The first crossing at the site of the bridge was established in the 11th century by
Margaret,
queen consort of King
Malcolm III, who founded a ferry service to transport religious pilgrims from Edinburgh to
Dunfermline Abbey and
St Andrews. Its creation gave rise to the port towns of Queensferry and North Queensferry, which remain to this day; the passenger ferry service continued without interruption for over 800 years. There were proposals as early as the 1740s for a road crossing at the site, although its viability was only considered after the
Forth Bridge was built in 1890. The importance of the crossing for vehicular traffic was underpinned when the
Great Britain road numbering scheme was drawn up in the 1920s. The planners wished the arterial
A9 road to be routed across the Forth here, although the unwillingness to have a ferry crossing as part of this route led to the
A90 number being assigned instead. There was more lobbying for a road crossing in the 1920s and 1930s, when the only vehicle crossing was a single passenger and vehicle ferry. Sir
William Denny championed the expansion of that service in the 1930s, providing and operating on behalf of the
London and North Eastern Railway two additional ferries to supplement the nearby railway bridge. Due to their success, two more ferry boats were added in the 1940s and 1950s, by which time the ferries were making 40,000 crossings annually, carrying 1.5 million passengers and 800,000 vehicles.
Design With the then newest and nearest bridge spanning the Forth (the
Kincardine Bridge, built in 1936) still around upstream, the upsurge in demand for a road crossing between Edinburgh and Fife prompted the
UK Government to establish the '
(FRBJB) by an act of Parliament, the ' (
10 & 11 Geo. 6. c. iv) to oversee the implementation of a new bridge to replace the ferry service. The authorities on both sides investigated in 1955, and drew up an alternative scheme for a tunnel beneath the estuary. This was known as the Maunsell Scheme, and was projected to run somewhat closer to the rail bridge than the present road bridge. The scheme was abandoned as too ambitious, and a bridge was built instead.
Construction , 2020 The final construction plan was accepted in February 1958 and work began that September.
Mott, Hay and Anderson and
Freeman Fox & Partners carried out the design work and a joint venture of
Sir William Arrol & Co.,
Cleveland Bridge & Engineering Company and
Dorman Long constructed the bridge at a cost of £15.1 million. The resident design engineer was John Alexander King Hamilton
FRSE (1900–1982). It was the longest steel suspension bridge in Europe. It used 210,000 tons of concrete, with of
grade-separated dual-carriageway
approach roads.
Reed & Mallik built the approach viaducts. Twenty-four individual bridges were built for the approach roads. The southern approach road of the A90 began at Cramond Bridge, over the
River Almond on the western outskirts of Edinburgh, near
Craigiehall. There were two-level interchanges built at Burnshot, Dolphington (B924) and the Echline junction (
A904 and B800). At
Dalmeny there was a bridge over the
railway. The southern approach roads were built by A.M. Carmichael Ltd. The northern approach road had three two-level junctions at Ferry Toll (for the B980), Admiralty (for
Rosyth Dockyard via the
A985, and
Inverkeithing via the
A921) and at Mastertown/Masterton (for what would be the fledgling M90 southern terminus). The Masterton junction was an octopus junction, a variation of a
clover-leaf junction, with six bridges and a 600 ft viaduct. There were fifteen bridges built for this approach road. The northern approach road terminated as the
A823(M) at a roundabout with the
A823 south of Dunfermline, next to
Rosyth railway station. The northern approach roads were built by Whatlings Ltd of Glasgow, later bought by
Alfred McAlpine. Seven people died during construction before the bridge was opened by
Queen Elizabeth II and the
Duke of Edinburgh on 4 September 1964. The ferry service was discontinued as of that date.
Operation The bridge's management was delegated to the FRBJB, and remained so until 2002 when its operation was transferred to a new body with a wider remit, the
Forth Estuary Transport Authority. On 1 December 2010, the bridge was closed for the first time due to heavy snow. After several accidents meant snowploughs were unable to clear the carriageways, the bridge was closed in both directions at 6.40 a.m. and remained closed for several hours. As part of celebrations of the 50th anniversary of the bridge's operation, artist
Kate Downie was commissioned to create a print of the bridge and hold an exhibition of works portraying it. On 1 June 2015,
Amey took over the maintenance and operating of the bridge on behalf of Transport Scotland from the Forth Estuary Transport Authority, and are now called the Forth Bridges Unit.
