Hudson & Manhattan Railroad The PATH system pre-dates the
New York City Subway's
first underground line, operated by the
Interborough Rapid Transit Company. The Hudson & Manhattan Railroad (H&M) was planned in 1874, but it was not possible at that time to safely tunnel under the
Hudson River. Construction began on the existing tunnels in 1890, but soon stopped when funding ran out. It resumed in 1900 under the direction of
William Gibbs McAdoo, an ambitious young lawyer who had moved to New York from
Chattanooga, Tennessee, and later became president of the H&M. The railroad became so closely associated with McAdoo that, in its early years, its lines were called the McAdoo Tubes or McAdoo Tunnels.
Construction (lower left) and the
IRT Lexington Avenue Line at Astor Place (center) Construction started on the first tunnel, now called the
Uptown Hudson Tubes, in 1873. Chief engineer
Dewitt Haskin built the tunnel by using
compressed air to open a space in the mud and then lining it with brick. accidents, including a particularly serious one in 1880 that killed 20 workers, caused additional delays. The project was abandoned in 1883 due to a lack of funds. When the New York and New Jersey Railroad Company resumed construction on the uptown tubes in 1902, its chief engineer, Charles M. Jacobs, used a different method. He had workers push a
tunnelling shield through the mud and then place tubular cast iron plating around the tube. and the southern tube was built the same way. The uptown tubes were completed in 1906. By the end of 1904, the
New York City Board of Rapid Transit Commissioners had given the company permission to build a new subway line through
Midtown Manhattan to connect with the Uptown Hudson Tubes, along with 26 years of exclusive rights to the line. The Midtown Manhattan line would travel eastward under
Christopher Street before turning northeastward under
Sixth Avenue, then continue underneath Sixth Avenue to a
terminus at 33rd Street. In January 1905, the Hudson Companies, with $21 million in capital ($ in ), were incorporated to complete the Uptown Hudson Tubes and build the Sixth Avenue line, as well as construct a second pair of tunnels, the current
Downtown Hudson Tubes. The H&M was incorporated in December 1906 to operate a passenger railroad system between New York and New Jersey via the Uptown and Downtown Tubes. The current Downtown Hudson Tubes were built about south of the first one. Three years of construction using the tubular cast iron method finished in 1909. The eastern sections of the tunnels, in Manhattan, were built with the
cut and cover method.
Opening in Newark was the H&MRR's terminus until the completion of Newark Penn Station in the late 1930s. Test runs of empty trains started in late 1907. Revenue service started between
Hoboken Terminal and 19th Street at midnight on February 26, 1908, when President
Theodore Roosevelt pressed a button at the
White House that turned on the electric lines in the uptown tubes (the first train carrying passengers, all selected officials, had run the previous day). This became part of the current
Hoboken–33rd Street line. The H&M system was powered by a 650-
volt direct current third rail which, in turn, drew power from an 11,000-volt
transmission system with three substations. The substations were the
Jersey City Powerhouse, as well as two smaller substations at the
Christopher Street and
Hudson Terminal stations. In July 1909, service began between the Hudson Terminal in
Lower Manhattan and
Exchange Place in Jersey City, through the downtown tubes. The connection between Exchange Place and the junction near
Hoboken Terminal opened two weeks later, forming the basic route for the Hoboken-Hudson Terminal (now
Hoboken–World Trade Center) line. A new line running between 23rd Street and Hudson Terminal was created in September. and the 23rd Street–Hudson Terminal line was rerouted to Grove Street, becoming part of the current
Journal Square–33rd Street line. A fourth line, Grove Street–Hudson Terminal (now the
Newark–World Trade Center line), was also created. The Grove Street–Hudson Terminal line was extended west from
Grove Street to
Manhattan Transfer in October 1911, and then to
Park Place in
Newark on November 26 of that year. After completion of the uptown Manhattan extension to 33rd Street and the westward extension to the now-defunct Manhattan Transfer and Park Place Newark terminus in 1911, the H&M was complete. A stop at
Summit Avenue (now Journal Square), located between Grove Street and Manhattan Transfer, opened in April 1912 as an
infill station on the Newark-Hudson Terminal line, though only one platform was in use at the time. The station was completed by February 1913, allowing service from 33rd Street to terminate there. In 1908, McAdoo proposed to build a branch of the H&M southward to the
Central Railroad of New Jersey Terminal at
Communipaw. When the rapid transit commissioners approved construction of the H&M's Sixth Avenue line in 1904, they left open the option of digging an east-west crosstown line. The New York and New Jersey Railroad Company received perpetual rights to dig under Christopher and
Ninth Streets eastward to either
Second Avenue or
Astor Place. The openings of the 28th and 33rd Street stations were delayed because of planning for the Grand Central extension.
