
Western suburbs of Mumbai. It facilitates interchange between the Mumbai Suburban Railway and Mumbai Metro at
Andheri and
Ghatkopar stations. The line significantly reduces the journey time from
Versova to Ghatkopar from 90–120 minutes to 21 minutes, and bypasses about 45 traffic signals. It also provides rail connectivity to the
MIDC and
SEEPZ.
Construction under construction in Andheri in March 2012 during the trial run in May 2013 The concession agreement for the Versova–Andheri–Ghatkopar corridor was signed with Mumbai Metro One Pvt Ltd (MMOPL), a joint venture company owned by
Reliance Infrastructure (69%),
Veolia Transport (5%) and the MMRDA (26%), in March 2007. SSRI Creative Infrastructure (Choksi Group) was the main technical contractor.
Prime Minister Manmohan Singh laid the foundation stone on 21 June 2006. The work order for the project was issued on 21 January 2008, and work began on 8 February 2008. The deadline for completion of Blue line has been shifted several times. The following months have all, at some point of time, been announced as the deadline for completion of the project - July and September 2010, July 2011, March and November 2012, September 2013 (Phase 1: Versova to
Airport Road) and December 2013 (Phase 2: Airport Road to Ghatkopar), and 31 March 2014. The MMOPL blamed the delay in construction on the MMRDA. RInfra officials said that the MMRDA had to acquire land along the route and provide
right of way to the MMOPL by December 2008. As of August 2008, the MMRDA had only freed up 20% of required land. The lack of maps of underground utilities made the task more difficult. As per the contract between the MMOPL and the MMRDA, the MMRDA was supposed to hand over complete right of way to the MMOPL by mid-2008. The MMOPL eventually received nearly 100% of the land required for the project in December 2011, with the exceptions of the
minaret of a mosque near
Andheri station and a portion of the roof of
Maheshwar Temple near
Jagruti Nagar station that still needed to be demolished. under construction in
Andheri in 2012 By October 2011, the majority of the corridor's track-support pillars and girders had been laid, and the 12 individual stations were 70% complete, with most of the stations rising above platform level. However, land acquisition and right-of-way issues, along with problems with the construction of a Metro-related viaduct, delayed the line's predicted completion to summer 2012. In May 2012, the
Indian Bank restructured the Mumbai Metro's loan account, citing the project's land use problems. On 1 May 2013, a successful trial run from Versova to Azad Nagar stations was conducted on Blue Line in the presence of
Chief Minister Prithviraj Chavan, who said that the line would open to the public from September 2013. However, MMRDA officials told
Business Standard in August 2013 that the metro would be delayed further as it had not received approval from the Central Railway Safety Commissioner, and some of the facilities remained incomplete. The first major trial run on Blue Line, began at 6:45pm IST on 3 June 2013 from
Versova metro station, and covered the stretch to
Airport Road metro station by 7:05pm, according to MMRDA additional commissioner S.V.R. Srinivas, who was on board the train. Trial runs had been conducted for the past month, the most notable being the trial run on 1 May 2013, that was officially flagged off by the Chief Minister. Several tests were conducted before the metro opened to the public. The MMRDA sent a letter to
RInfra on 31 December 2013, asking them to change the name of the metro system from Reliance Metro to Mumbai Metro. The MMRDA pointed out that the original concession agreement said that the project would be named as the Mumbai Metro. RInfra issued a press statement on 2 January 2014, blaming the MMRDA for having "failed to provide any guidance on this subject during the bidding stage and/or during the implementation stage".
Republican Party of India (A) workers protested the name Reliance Metro on 8 January 2014 by blackening boards with Reliance's logo at
Chakala (J. B. Nagar) metro station. On 11 January,
Shiv Sena MLA
Subhash Desai sent a letter to Chief Minister Chavan opposing the Reliance Metro name, and expressing support for the name Mumbai Metro. In February 2014, U.P.S. Madan, metropolitan commissioner of MMRDA, confirmed that RInfra had agreed to rename the project as Mumbai Metro from Reliance Metro. However, even by April 2014, the Reliance Metro logos that had been stuck on trains and stations had not been removed. MMOPL officials said that they had not yet received any new logo design, and were still awaiting the same. On 30 April 2014 The MMOPL unveiled a new logo, which uses the name "Mumbai Metro" but also includes the MMRDA and Reliance Infrastructure. The new name was also confirmed by Chavan at a press conference at
Vidhan Bhawan on 14 June 2014. When asked about RInfra posting its "Reliance Metro" branding at some metro stations, he said, "It is 'Mumbai Metro' and we will ensure that it remains the same in future also". under construction in
Ghatkopar in 2012 On 6 February 2014, RInfra announced that construction was complete, and that some of the regulatory approvals were in place. However, the construction of approach roads to stations such as Jagruti Nagar and Asalpha Road had not been completed, During trials in mid-March 2014, the Mumbai Metro ran trains at a headway of almost 4 minutes. Oscillation trials were completed in early 2014. However, the submission of the report by the RDSO to the Chief Commissioner of Railway Safety was delayed a public interest litigation (PIL) filed in
Maharashtra High Court on the height of Mumbai Suburban Railway station platforms. The RDSO had to divert its resources to inspecting the suburban railway platforms, because passengers were falling into the gap between the platform and the trains. The MMOPL was granted a "speed certificate" from the RDSO on 2 April. MMRDA and MMOPL authorities jointly applied to the CMRS for safety certification on 4 April. The CMRS required certain minor improvements to access areas before the metro could begin operations. The CMRS also said that he would travel to Lucknow to discuss the inspection with RDSO officials and then cross check all the other necessary approvals, including rolling stocks, from the Railway Board. The Congress-NCP government had wanted to open the line by 24 April 2014, the voting day in Mumbai for the
2014 general elections. The MMOPL approached the Railway Board for approval of rolling stock (including the rakes and wheels) on 22 April. MMRDA and MMOPL officials said that the line would open within 7 days of receiving approval from the Railway Board. Despite the MMOPL submitting the necessary paperwork on 22 April, the Railway Board did not grant approve until late May 2014. According to railway officials, this was because the rakes and wheels used in the metro were "of a new kind, with newer dimensions". The newly appointed Railway Minister
D.V. Sadananda Gowda gave the final approval on 5 June. MMOPL Chief Executive Abhay Mishra announced on 7 June that the metro would open the following day. A key proposal of the Station Area Traffic Improvement Scheme (SATIS) was the integration of the metro rail system with the
BEST. The BEST and the
BMC jointly worked towards relocating existing bus stops. BEST bus feeder routes were created along the metro corridor. Bus stops have electronic indicators displaying the expected arrival time of the next train, and information about bus schedules is available inside the metro stations. The MMRDA widened footpaths below metro stations. Parking for bikes and motorbikes is available at all stations.
