Background On 19 June 2009, the Defence Acquisition Council (DAC) — the main acquisition panel subordinate to India's
Ministry of Defence (MoD) and chaired by the then
Defence Minister of India A. K. Antony — cleared a proposal for the procurement of seven stealth frigates at a cost of under the designation Project 17A, as an advanced variant of s. The ships were to be constructed by
Mazagon Dock Shipbuilders (MDL), Mumbai and
Garden Reach Shipbuilders & Engineers (GRSE), Kolkata. The DAC also rejected the Navy's proposal of building two of the warships abroad. The construction of the warships will incorporate modular shipbuilding where 300-tonne prefabricated blocks would be put together similar to the construction style of . Earlier, on 4 December 2006, the Navy had sent out a pre-tender
Request for Information (RFI) to French
DCNS, Italian
Fincantieri, American firms
Lockheed Martin and
Northrop Grumman besides shipyards in Russia and Korea for the construction of the first two ships by one of the foreign shipyards so as to ensure the timely absorption of the technology by the Indian shipyards. The project is expected to start in 2011 after both MDL and GRSE completes an upgrade to allow the modular construction. The deliveries were to begin 3–4 years after start of construction. All the firgates are to be inducted by 2022. As reported on 5 August 2013, the design of the Project 17A frigates along with Project 15B destroyers (now, s) were completed by the Directorate of Naval Design (DND) of the Indian Navy. Additionally, the cost negotiations for the construction of the seven vessels had been completed. As part of the project, MDL and GRSE will construct four and three frigates, respectively. Now, the Navy was awaiting clearance from the government. On 18 February 2015, the
Cabinet Committee on Security (CCS) — India's top decision-making institution on matters related to defense and national security chaired by
Prime Minister Narendra Modi — green-lighted the proposal for the Project 17A frigates at a cost of . The contract would be signed in the same month with an initial payment of . The project is the follow-on of the
Shivalik-class or Project 17 frigates and the first ship by each the shipyards is expected to be delivered in 2022.
Construction Garden Reach Shipbuilders & Engineers On 20 February 2015, the Indian Navy signed the contract with the
Garden Reach Shipbuilders & Engineers (GRSE), a
Kolkata-based public-sector shipyard, to build three frigates under Project 17 Alpha at an estimated cost of . According to the terms of the contract, GRSE is slated to deliver the three frigates in 2023, 2024 and 2025, respectively. The frigates would be constructed with "Integrated Construction Methodology" in partnership with Italy's
Fincantieri. In preparation for the order, GRSE re-augmented its infrastructure by establishing newer, modular shipyards along with a
Goliath gantry crane, meant for enabling the construction of the frigates in a short time frame. A significant proportion of the hull's blocks needed for the vessel's construction was procured from smaller shipyards and metal fabrication shops in and around Kolkata, while the construction/fabrication of additional infrastructure was done at GRSE's
Rajabagan shipyard. Construction reached a hiatus in April 2018, when the shipyard's Goliath crane, having failed to withstand strong cyclonic winds which had been travelling at around . The accident rendered the crane permanently inoperable, whilst the module hall - which was to have fabricated the modular blocks for the future frigates, was rendered unusable. However, no damage was reported to have been inflicted on the vessels that were being built by the shipyard, according to representatives from the IN and GRSE. The mishap forced GRSE to modify the project's timeline, by prioritizing the construction of the modular blocks at its other facilities, rather resuming constructing post-repairs to the shipyard. With the loss of the crane, GRSE resorted to building smaller 50 t and 100 t blocks (instead of the regular 250 t blocks) with the shipyard’s smaller cranes. In 2021, GRSE installed a Goliath crane that had purchased from
South Korea, with a lifting capacity of 250 t, thus resuming regular construction operations. The construction of the first frigate began in November 2018, while work on the second and third frigates began in January 2020 and March 2021, respectively. The first of the three frigates, , was
launched on 14 December 2020, with its delivery slated to occur in August 2023. The second frigate, '
, was launched on 15 June 2022, with its delivery expected in 2024. The final frigate, ', was launched in August 2023. On 3 March 2025, GRSE completed the Contractor Sea Trials (CST) of INS
Himgiri was completed by GRSE along with
INS Androth. As per a press release, "CST is considered the final stage of construction, when a vessel’s seaworthiness is tested".
Himgiri was delivered to the Indian Navy on 31 July 2025 and was commissioned simultaneously with MDL's
Udaygiri on 26 August 2025. The second ship from the GRSE lot,
Dunagiri, was laid down on 24 January 2020,
Mazagon Dock Shipbuilders Limited In February 2015, the IN contracted Mazagon Dock Shipbuilders Limited (MDL), a
Mumbai-based public-sector shipyard, to build four P-17A frigates at an estimated cost of over ₹21,000 crore. According to the terms of the contract, MDL is to deliver the four frigates in 2022, 2023, 2024 and 2025, respectively. The four frigates were built at different locations, namely, at MDL's main shipbuilding facility in Mumbai, at MDL's subordinate facility in
Nhava, at a smaller shipbuilding facility also operated by MDL in Mumbai, at an MSE shipyard in
Gujarat and at another shipyard in
Goa. Similarly to GRSE, MDL also upgraded its existing infrastructure; the shipyard augmenting its existing facilities with newer equipment, including a "Goliath" gantry crane, a module workshop, a
wet basin and a "cradle assembly" shop, meant to facilitate modular construction. The construction of the first frigate began in December 2017, while work on the second, third and fourth frigates began in May 2019, September 2020 and June 2022, respectively. The first of the four frigates,
Nilgiri, was launched on 28 September 2019, and began its sea trials five years later, in August 2024. The second frigate,
Udaygiri, was launched on 17 May 2022, in a ceremony coinciding with the launch of , a . The third frigate,
Taragiri, was launched on 11 September 2022, and is scheduled to be delivered by 2025.
Nilgiri was commissioned into the Indian Navy service on 15 January 2025. and commissioned on 3 April 2026. The final ship from the MDL,
Mahendragiri, was delivered to the Indian Navy on 30 April 2026. == Ships in the class ==