Construction and opening A
broad-gauge railway from Portishead to Clevedon was proposed in 1865 to connect with the
Bristol and Portishead Railway which was then under construction. If it had been built it would have allowed direct services from Clevedon to Bristol which would have avoided the need to change at . A new proposal in 1884 envisaged the three towns being linked by a 'Weston-super-Mare, Clevedon and Portishead Tramway'. This standard-gauge line would run along the street from the Boulevard to Ashcombe Road in Weston-super-Mare and then off-road (apart from numerous
level crossings) from there to Portishead. An
act of Parliament, the '''''' (
48 & 49 Vict. c. clxxxii) authorising its construction was passed on 6 August 1885. Building of the Weston-super-Mare to Clevedon section of the tramway began in 1887, but progress was slow due to many legal and financial problems. The act had stipulated that construction should be completed within five years, but further acts had to be passed on 25 July 1890, with the '
(53 & 54 Vict. c. cxxxii) and again on 27 July 1892 with the ' (
55 & 56 Vict. c. clviii) to extend the time allowed. The section from Ashcombe Road to Clevedon was formally inspected by the
Board of Trade on 26 August 1897 but not allowed to open. Due to the long time taken to build the line, some of the wooden
sleepers had rotted and needed to be replaced. The local council also complained about the state of the track along the streets in Weston-super-Mare, so this section was taken up. A second inspection was made on 9 November and the line finally opened on 1 December 1897.
Completion to Portishead The powers to construct the railway had run out in 1896 so another act of Parliament was required. After some opposition from the Clevedon Urban District Council regarding the necessary level crossings, the
Weston Clevedon and Portishead Light Railways Act 1899 (
62 & 63 Vict. c. ccxxi) was passed on 9 August 1899. In addition to allowing construction to be completed to Portishead by August 1904, it enabled the tramway to convert to a
light railway with the name changed to the Weston, Clevedon and Portishead Light Railway Company. Financial difficulties continued. By 1904 the company was about £76,000 in debt so a new limited company, the Weston, Clevedon and Portishead Docks Railway, was formed with a capital of £120,000. The new company still found it difficult to raise enough money until September 1905, when £14,500 of 5%
debentures were taken up by the Excess Insurance Company. In 1906, it borrowed £16,000 from other sources but was unable to repay the interest so the Excess Insurance Company provided funds up to £15,000 in March 1907 on the condition that the existing directors were replaced by new directors chosen by the insurance company. With money available again work could be completed on the new line to Portishead. It was inspected on 31 July 1907, and opened for traffic on 7 August.
Receivership and closure In 1909, Cuthbert Heath, the managing director of the Excess Insurance Company, petitioned for the railway to enter
receivership. Spencer Gore-Browne, one of the directors nominated by the insurance company, was appointed as the receiver and
Colonel Stephens, the so-called' 'Light Railway king' was appointed as manager in 1911. He managed the railway along with a number of similar lines from an office in
Tonbridge,
Kent. Stephens tried to gain additional business for the line. A small branch was opened at
Wick St. Lawrence to serve a wharf which the railway built on the
River Yeo; the railway operated some boats carrying coal from
Wales for a few years in the 1920s. Two additional passenger halts were opened in 1917-1918 and the larger stations given improved facilities. From 1921, a number of internal combustion
railcars and rail-mounted tractors were used which significantly reduced costs. Steam locomotives were retained, especially for the trains from Clevedon to Portishead which conveyed heavy traffic from quarries in the area. Some wagons were stored in various sidings at the Weston-super-Mare end of the line but were moved back across the river in case of bombing. The WC&PR rolling stock was all taken to
Swindon Works in August 1940 but was scrapped except for two Terriers which were overhauled and retained by the GWR. Lifting the line started on 3 October 1942 from the Weston-super-Mare end using one of the Terriers. By the end of October, the track had been lifted as far as Ebdon Lane. Between February and June 1943, the track was lifted between Portishead and the River Yeo but the remainder had to be removed by road. 16,000 tons of material was recovered. The company which owned the land no longer existed, so it could not be sold off. The town councils at Weston-super-Mare and Clevedon wanted it for roads and houses so paid the £3,750 value of the land to the
Bank of England. ==Description==