Accidents Eight accidents occurred during the construction of Blue Line. In total, 2 people were killed and 21 injured during the construction of the line. The first accident occurred in May 2008 when 1 person was killed and another injured, when a pile rig collapsed at a construction site in Andheri (West). In 2009, 4 people were injured, when a steel reinforcement cage and temporary scaffolding of a concrete pillar caved in it Andheri (East). In April 2012, a crane at a construction site in Ghatkopar, veered off a truck and crashed on a portion of the nearby Sarvodaya Hospital. No one was injured as the affected portion of the hospital building was empty at the time. On 5 September 2012, a slab collapsed at the under-construction Subhash Nagar metro station in
Andheri, killing one construction worker and injuring 16 people. Following the incident, construction work on the metro was suspended. MMOPL fined the contractor,
Hindustan Construction Company, . On 11 September 2012, MMOPL appointed Geneva-based SGS Consultants as independent safety consultants for the construction of Blue Line. Construction resumed on 25 September 2012, under the supervision of SGS Consultants, after the consultant submitted its preliminary report to the MMOPL. The consultant remained with the project until the completion of Blue Line to help prevent future accidents. According to SVR Srinivas, then additional metropolitan commissioner at MMRDA, "The accident was basically due to voids in the support. The support weakened due to rain and utilities underneath created voids. So, it was basically due to loosening of the soil due to construction activity and its erosion due to heavy rain that the support weakened. If because of any reason a part of the support settles, stress increases on the staging and causes it to fail leading to a cascading effect".
Opening The first metro service was flagged off by Maharashtra Chief Minister Prithviraj Chavan, along with Reliance Infra Chairman Anil Ambani and wife Tina Ambani, on 8 June 2014 at 10:10 am from Versova station. Chavan's appearance at the inauguration came despite the fact that he had threatened to boycott the ceremony the previous day to protest RInfra's decision to raise fares. The line was scheduled to open to the public at 12:10pm, with the first service departing from Ghatkopar station. This was delayed by 10 minutes and departed at 12:20 pm. The train was further delayed by nearly half an hour, as it had to halt beyond the planned
dwell time at certain stations due to a technical glitch. This in turn caused some other trains to also be delayed by 20–30 minutes. MMOPL announced a special introductory fare of 10, regardless of distance, for the first 30 days of service. In the first week of operations, 21.56 lakh commuters travelled on the line, at an average of 3.08 lakh daily. Within days of the metro's opening, many commuters switched from using BEST buses and autos. Authorities estimated a 25% reduction in BEST commuters along the route as a result of the metro. Ticket sales on BEST Bus Route Number 340, the most popular bus route between Andheri and Ghatkopar, dropped by 1.5 lakh in the first three days of Blue Line's opening.
2014-17 In its first year of operation, from June 2014 to June 2015, Blue Line transported over 92 million commuters, and made over 130,000 trips, covering a distance of over . The line carried an average of 263,000 commuters on weekdays. The MMOPL earned a total revenue of , and incurred losses of . The revenues include earned through leasing station space to 52 stalls across its 12 stations. The MMOPL said that it incurred an expenditure of per day to maintain the system and car depot. On 4 June 2015, metro authorities announced that Blue Line had transported 100 million passengers since operations began. Mumbai Metro One announced that Blue Line had transported more than 150 million passengers since operations began, crossing the milestone on 26 January 2016, India's 67th Republic Day. Blue Line transported 200 million passengers within 786 days of operations. It crossed the 250 million mark on 11 February, or within 957 days, the fastest time in which any metro in India has reached the milestone. station in 2019 In 2017, Mumbai Metro One partnered with
Google to integrate metro details into
Google Maps. This collaboration enabled users to access authentic timetables and geographic information for the Versova-Andheri-Ghatkopar route. Trip timings, with frequencies of four minutes during peak hours and eight minutes during non-peak hours, were provided. Google Maps also displayed facilities like stairs, escalators, and ticket counters, helping commuters plan their journeys more efficiently. ==Finances==