The transmission system is currently composed of three bipole transmission lines with their converter stations and ground return electrodes to enable monopole operation.
Bipole 1 mercury arc valve in Bipole 1 of
Manitoba Hydro's Radisson converter station, August 2003. By the end of 2004 all of these mercury arc valves had been replaced with
solid state thyristors. Bipole 1 runs from Radisson to Dorsey. It was originally rated to run at a maximum
potential difference of ±450
kilovolts and a maximum
power of 1620
megawatts. This results in an
electric current of 1800
amperes. Bipole 1 consists of six
6-pulse converter groups at each end (three in series per pole), each originally rated at 150 kV DC, 1800 A. Each converter group can be bridged at the DC side with a vacuum switch. Subsequent upgrades have increased the current rating to 2000 A and the voltage rating of most equipment to 166 kV per bridge (i.e., 500 kV total), although as of January 2013 Manitoba Hydro still report that the line is operated at +463 kV/−450 kV. When it was built between March 1971 and October 1977,
mercury-arc valves were used to rectify the
alternating current. These
valves, supplied by
English Electric, each had six anode columns in parallel and were the most powerful mercury arc valves ever built. Each of them had a weight of , a length of , a width of and a height of . Between 1992 and 1993 the mercury arc valves of Pole 1 were replaced with
solid state thyristors from GEC Alsthom, increasing the maximum power and voltage of the line to its current levels. The mercury arc valves of Pole 2 were replaced later by
Siemens. By the end of 2004 the last of the mercury arc valves in Pole 2 had been replaced by thyristors. At both Radisson and Dorsey, the thyristors are situated in the same hall where the mercury arc valves originally stood. At both locations, the hall has a height of , a width of and a length of .
Bipole 2 The Bipole 2 transmission line runs from Henday to Dorsey. Bipole 2 can transfer a maximum power of 1800 MW at a potential of ±500 kV. Bipole 2 consists of four
12-pulse converter groups at each end (two in series per pole) and was put into service in two stages. After the first stage in 1978 the maximum power was 900 MW at 250 kV, which increased to its present figure when it was completed in 1985. Bipole 2 crosses Nelson River at 56.459811 N 94.143273 W. There is a backup crossing of Nelson River at 56.441383 N 94.176114 W. It is not possible to directly switch the line to the backup crossing. Unlike Bipole 1, Bipole 2 has always been equipped with thyristors. The thyristors, supplied by the German HVDC consortium (
Siemens,
AEG and
Brown Boveri) used water cooling for the first time in an HVDC project. Until that time, the relatively few HVDC schemes using thyristors had used either air cooling or, as on the
Cahora Bassa project supplied by the same consortium, oil-cooling. The thyristors were arranged in floor-mounted vertical stacks of four each (
quadrivalves). Each set contained 96 thyristor levels in series, with two in parallel. These were arranged in 16 thyristor modules connected in series with 8 reactor modules.
Bipole 3 In 1996 an extreme wind effect damaged both Bipoles 1 and 2 and threatened to black out Winnipeg. Power was maintained by importing from
Minnesota while the two existing Bipoles were repaired. To avoid a repetition of this event, and further improve the reliability of the power supply, Manitoba Hydro examined routes further to the west for their Bipole 3 line. The plans also include an additional converter station and feeder lines around the city. Bipole 3 construction started in 2012. The line was completed and entered service in July 2018. The main elements of the Bipole III system are: • Keewatinohk Converter Station, located on the Nelson River near the site of the proposed Conawapa Generating Station at • A 1,324 km bipolar transmission line operating at nominally +/-500 kV, running to the West of
Lake Manitoba • Riel Converter Station, on the east side of the
Winnipeg Floodway, in the
Rural Municipality of Springfield at • Additional 230 kV AC lines for the northern collector system. The line uses guyed steel towers in northern stretches of the line and self-supporting steel lattice towers in the southern part. On average there will be about two structures per kilometre. Each tower carries a bundled conductor for each pole. Each pole conductor is made of three sub-conductors equivalent to 1,590
MCM ACSR. Conductors are supported by toughened glass or porcelain strain insulators with a maximum clearance to ground level of 34 metres, with a minimum of 13.2 metres at mid span and maximum conductor sag. The top of the towers carries an
optical ground cable providing grounding interconnection for the towers and optical fibers for control and communication of the system. Typically the right-of-way for the HVDC line is 66 metres, with 45 metres cleared directly below the line. The system is capable of transmitting 2000 megawatts from the Nelson River stations to loads in the south.
Ground return electrodes Although normally each of the lines run as bipolar systems, if a pole is shut down for maintenance or a fault, the ground return electrode is used to maintain partial capacity operation. Bipoles 1 and 2 share a ground electrode of
ring type, in diameter, from the Dorsey Converter Plant at . The Dorsey electrode is connected with the converter plant by two overhead lines on wooden poles, one for Bipole 1 and one for Bipole 2. At Radisson, Bipole 1 uses a ground electrode of the same size and type as Dorsey, but only away from the station at . Bipole 2 uses a ground electrode in diameter, and from the
Henday Converter Station . Bipole 3 has a ground electrode site near the Keewatinohk Converter Station at connected by a 30 km electrode line. At the southern Riel Converter Station, the electrode line runs about 26 km to a grounding electrode site at near
Hazelridge, Manitoba. ==References==