As of November 2022 there are four zones in the Dogger Bank Wind Farm project that are either in the pre-construction or full construction phase. They are Dogger Bank A, B & C as well as Sophia.
Dogger Bank A and B The first phase was called Dogger Bank Creyke Beck A and B. with a total installed capacity of up to 2.4 GW. Dogger Bank Creyke Beck A will cover an area of , and Dogger Bank Creyke Beck B will cover an area of . These two projects were owned by
SSE and
Equinor,
ABB was chosen for the
HVDC power transfer cables to shore. On 21 September 2020, it was announced that Dogger Bank A and B will use 190
GE Haliade-X 13 MW offshore wind turbines over both sites, meaning that 95 turbines will be used on each site. The availability of upgraded Haliade-X turbines rated at 13 MW rather than 12 MW means that each site will be capable of generating up to 1.235 GW, for a total of 2.47 GW. Turbines will be pre-assembled at Able Seaton Port in
Hartlepool, an activity that will lead to the creation of 120 skilled jobs at the port during construction. Turbine installation commenced in August 2023 at Dogger Bank A.
Power Purchase Agreements (PPA) for 15 years were signed in November 2020. Offshore cable laying started in April 2022. Installation of the turbine foundations was started in July 2022. In April 2023, SSE announced that the world's first unmanned High Voltage Direct Current (HVDC) substation had been installed at Dogger Bank A, with similar infrastructure to be completed for Dogger Bank B and C. A 107m long wind turbine blade failed during commissioning of the Dogger Bank A wind farm. Dogger Bank A wind farm is expected to be complete in the second half of 2025. As at 12 November 2025 SSE reported in its 2025 Interim Results and Strategic Update that 88 out of 95 turbines had been installed.
Dogger Bank C Dogger Bank C will use GE Haliade 14 MW turbines. Installation of the turbines is set to begin in 2025 with completion of the overall project in 2026. Similar to Dogger Bank A&B, a 15-year Power Purchase Agreement was agreed in November 2021. All output (estimated at 18 TWh/year) from A, B and C were thus in contract, a stepping stone towards financing. As a first for UK offshore wind, Dogger Bank C onshore
converter station was a winner of an auction to provide the affordable options for
reactive power to stabilize the grid and reduce grid cost. The converter will provide up to 200 megavolt amperes with a price of 0.34 £/MVAr/SP from April 2025 and ten years on.
Sofia Sofia will use 100
Siemens Gamesa 14 MW turbines. Offshore construction is set to begin in 2023 with completion of the overall project in 2026. 44 turbines use recyclable blades made in
Hull.
Dogger Bank South RWE is moving forward with two new offshore wind farms in the Dogger Bank area, Dogger Bank South West and Dogger Bank South East. Each will have a capacity of 1.5 GW generation. Following the Round 4 leasing process, RWE obtained approval from the UK Secretary of State for Business, Energy and Industrial Strategy (BEIS) to enter into an Agreement for Lease with The Crown Estate in summer 2022. In January 2026, RWE and Masdar won a
CfD auction for 3 GW to be delivered in 2030/2031 (first phase). ==Potential additional zones==