After the Civil War, in the late 1860s, Congress belatedly realized the military importance of having easily navigable waterways, and charged the Army Corps of Engineers with clearing Hell Gate of the rocks there that caused a danger to navigation. According to a January 1867 Corps report, deepening the channel from would cost $18,000, about half the cost of the annual loss in shipping. A steam-powered drilling
scow, with a hole to accommodate 21 drills, was used to remove the rocks in the middle of the channel. It was first used on Diamond Reef in the spring of 1869; a number of holes were drilled into the rock, into which charges of
nitroglycerin were inserted. Coenties Reef followed in 1871 with 17 surface blasts, and 39 surface blasts two years later; it was broken up with of nitroglycerin. Congress failed to include Diamond Reef in its 1875 appropriation, and debris removal was suspended. The scow was towed to Frying Pan Rock in 1872, where 11 surface blasts were made. Removal of the Hallett's Point reef began in August 1869; the reef was an irregular semi-
ellipse about . Producing
eddies on both sides (influenced by tidal currents), it was a danger to shipping. A wood
cofferdam was fastened to the rocks, and the water was pumped out about to accommodate a
shaft; work was then suspended because its funding had run out. Work resumed in July 1870, and the shaft was sunk to below mean low water. The rock was hand-drilled that year, with removed. Steam-powered equipment was added the following year, speeding up the work. Thirty thousand cubic yards of underwater broken stone were removed by
dredging. A scale model of the excavation was exhibited at Philadelphia's 1876
Centennial Exposition. The Hallet's Point reef's upper surface was surveyed in detail in 1871. Several explosives were tested. That year's appropriation was $225,000, half the amount requested. The following year, $600,000 was requested, less than half of which was granted. Work was suspended in mid-November 1873 due to lack of funds, although the excavation was nearly completed. A chain of explosions was planned which would minimize vibration in nearby
Astoria, and on Ward's and Blackwell's Islands. After blasting, the rocks were hauled by a mule-driven wagon to dump cars.
1876 explosion Until mid-1874, nitroglycerin had been principally used for blasting purposes;
mica powder, giant powder, rend-rock, and vulcan powder (all nitroglycerin compounds) were also used. None were as powerful as nitroglycerin, but were less expensive. After the holes were charged with tin canisters, priming charges in brass tubes were inserted. Brass was preferred to tin because of its greater durability in salt water and better protection against leakage. The primers also contained groups of 20 fuses as detonators. The connecting wires were 18-
gauge copper (), insulated with
guttapercha, for a total diameter of 9 gauge (). The lead and return wires were 12-gauge (), insulated with two coats of guttapercha, for a total size of 4 gauge (). The batteries were 40, 43, and 44 zinc-and-carbon cells, divided into 23 batteries. Each battery would fire 160 fuses in a divided circuit: eight groups of 20 each. The explosion began shortly after 2:50 p.m. on September 24, 1876. There was no damaging shock in the air, the water, or underground. The spray and gases reached a height of , but no windows broke. The underground shock was minor, but was felt in Manhattan and Brooklyn. Some plastering was dislodged from a ceiling in a house and in two houses from the site. One lesson learned from the detonation was that moderate charges, confined in rock and cushioned by water, would not damage surrounding objects. ==See also==