Sections of the Purple Line were opened as below:
Phase I Civil construction work on Phase I of the line began on 15 April 2007 and was originally scheduled to be completed in 5 years. However, the project faced delays and missed several deadlines. Difficult tunnel boring conditions through a mixed geology with hard rock caused major delays. The first stretch of Purple Line (Reach 1, fully elevated) between
Baiyyappanahalli and Mahatma Gandhi Road was inaugurated on 20 October 2011. Reach 2 (fully elevated) between Mysore Road and Magadi Road commenced operations on 16 November 2015. These two sections operated independently until the final section, the underground stretch between Mahatma Gandhi Road and City Railway station was opened on 30 April 2016, thus linking the previously opened stretches and completing Phase I. Costs for the Purple Line were estimated at 4500–5000 crores. The cost of the underground stretch alone amounted to about . Land acquisition for Phase I of the project cost . BMRCL secured through long-term loans and by selling bonds, while the remaining project cost was funded by the central and state governments. Loans were secured from several agencies: from the
Japan International Cooperation Agency (JICA), from the
Housing and Urban Development Corporation Limited (HUDCO), from the
Asian Development Bank (ADB), and the rest from a French lending agency. Approximately 10% of the 6500 crore was to be paid as interest by BMRCL each year. The Federation of Karnataka Chambers of Commerce and Industry (FKCCI) had estimated that interest payment alone would be ; however, BMRCL stated that it was not as high but "definitely more than per day". Two Japanese TBMs,
Helen and
Margarita, were used for tunneling work of the Purple Line. Tunneling work began in May 2011 and completed in May 2014. Underground stations (City railway station, Sir M Visvesvaraya, Vidhana Soudha and Cubbon Park) were built by the
cut-and-cover method which required 10,000 controlled blasts using of explosives of 125 gm gel nitrate capsules due to hard granite rock. A total of 2500 trees were cut down during the construction of both lines of Phase I. Reach 1 was originally scheduled to begin operations in March 2010. After missing several deadlines, it was finally opened to the public on 20 October 2011 at 4 pm
IST by
Union Urban Development Minister Kamal Nath. There was an overwhelming response to the metro at the commencement of operations; as per BMRCL sources, within the first three days of operations, people used the mass transit system. At the end of the 4th day, about 200,000 passengers had already commuted on Namma Metro. Namma Metro's first 12-day cumulative revenue was . During the first month, about 1,325,000 people traveled by metro. On average, 41,390 people took the train every day, while the average daily revenue was . BMRC earned a revenue of in its first month of operation. However, average ridership during the first six months of operation was just 24,900 after the initial rush. BMRCL earned a total of during the same period. Namma Metro posted a profit of after almost one year of operating Reach I. BMRCL estimates that nearly 8 million passengers traveled on the system during its first year of operations. Reach 2 received clearance to start services from Satish Kumar, the Commissioner for Metro Rail Safety, on 21 September 2015. Reach 2 was opened to the public on 16 November 2015. BMRCL applied for safety clearance to open the underground stretch in the third week of March 2016. The Commissioner for Railway Safety (CRS) granted clearance to begin operations on the underground section in the first week of April 2016. The underground section was inaugurated by Union Urban Development Minister
M. Venkaiah Naidu, Chief Minister
Siddaramaiah and other dignitaries at a ceremony at the
Vidhana Soudha on 29 April 2016. The inaugural train through the underground section departed from Vidhana Soudha station at 6:35 pm. The section was opened to the public from 6 am on 30 April 2016. Trains ran until 10 pm on the opening day, making 115 trips and transporting about 93,500 passengers, earning BMRCL a revenue of . The following day, 120 trips were operated on the Purple line, transporting about 125,000 passengers. On the first two days of operation, after opening of the underground section, BMRCL collected over 7 million in revenues from the Purple Line.
Phase II In October 2016, the BMRCL began civil work on the west extension of the Purple Line from
Mysuru Road to
Kengeri (8.81 km), later extended to
Challaghatta.
IL&FS Engineering Construction Company won the contract for Reach 2A of 3.94 km from Mysuru Road to
Pattanagere, including four stations, at 327 crore. Soma Enterprise won the contract for Reach 2B of 4.86 km from Pattanagere to Kengeri, later extended to Challaghatta, including two stations and a depot at Challaghatta at 332 crore. The land needed for the depot at Challaghatta, about 1.5 km away from Kengeri station, was already owned by BMRCL. Later, the line extension included a new station at Challaghatta, close to the depot. BMRCL floated tenders for the construction of the 15.5-km elevated stretch from
Baiyyappanahalli to Whitefield railway station in December 2016. Reach 1A is an 8.03 km section from
Baiyyappanahalli to
Seetharamapalya, including six new stations, and is estimated to cost 670.72 crore. Reach 1B, the 7.21 km section from
Kundalahalli to
Whitefield (Kadugodi), includes seven new stations and is estimated to cost 666.12 crore.
Italian-Thai Development was awarded the contracts for both packages, for a sum of in May 2017. Around 270 buildings were demolished for the construction of Reach 1A and 1B. BMRC spent an estimated 849 crore to acquire properties. Demolition work began in March 2017, and construction work began in February 2018. The extension from Mysore Road to Kengeri towards the southwest opened on 30 August 2021 and the extension from
Krishnarajapura to
Whitefield (Kadugodi) towards the east opened on 26 March 2023. Later, trial runs began from Baiyappanahalli to Krishnarajapura with one station in between (
Benniganahalli) on 26 July 2023 and from Kengeri to
Challaghatta on 29 July 2023. On 9 October 2023, both the sections were opened for general use, making the whole line operational from
Whitefield (Kadugodi) to
Challaghatta.
Phase III In November 2023, the Government of Karnataka announced that it planned to extend the Purple Line till
Hoskote,
Bengaluru North District eastwards and
Bidadi and
Ramanagara district headquarter in
Bengaluru South (Ramanagara) District westwards in the future. ==Stations==