Background and planning The University of Washington moved from its
downtown campus to the north side of
Portage Bay in 1895, later expanding during the
Alaska–Yukon–Pacific Exposition of 1909 that was hosted at the site. In 1911, urban planner
Virgil Bogue's rejected
comprehensive plan for Seattle envisioned a citywide
subway system, including a line serving the east side of the university campus and connected to
Ravenna and eastern
Capitol Hill. The
Forward Thrust Committee's planned regional rapid transit system, which was rejected by voters in 1968 and 1970, included a subway station at the University Hospital near Husky Stadium, from where trains would continue south through Capitol Hill to
Downtown Seattle. A 1986 regional transit plan from the
Puget Sound Council of Governments proposed a light rail line through the University District, including a station at the University Hospital, continuing through
Eastlake to Downtown Seattle. In the 1990s, a regional transit authority—later
Sound Transit—was formed to build a light rail system for the Seattle metropolitan area. The University District was named as a major destination for the system and given two stations at NE Pacific Street and NE 45th Street on the western side of the university campus, which would be connected to Downtown Seattle via a tunnel under Capitol Hill. The $6.7 billion proposal, including a light rail line continuing north from the University District to
Northgate and
Lynnwood, was rejected by voters in 1995 and replaced with a smaller plan. In November 1996, voters approved a condensed $3.9-billion regional transit plan that included a shorter light rail line from the University District to Downtown Seattle and
SeaTac. A surface alignment through Eastlake was also proposed in the event boring a tunnel through Capitol Hill and under Portage Bay would be too expensive. Sound Transit finalized its preferred alignment for the light rail project, which included stations at NE Pacific Street and NE 45th Street, in 1999. Sound Transit suspended planning for the Portage Bay tunnel in 2000 after it received construction bids that were $171 million higher than expected, blamed on a competitive labor market and
soil testing that indicated that a deeper tunnel was needed. Faced with budget issues and further schedule delays, Sound Transit deferred construction of the segment between Downtown Seattle and the University District in 2001 while re-evaluating alignment options. The alternatives were narrowed to two options in early 2002: a tunnel below the Ship Canal at
University Bridge with a single station at Northeast 45th Street; and a tunnel under the
Montlake Cut and stations near Husky Stadium and at Northeast 45th Street. A Sound Transit study determined the Montlake route was the most cost-effective, and the University of Washington endorsed it as the least disruptive to its research buildings. In 2004, the Sound Transit Board confirmed this route, including an underground station at Husky Stadium with a subterranean pedestrian connection to the campus, as the new preferred alignment for the Link light rail project. The $1.9 billion University Link project, with the Husky Stadium station as the northern terminus, received final approval from Sound Transit and the
Federal Transit Administration (FTA) in 2006. Under the plan approved in 2006, the Husky Stadium station would have three entrances connected via underground walkways or overpasses: on the east side of Montlake Boulevard adjacent to the stadium; on the north side of Pacific Place on the Burke-Gilman Trail; and on the west side of Montlake Boulevard near the University of Washington Medical Center. In 2007, the Seattle Design Commission recommended an overpass to cross Montlake Boulevard in lieu of the underground walkway, and Sound Transit updated the station's design plan accordingly, adding a bridge on the north side of the Montlake Triangle across from Rainier Vista. The University of Washington unveiled its plans to redevelop the Montlake Triangle into a landscaped park with a land bridge over Pacific Place, and requested Sound Transit to connect the station through a mid-block crosswalk instead of the bridge. The FTA rejected the mid-block crosswalk and a compromise pedestrian overpass connecting to the center of the Montlake Triangle from Rainier Vista was adopted in 2011. The station was named "University of Washington" in 2012, leading to confusion with the existing
University Street station in Downtown Seattle and the future
U District station that would open west of the campus in 2021. Other suggested names included Montlake, Husky Stadium, and UW Medical Center. In 2015, the
Washington House of Representatives passed a transportation package with language that ordered Sound Transit to consider naming the station for state senator
Scott White, who died in office.
Construction and opening , seen from above in February 2012|alt=A construction site with several cranes and walls surrounding a long, rectangular hole in the ground. The University Link project received an $813 million grant from the federal government in January 2009, allowing it to move towards final design and construction. A
groundbreaking ceremony was held at the future University of Washington station on March 6, 2009, marking the start of construction. Utility relocation and site preparation at the station, consisting of the demolition and replacement of facilities at Husky Stadium—including two ticket offices, a concessions kitchen, and restrooms—had begun in February and continued until August. A new access road around Husky Stadium was built and part of the stadium's parking lot was closed and fenced off in early 2010. Excavation of the
station box, along with
shoring installation and
jet grouting of the soil, began in June 2010. The platform level, at a depth of , was reached in late February 2011, allowing concrete pouring to commence. The tunnel boring machines were launched in June and July towards
Capitol Hill station, arriving in spring 2012. Station box excavation was completed in June 2012, and contractors
Hoffman Construction Company moved on to steel erection and pouring of the station's upper levels. Station construction reached street level in late 2012, and structural elements of the
headhouse and Montlake Boulevard overpass were installed. The station's basic structure was finished in early 2014, and landscaping and road access around the entrance was restored while finishing work continued underground. The station and overpass were declared substantially complete in November 2014, while work above ground continued. The University of Washington completed work on the Montlake Triangle in July 2015, and the Montlake Boulevard overpass opened to the public later that month. Capitol Hill and University of Washington stations opened on March 19, 2016, during a community celebration that attracted 67,000 people; the two stations opened six months ahead of schedule. The following week, several bus routes in Northeast Seattle were redirected to
feed the new station as part of a major restructuring of service brought on by the cancellation of downtown express routes from the University District. By the end of the year, the station was averaging 9,300 daily boardings, placing it second among Link stations for ridership behind Westlake. The station has had long-term escalator outages that began soon after it was opened, blamed on components failing prematurely. In one incident on March 16, 2018, both of the station's down escalators were broken for three hours, forcing passengers to queue for the elevators. The incident prompted Sound Transit to change their escalator protocol in April, allowing passengers to temporarily use the shut-off escalators as stairs and opening emergency stairways. The downward escalators failed again for an hour on April 27, during which the new escalator protocol was used to allow access to the emergency stairways. In October 2018, Sound Transit approved a $20 million contract to replace the station's 13 escalators, open one set of stairs to the public, and build a connection between the two sub-mezzanines above the platform. The escalator replacement plan was later cancelled in October 2020 following improved performance due to preventative maintenance under a new contractor. Buses from the Eastside area using State Route 520 were redirected to the station beginning in March 2019 as part of a restructure of downtown bus service before the
downtown transit tunnel was closed to buses. A new set of bus stops and dedicated bus lanes on the east side of Montlake Boulevard were built to serve the redirected routes. University of Washington station served as the northern terminus of the 1 Line until October 2, 2021, when an
extension to
Northgate station opened. Tunnel boring from U District station, located northwest of the university campus, was completed in September 2016. On September 17, 2024, a bent
pantograph on a train damaged the overhead wire over the northbound track at the station and caused a stall that was not removed for the remainder of the day. Northbound trains have been limited to on approach or departure from University of Washington station to prevent further damage to the wires, which was originally scheduled to be repaired in December. The slow order added an extra two minutes of travel time to Link trains through the area. The repair was delayed to February 2025 due to ongoing signaling issues that could have potentially disrupted the limited train schedule during reduced service. The
2Line entered simulated service on February 14, 2026, with passengers able to board trains from Lynnwood to
International District/Chinatown station. ==Station layout==