The New York Times speculated that the downtown tunnels would see more passenger use than the uptown tunnels because they better served
the city's financial district. As an alternative, it was proposed to connect the Uptown Tubes to the Steinway Tunnel. A franchise to extend the Uptown Tubes to Grand Central was awarded in June 1909. By 1914, the H&M had not yet started construction of the Grand Central extension, and requested a delay. The Rapid Transit Commissioners declined the last one, effectively ending the H&M's rights to a Grand Central extension. The franchise for the Broadway line was ultimately awarded to the
Brooklyn Rapid Transit Company (BRT) in 1913, as part of the
Dual Contracts. In 1909, McAdoo considered extending the H&M in New Jersey, building a branch north to
Montclair, in
Essex County. A route extending north from Newark would continue straight to
East Orange. From there, branches would split to
South Orange in the south and Montclair in the north.
Decline and bankruptcy A record 113 million people rode the H&M in 1927. The opening of the
George Washington Bridge in 1931 and the
Lincoln Tunnel in 1937 drew more riders out of trains and into their cars. The 33rd Street terminal was moved south to 32nd Street and reopened in 1939. The city had to pay the railroad $800,000 to build the new 33rd Street station; it reimbursed H&M an additional $300,000 for lost revenue. The 28th Street station was closed at this time as unnecessary since the southern entrances to the 33rd Street terminal were only two blocks away; it was later demolished to make room for the IND tracks below. The
Manhattan Transfer station was closed in mid-1937, and the H&M realigned to Newark Penn Station from the Park Place terminus a quarter-mile () north; the Harrison station across the
Passaic River was moved several blocks south as a result. The upper level of the Centre Street Bridge to Park Place later became
Route 158. Promotions and other advertising failed to stem the financial decline of the H&M. The 19th Street station in Manhattan was closed in 1954. That year, the H&M entered receivership due to its constant losses. It operated under
bankruptcy protection; in 1956 the two states agreed to settle its unpaid back taxes for $1.9 million. That year, the H&M saw 37 million annual passengers, and transportation experts called for subsidies. One expert proposed a "rail loop", with the Uptown Hudson Tubes connecting to the IND Sixth Avenue Line, then continuing up Sixth Avenue and west via a new tunnel to
Weehawken, New Jersey. By 1958, ridership had dropped to 30.46 million annual passengers. Two years later, creditors approved a reorganization plan. During this time, H&M workers went on strike twice over wages: for two days in 1953, and for a month in 1957.
Port Authority takeover In the early 1960s,
planning for the
World Trade Center resulted in a compromise between the Port Authority and the state governments of New York and New Jersey. The Port Authority agreed to purchase and maintain the Tubes in return for the rights to build the World Trade Center on the footprint of H&M's Hudson Terminal, which was the Lower Manhattan terminus of the Tubes. A formal agreement was made in January 1962; four months later, the Port Authority set up two wholly owned subsidiaries: the Port Authority Trans-Hudson Corporation (PATH) to operate the H&M lines, as well as another subsidiary to operate the World Trade Center. All of the Port Authority's operations would have been subjected to federal
Interstate Commerce Commission rules if it ran the trains directly, but with the creation of the PATH Corporation, only the subsidiary's operations would be federally regulated. In September, the Port Authority formally took over the H&M Railroad and the Tubes, rebranding the system as
Port Authority Trans-Hudson (PATH). Upon taking over the H&M, the PANYNJ spent $70 million to modernize the system's infrastructure ($ in ). The PANYNJ also repainted H&M stations into the new PATH livery. In 1964, the authority ordered 162 PA1 railway cars to replace the H&M rolling stock, much of which dated to 1909. The first PA1 cars were delivered in 1965. During excavation and construction, the original Downtown Hudson Tubes remained in service as elevated tunnels. The new terminal, west of the Hudson Terminal, opened in 1971. It cost $35 million to build, and saw 85,000 daily passengers at the time of its opening. Hudson Terminal was then shut down. In January 1973, the Port Authority released plans to double the route mileage of the PATH system with an extension from Newark Penn Station to
Plainfield, New Jersey. A stop at
Elizabeth would allow PATH to serve
Newark Airport, where passengers could transfer to a
people mover serving the terminals. Preliminary studies of the
right-of-way, as well as a design contract, were conducted that year. The extension was approved in 1975. The
Federal Urban Mass Transit Administration was less enthusiastic about the extension's efficacy and reluctant to give the Port Authority the $322 million it had requested for the project, about 80% of the projected cost. Eventually, the administration agreed to back it, but in 1977, the
U.S. Supreme Court ruled that the two state legislatures had violated the
U.S. Constitution's
Contract Clause by repealing a
covenant in the 1962 bond agreements in order to make the extension possible. In June 1978, the extension, by then estimated to cost $600 million ($ in ), was canceled in favor of improving bus service in New Jersey.