Structural issues Forth Estuary Transport Authority (FETA) began to be concerned over the structural wear of the bridge in the early years of the 21st century. The planned theoretical capacity for the bridge (30,000 vehicles per day in each direction) was routinely exceeded as traffic levels outstripped predictions. The
Scottish Government stated in 2006 that 60,000 vehicles travelled on more than half the days in a year. In 2003, an inspection programme was launched (costing £1.2 million) to assess the condition of the main suspension cables after corrosion was discovered in a number of older bridges in the United States of a similar design and size. The study was completed two years later and reported that the main cables had suffered an 8%–10% loss of strength. This weakening was projected to accelerate, with traffic restrictions to limit loading required in 2014 in the worst-case scenario, followed by full closure by 2020. An acoustic monitoring system was commissioned in August 2006, using listening devices to monitor any further strands snapping and pinpoint their location within the main cables. In January 2006, the Scottish Executive completed a third-party audit on the bridge which concluded that FETA had performed the initial internal inspection and cable strength calculation in accordance with accepted practice. The report suggested that traffic restrictions could be required by 2013. Several actions were taken to increase the bridge's lifespan. These included a
dehumidification programme that slowed the rate of corrosion in the main cables by keeping air in the voids between the main cables' strands below 40% humidity. Engineering consultants
Faber Maunsell began work on the project in 2006; it took two and a half years to complete at a cost of £7.8 million. As part of the works, some of the corroded cable strands were
spliced. The southbound carriageway of the bridge was closed on 1 December 2015, with all traffic using a single lane each way on the northbound carriageway after steelwork defects had been discovered during routine inspections, and traffic was restricted to 7.5 tonnes or less (public service vehicles excepted). On 4 December, the bridge was fully closed when further structural faults were found. It was initially not expected to reopen until January 2016, and Transport Scotland began work to lay on extra trains and buses and considered whether to reintroduce a ferry service to mitigate the impact on travellers. On 23 December, the bridge was reopened for all traffic except
heavy goods vehicles (HGVs). On 4 February, it was announced this had been pushed back to March, due to further problems with the truss end link pins in the southern towers, which required additional remedial work. However, a limited number of HGVs were allowed to cross, in a northbound direction only, between 11 pm and 4 am each night. On 20 February 2016, the bridge was fully reopened.
2016 public inquiry On 20 January 2016, the Scottish Parliament began an inquiry led by the Infrastructure and Capital Investment Committee (ICI) to determine the circumstances that led to the discovery of a cracked truss in the bridge's undercarriage. Evidence was heard from FETA, Transport Minister Derek Mackay, engineers and officials from Amey along with a number of other experts and key personnel. On the first day, Richard Hornby, of engineering consulting firm
Arup, stated that the truss end in question had been inspected 23 times since 2001, and no fault had been found. It was revealed that a pin had seized up, which caused the truss end to crack, and it was only the quality of the steel which had stopped its cracking appearing earlier. Hornby also made clear that even if the seized pin had been picked up earlier, it was "virtually impossible" to lubricate the bearing. Several witnesses defended a decision by previous operator FETA not to proceed with a £15 million truss end link replacement project in 2010. This was disputed by Barry Colford, former chief engineer and bridgemaster at FETA. Lesley Hinds, FETA's former convener, pointed out that the bridge budget had been cut by 58% in 2011, while senior staff at FETA had "deep concerns" about the transfer of bridge management to a private company.
New crossings and change of use , the newer road bridge crossing the Firth of Forth, is shown in the background. The strategic transport importance of the road bridge and the threat of closure by 2020 if major structural work were not undertaken led to fears of serious economic consequences. Increasing traffic levels across the Firth of Forth had also led to the construction of the
Clackmannanshire Bridge adjacent to the existing
Kincardine Bridge. This bridge opened in November 2008. Proposals for a second road crossing at Queensferry had been made in the 1990s, but were shelved, despite preliminary work on route selection. Following the discovery of potentially serious structural issues with the Forth Road Bridge in 2005 the proposals were revisited and plans advanced. The decision to proceed with a replacement bridge was taken at the end of 2007, and it was announced the following year that the existing bridge would be retained as a public transport link. The Forth Crossing Act received Royal Assent in January 2011, and the new bridge was opened in late 2017. On 1 February 2018, the Forth Road Bridge became a Public Transport Corridor, with all approach roads in full operation. The bridge was closed between September and mid October 2017 for roadworks before partially reopening for public buses. As of December 2020, work was underway that would allow the Forth Road Bridge to become an emergency diversion route for private transport. The Queensferry Crossing has proofing that makes it less vulnerable to high winds than the Forth Road Bridge, but it was closed for the first time in February 2020 due to accumulations of ice on its towers. The service was terminated in December 2024 due to lack of interest. ==Statistics==