The first works near Den Helder are opened In August 1817 the commercial lock of Den Helder first became operational. On 4 November 1817 King William I and
Prince Frederick arrived in Den Helder to see the lock. They also made a trip on a large boat that was towed along the new canal on the inside of the new Koegras dyke till they reached 't Zand, from whence they returned home.
The canal is opened On 13 December 1824 the frigate HNLMS
Bellona of 44 guns passed the Willem I Lock and entered the canal. She was commanded by Captain Roepel and had a temporary draft of 16 Amsterdam feet. She was to be drawn to Nieuwdiep by 12 horses, to be rigged and armed over there.
Bellona arrived in Buiksloot after 25 minutes. On the 14th she was towed past
Ilpendam at 10 am, and passed the Lock of Purmerend at noon. She passed Spijkerboor, and reached
West-Graftdijk at 5 pm, where the frigate moored due to the extremely bad sight. On 15 December fierce winds delayed
Bellona, but by the end of the day she had reached the Zeglis at Alkmaar. On 16 December
Bellona passed through Alkmaar in the morning. Meanwhile, the three-master
Christina Bernardina of Captain H.H. Zijlstra, flag C.J.F. coming from Batavia, had arrived in Nieuwediep in early December. She had left Nieuwediep for Amsterdam on 15 December 1824, but got not further than 'De Kooi' by evening. On 16 December 1824 at four PM, the ships passes each other between the Sint Maarten and Schagen bridges. This was an event: there was music and
Christina Bernardina saluted
Bellona with 9 shots. This was a two-week journey, which was not that surprising, because many facilities like towpaths were not yet ready.
First developments Up to 1 July 1825 about 200 sea-going ships used the canal, even though many things were not ready yet. In July 1826, for example, the construction of part of the
towpaths along the canal still had to be ordered. This made it very difficult for ships to be moved along parts of the canal. Usage of the canal had also been adversely affected by drainage tests with the sea locks. Another problem was that a
wet dock had not yet been built in Amsterdam. It meant that the ships that used the canal did not find a deep water port at the end of their journey. A commission was appointed to investigate what would have to be done. In September 1826 two vessels were launched for J. Goedkoop and Comp. who founded a
shipping line from Amsterdam to Nieuwediep and Willemsoord. One vessel was called
Onderneming and measured 160 Dutch tons. By July 1831 the dykes around the two wet docks of Amsterdam (Westerdok and Oosterdok) provided shelter to the ships using them. Oosterdok had also been brought to sufficient depth for sea-going ships to reach the
Entrepotdok, where goods could be stored for transit without having to pay import taxes. The locks of the wet docks were not yet ready.
Traffic on the canal Some numbers are available about the total number of sea going ships reaching Amsterdam. For the numbers of 1826–1850 it is tempting to assume that all loaded ships that came in used the canal, but this was by far not the case. The numbers of ships passing Alkmaar is at first only about a quarter of the number of ships reaching Amsterdam, later this increased to about half the number at Amsterdam in 1840. In 1852, this was still about half. Specific numbers of incoming and outgoing ships on the canal, consistently show a significantly smaller number of outgoing ships. This is true for Alkmaar, but also for later numbers collected at specific locks. It suggests that on the return journey many empty, lightly loaded, and small enough ships, sailed the Zuiderzee, even if they had come in through the canal.
New lock at Nieuwediep and the 8-Ton Plan (1850–1858) Up till about 1850 all kinds of small improvements were made on the canal. Many of these centered on getting the desired bottom width of 10 m. Meanwhile, the size of ships increased, which was problematic for the locks. The locks were 65 m long and 15.70 m wide. At the time of construction this had been enough for any commercial ship. The Koopvaarders Lock (II 1823–1860) at Nieuwediep was only 53.30 m long and 14.10 m wide. However, this lock had an alternative route through the navy wet dock, albeit with its own limits and extra delays. The first serious works to improve the canal were the construction of a new lock for merchant shipping at Nieuwediep, and the 8-Ton Plan. Construction of the new Koopvaarders Lock (III) lock at Nieuwediep was started in 1850. It was opened on 1 July 1857. The new lock was 69.60 m long, 16.93 m wide and deep 6.00 m below summer canal level, or 6.84 m below high tide. As regards locks, the new limits were then set by: the 15.70 m width of all other canal locks, the 65 m length of the Willem I and Purmerend locks, and the 5.40 m depth of Buiksloot Flood Gate. The 8-Ton Plan was named after its budget. For 7 years, from 1852 to 1858, 113,000 guilders a year were to be spent on deepening the canal. It included making some shortcuts near Alkmaar and Ilpendam. This plan was indeed executed.
The canal becomes unsuitable Since its construction, the basic problem of the canal was that shipping lines lost two days or more when their ships passed through. A problem that was even more serious because Amsterdam did not have much to offer as return shipment. The time for passage of the canal was increased by the many bridges, the lock gates and the curves and turns in the canal. At the time the canal also froze for extended periods in winter. A 'new' problem was that the size of ships steadily increased. Even while the new lock at Nieuwediep and the 8-Ton Plan were getting executed, one knew that it would not be sufficient. A ship loaded deeper than 5,00 m would still have to partially unload at Nieuwediep, and in about 1850 the bigger sea-going ships reached a draft of 6.20 m when loaded. As a consequence, these sometimes had to unload more than half their cargo to use the canal.
Last Improvements (1856–1876) On 27 July 1856 the government appointed a commission to investigate how the Noordhollandsch Canal could be made completely suitable to the needs of commerce and navy. One of the questions it had to answer, was how it could made suitable to service the largest type of commercial ship. The commission made proposals for much larger locks, a canal of 50 m wide at the surface and 6.75 m deep, removal of the inland locks etc. One of the recommendations of the commission was the construction of a new lock next tot the existing Willem I Lock. It would become 110 m long, 18.20 m wide and 7.33 m deep below
Amsterdam Ordnance Datum and was finished on 15 December 1864. Other recommendations of the commission were the construction of two shortcuts of 92,500 and 53,000 guilders near
Koedijk in 1859 and 1860, and a shortcut near the Slochterbrug for 60,000 guilders in 1860. Furthermore, a lot of reinforcements were made on the shores, so steamers and steam tugboats could make better use of the canal. In 1864 the shortcut near the Texelse Poort in Alkmaar was made. The removal of the Purmerend lock would not be executed. By 1860 there were 6 steam vessels pulling ships on the canal. In July 1866 Gebroeders Goedkoop started Schroef-Stoom Sleepdienst Noord Holland, that towed ships along the canal using propeller driven tugboats. This was a major plus, because moving a ship by tugboat was faster than towing it with horses.
The North Sea Canal In January 1852 Amsterdam appointed a commission to investigate the construction of a canal from Amsterdam to the west, the later
North Sea Canal, between Amsterdam and
IJmuiden. It gave a positive advice in December 1852. Completed in 1876, the North Sea Canal made the Noordhollandsch Kanaal largely obsolete. == The current Noordhollandsch Kanaal ==