Strikes Labor problems also beset PATH during this time. talks failed and workers walked out in April. A month into the strike, negotiations broke down again; the union returned to work in June. The
1980 New York City transit strike suspended service on the
New York City Transit Authority (NYCTA)'s bus and subway routes for 10 days. A special PATH route ran from 33rd Street to World Trade Center via Midtown Manhattan, Pavonia–Newport, and Exchange Place during the NYCTA strike. PATH motormen also threatened to go on strike during this time for different reasons. The special service was suspended in April after some workers refused
overtime. In June 1980, PATH workers again went on strike for higher pay, their first such action since 1973. During the strike, moisture built up in the tunnels and rust accumulated on the tracks; pumps in the underwater tunnels remained in operation, preventing the tubes from flooding. Alternative service across the Hudson River was provided by "inadequate" shuttle buses through the
Holland Tunnel. The 81-day strike
1980s and 1990s Substantial growth in PATH ridership during the 1980s required expansion and improvement of the railroad's infrastructure. The Port Authority announced a plan in 1988 that would allow stations on the Newark–WTC line to accommodate longer eight-car trains while seven-car trains could operate between Journal Square and 33rd Street. Two years later, it announced a $1 billion plan to renovate the PATH stations and add new cars. Video monitors were installed in stations to make money from advertising. PATH also sought a fare hike, even though that would reduce its per passenger subsidy, to reduce its $135 million annual deficit. By 1992, the Port Authority had spent $900 million on infrastructure improvements, including repairing tracks, modernizing communications and signaling, replacing ventilation equipment, and installing elevators at seven stations per the
Americans with Disabilities Act of 1990 (ADA). A $225 million car maintenance facility was opened in Harrison in 1990. It replaced PATH's old Henderson Street Yard—a below-grade, open-air train storage yard at the northeast corner of Marin Boulevard and Christopher Columbus Drive just east of the Grove Street station. High tides from the
December 1992 nor'easter flooded the PATH tunnels, including a section between Hoboken and Pavonia. Some water pumps within the system were overwhelmed. A section of ceiling in the World Trade Center PATH station collapsed and trapped dozens during the
1993 World Trade Center bombing; the station itself did not suffer any structural damage. Within three days, PATH service to the station resumed. In the summer of 1993, the Port Authority banned tobacco advertisements in all trains and stations. A new wash for cars opened in mid-September 1993 in Jersey City, replacing the one at the 33rd Street terminal. In April 1994, an ADA-compliant entrance to the Exchange Place station was opened. Two years later, three trains began running express on the Newark–World Trade Center service for six months, cutting running time by 3 minutes. Weekend Hoboken–World Trade Center service began in October 1996 on a six-month trial basis, and the express Newark–World Trade Center service was made permanent on the same day.
21st century September 11, 2001, and recovery The
World Trade Center station in Lower Manhattan, under the World Trade Center, one of PATH's two New York terminals, was destroyed during the
September 11 attacks, when the
Twin Towers above it collapsed. Just prior to the collapse, the station was closed and all passengers evacuated.
