Under the act, contractors are required to submit and certify that the
cost or
pricing data provided to the government is accurate, complete, and current as of the date of the price agreement. These requirements apply to negotiated
contracts,
subcontracts, and modifications where there is a lack of "adequate price competition". As of October 1, 2025, the threshold for submitting certified cost or pricing data was adjusted for inflation to $2.5 million for awarded contracts. Following the 2026 National Defense Authorization Act, the threshold for certification was raised to $10 million for contracts entered after June 30, 2026. Contractors are generally required to flow these thresholds down to subcontractors unless a specific exemption applies.
Defective pricing The act provides the government a statutory right to a downward
price adjustment, including
interest, if it is discovered that the contractor's certified data was defective at the time of the agreement. A
defective pricing claim does not require the government to prove intent to deceive; it only requires proof that the data was not accurate, complete, or current, and that the government relied on that data to its financial detriment.
Certification and disclosure A '''''' is a signed statement from a
bidder stating that, to the best of the bidder's knowledge and belief, the costs or pricing data which they have submitted in a
tender are accurate, complete and current at the time. TINA requires that contractors submitting bids should supply certified cost or pricing data before an agreement on price for most negotiated
procurements for government contracts worth more than $750,000 for prime contracts awarded before July 1, 2018, and $2 million for prime contracts awarded on or after July 1, 2018 and beforer June 30, 2026. A form for a certificate of current cost or pricing data submission is available in the
Federal Acquisition Regulation (FAR) at section 15.406-2.
Scope The requirement for a certificate of cost or pricing data may also apply to
sub-contractors at any tier in the
supply chain. Certified cost or pricing data may not be obtained for acquisitions at or below the
simplified acquisition threshold. Other exceptions are stated in FAR 15.403-1(b) or may be adopted under a waiver requested by the
contracting officer in exceptional circumstances. If certified cost or pricing data has been requested by the government and submitted by an offeror, but an exception is later found to apply, the data should not be considered to be "certified". == Exemptions ==