Exchange Place, the next-to-last station before World Trade Center, had to be closed as well because trains could not turn around there; it had also suffered severe water damage. Shortly after the attacks, the Port Authority started operating two uptown services: Newark–33rd Street and Hoboken–33rd Street, and one intrastate New Jersey service, Hoboken–Journal Square. The new
Exchange Place station opened in June 2003. Because of the original alignment of the tracks, trains to or from Hoboken used separate tunnels from the Newark service. Eastbound trains from Newark crossed over to the westbound track just west of Exchange Place, where they reversed direction and used a
crossover switch to go to Hoboken. Eastbound trains from Hoboken entered on the eastbound track at Exchange Place, then reversing direction and used the same crossover switch to get on the westbound track to Newark before entering Grove Street. A new entrance on Vesey Street opened in March 2008; the Church entrance was demolished. in April 2016 The construction of the permanent four-platform
World Trade Center Transportation Hub started in July 2008, when the first prefabricated "ribs" for the pedestrian walkway under Fulton Street were installed. Platform A, the first part of the permanent station, opened in February 2014, serving Hoboken-bound riders. Platform B and the remaining half of Platform A opened in May 2015. The hub formally opened in March 2016 with part of the headhouse. Platforms C and D, the last two, were opened that September. An image captured by a PATH security camera showing water flowing into Hoboken during the storm
went viral online and became one of several representative images of the hurricane. The first PATH trains after the hurricane were the
Journal Square–33rd Street service, which resumed on November 6 and ran only in daytime. Service was extended west to Harrison and Newark on November 12, in place of the
Newark–World Trade Center service. Christopher Street and Ninth Street were reopened during the weekend of November 17–18, but remained closed for five days afterward. Normal weekday service on the Newark–World Trade Center and Journal Square–33rd Street lines resumed on November 26. On weekends, trains operated using the Newark–33rd Street service pattern. The PATH station at Hoboken Terminal suffered major damage after floodwaters as high as submerged the tunnels; it was closed for several weeks for $300 million worth of repairs. The Newark–33rd Street route was suspended for two weekends in mid-December, with the Newark–World Trade Center running in its place, in order to expedite the return of Hoboken service. Hoboken Terminal reopened in December for weekday daytime Hoboken–33rd Street service, followed by the resumption of weekday 24-hour PATH service in early 2013. The Hoboken–World Trade Center trains resumed in late January, and all normal service was restored by March. The Downtown Hudson Tubes were severely damaged by Sandy. As a result, to accommodate repairs, service on the Newark–World Trade Center line between Exchange Place and World Trade Center was to be suspended during almost all weekends, except for holidays, in 2019 and 2020. However, weekend service was restored in June 2020, six months ahead of schedule.
2010s improvements The Port Authority began rebuilding the
Harrison station in 2009. It has longer and wider platforms to allow 10-car trains; street-level-to-platform elevators within the platform extensions, in compliance with the ADA, and architectural modifications. The westbound platform of the new Harrison station opened to the public in October 2018 and the eastbound one the following June. In January 2010,
Christopher O. Ward, as executive director, announced that PATH would be spending $321 million on
communications-based train control (CBTC) with
Siemens'
Trainguard MT, upgrading its
signal system for an increase in ridership. CBTC would replace a four-decade old fixed-
block signaling system. The Port Authority also spent $659 million to upgrade 13 platforms on the Newark–World Trade Center line to accommodate 10-car trains; until then, the line could only run eight-car trains. The Newark–World Trade Center line west of Journal Square was converted to PTC in April 2018, followed by the segments of track east of Journal Square the following month. This caused delays across the entire system when train operators had to slow down and manually adjust their trains to switch between the two signaling systems. PTC was tested on the Uptown Hudson Tubes from July to October 2018, forcing weekend closures. and the entire system was converted by December. The Port Authority also installed two amenities in all PATH stations. Cellphone service was added for all customers by early 2019. Countdown clocks, displaying the time the next train arrives, were installed in all PATH stations that year. Subsequently, in June 2019, the Port Authority released the PATH Improvement Plan, calling for over $1 billion in investments, including $80 million to extend Newark–World Trade Center line platforms, as well as funding for two ongoing projects: $752.6 million to complete the CBTC system by 2022 and $215.7 million on the new PA5 cars by 2022. The goal is to increase train frequencies on the Newark-World Trade Center line by 40 percent, and 20 percent on other lines, during rush hours. Every train on the Newark–World Trade Center line would be nine cars long. In addition, the platform at Grove Street would be extended eastward, at the Marin Boulevard end of the station, and two additional cross-corridors would be added at Exchange Place. The Port Authority would also allocate funds to study the implementation of 10-car trains. In September 2019, service on the Newark–World Trade Center and Journal Square–33rd Street lines would be increased by 10 percent during rush hours, reducing the headway between trains from four minutes to three. Train service returned to 96 percent of 2019 levels in June 2020, yet ridership continued to lag far below pre-pandemic numbers, rebounding to only 60 percent of 2019 ridership by February 2022. Amid the spread of the
Omicron variant, PANYNJ was projected to reach $3 billion in pandemic losses by March 2022. The platform-lengthening project was finished the same year. In February 2023, it was announced that nine-car operation on the Newark–World Trade Center line would begin the next month; nine-car trains began operating on March 22, 2023. PANYNJ commissioners voted in late 2023 to spend $230 million replacing some wheel sets on the PA5 fleet and replacing tracks on the New Jersey side. In 2024, the PANYNJ announced that it would spend $430 million to refurbish four stations and replace railroad switches as part of the PATH Forward program. In addition, the agency announced that the Hoboken Terminal station would be closed and extensively refurbished during February 2025. As part of its 2026–2035 capital plan, the PANYNJ announced in November 2025 that it would increase weekend service, with all four weekday lines running during the weekend, and that fares would incrementally increase annually from $2.90 to $4.00 by 2029. In 2026, the PANYNJ announced that it would replace turnstiles at all PATH stations for $3.5 million. The PATH Forward improvements were completed in late April 2026. The weekend service changes effect on May 17, 2026. estimated at that time to cost $500 million; the study began in 2012. In September 2013, ''
Crain's'' reported that New Jersey Governor
Chris Christie would publicly support the extension, estimated by then to cost $1 billion. The governor asked that the airport's largest operator,
United Airlines, consider flying to
Atlantic City International Airport as an enticement to further the project. In February 2014, the Port Authority's Board of Commissioners approved a 10-year capital plan that included the PATH extension to
NJ Transit's
Newark Liberty International Airport Station. The alignment would follow the existing
Northeast Corridor approximately one mile (1.6 km) further south to the Newark Airport station, where a connection to
AirTrain Newark is available. In late 2014, there were calls for a reconsideration of Port Authority funding priorities. The PATH extension followed the route of existing Manhattan-to-Newark Airport train service (on NJ Transit's
Northeast Corridor Line and
North Jersey Coast Line as well as Amtrak's
Keystone Service and
Northeast Regional). On the other hand, there was no funding for either the
Gateway Tunnel, a pair of commuter train tunnels that would supplement the
North River Tunnels under the Hudson, or the replacement for the
Port Authority Bus Terminal. In December 2014, the PANYNJ awarded a three-year, $6 million contract to infrastructure design firm
HNTB to do a cost analysis of the Newark Airport extension. In 2017, the PANYNJ released a 10-year capital plan that included $1.7 billion for the extension; at the time, construction was projected to start in 2020, with service in 2025. A presentation at two December 2017 public meetings showed the new PATH station would include a
park-and-ride lot and a new entrance from the nearby
Dayton neighborhood. An extension of the PATH to Newark Airport was still being considered in mid-2022, but the PANYNJ announced in March 2023 that it was deferring funding for the Newark Airport extension to a future capital plan. In December 2025, the PANYNJ announced that the Newark Airport PATH extension would be delayed by ten years because the agency was prioritizing the ongoing replacement of the
AirTrain Newark.
Marion station proposal West of
Journal Square in Jersey City, the NWK-WTC line runs through the
Marion Section parallel to the
Conrail Passaic and Harsimus Line freight line. A pedestrian bridge crosses the tracks. Since the 1980s, there have been calls for an
infill station to be built there. In 2018, the government of Jersey City and the PANYNJ reached an agreement that included a
feasibility study for a potential station, which resulted in the "Marion PATH Station Physical Feasibility Study". The senior
U.S. Senator, the
Hudson County Executive, and the
Mayor of Jersey City have written letters encouraging the PANYNJ to continue with the project. The estimated cost of construction varies and could be funded by nearby real estate developers. == Route operation ==