As of 2023, the total installed wind power capacity in Denmark was 7,510 MW, of which 4,860 MW were
onshore and 2,650 MW were
offshore. At the end of 2015, Denmark's total installed capacity for wind power stood at 5,070 MW. Denmark has the highest proportion of wind power in the world. In 2015, Denmark produced 42% of electricity from wind, (790 MW in late 2015). A peak generation period occurred on 21 December 2013 when the wind share was 102%, and for 1 hour the share was 135%. In 2009, Denmark's wind capacity grew to 3,482 MW; most of the increase came from the 209 MW
Horns Rev 2 offshore wind farm, which was inaugurated on 17 September 2009 by
Crown Prince Frederik. In 2010, capacity grew to 3,752 MW, and most of the year's increase came from the
Rødsand II off-shore wind farm. On 22 March 2012, a coalition of parties representing 95% of all members of the Danish parliament agreed that the Danish state would increase the country's offshore wind capacity by 1,500 MW. The 1,500 MW extra capacity was achieved by constructing several offshore wind farms; the 400 MW
Anholt wind farm in 2014, in 2019, and the
Kriegers Flak at 37.2 øre/kWh Eight groups applied for pre-qualification for Kriegers Flak, of which 7 were approved – 3 more than the 4 companies approved to compete for Horns Rev 3, both having more bidders than the single bidder for Anholt. By 2018, Danish offshore wind farms had average 40% capacity factor. Newer farms had higher CF than older. Offshore operators are required to secure a
decommissioning fee. Wind power output reduces spot market prices in general via the
Merit Order effect; in 2008 this caused a net reduction of pre-tax electricity prices (balancing the increase from the feed-in law).
Statistics The chart shows the minimum (guaranteed) price a plant receives during the FLH period in
øre/kWh. Subsidy = guaranteed price minus market price. FLH=
Full Load Hours; the amount of production the plant receives support for. After that, the plant usually receives market price. Transmission is included in the nearshore "Vesterhav", but not the other plants. The levels are usually below levels in Germany and UK.
Future parks in Denmark Offshore The 1,000 MW Thor offshore wind (a $2.5 billion project scheduled for 2027 in the North Sea) was agreed in December 2021. 5 of 6 bidders bid the same price of 0.01 øre/kWh, and
drew lots to find the winner (RWE) for a
Contract for difference, which included connection costs and a potential DKK 2.8 billion (€377m)
payment to the state. The similar bids raised questions about the suitability of the auction. Three days after the auction, the
Parliament agreed on a further 2 GW offshore wind by 2031 due to the success of the Thor auction. In early June 2023, an agreement was made by
Germany and
Denmark to link the Danish island of Bornholm's wind energy producing capacity to the mainland by the early 2030s, with a minimum capacity of 3 gigawatts.
Nearshore {{external media In addition 6 nearshore wind farms with a total capacity of up to 450 MW are scheduled along with 50 MW of experimental offshore wind farms. The nearshore differ from conventional offshore in having the being close enough to the coast to have the transformer on land, decreasing cost. Vattenfall bid the lowest price for the 350 MW nearshore farms at 47,5 øre/kWh in September 2016, but the political situation was unclear.
Onshore In addition to the offshore projects, a further 500 MW additional net capacity of onshore windfarms is expected to be constructed until 2020. The 500 MW of additional net capacity is the expected result of the scrapping of 1,300 MW capacity from obsolete wind turbines combined with the simultaneous building of 1,800 MW capacity of modern wind turbines – a process also known as
repowering.
Electricity exports from Denmark In 2020, Denmark produced 16.3 TWh of wind power, of which 15 TWh (91.8%) were consumed in Denmark, measured hourly. A further 0.8 TWh of wind power were imported. In 2017, annual wind power production corresponded to about 43% of electricity consumed in Denmark. The proportion of this that is actually consumed in Denmark has been disputed, as the larger
hydropower resources of Norway (and to some extent, Sweden) is used as
grid storage with low loss. Hydropower can rapidly reduce generation whenever wind farms are generating power, saving water for later, and can export electricity to Denmark when wind power output drops. Short term, Denmark imports electricity from Norway during daytime and exports in nighttime. Long term, Denmark imports electricity in summer and exports in winter. Wind is higher in autumn and winter, when consumption is also high. Market price sometimes falls to near or below zero, particularly in high winds and low consumption. In 2014, there were 46 hours with negative prices, costing DKK 37.7 million. In 2015, negative prices occurred in 65 hours in West Denmark and 36 hours in East Denmark – less than 1% of the time. Danish prices are mainly negative when
German prices are even more negative; 90% of
curtailment happens as a request from German power producers, and represents 2% (or DKK 80 million in 2018) of wind power production. In most years, curtailment mainly happened at thermal power plants, but became mostly by wind turbines in 2020. In 2019, Germany paid for curtailment of 420 GWh of Danish wind power, and the number increased to 1,463 GWh in 2020 (plus 1,066 GWh for thermal power), earning DKK 522 million. The 24-hour period of 2 September 2015 was the first occasion when most electricity came from wind, and no central power plants were running in West Denmark, while grid stability was maintained by
compensators. and plans to add cables to England (
Viking Link) as well, further increasing the function of being a
crossroads for electricity. From 2005 to 2010, claims of up to 40% of wind power being exported have been made, According to the first argument, power in excess of immediate demand is exported to neighbouring countries at lower prices. Part of the benefit of this goes to Denmark's northern neighbours: when Denmark exports power, it is sold at the
spot market price which must be lower than at the importing market to be transmitted. According to the second argument, the correlation between exports and wind power is weak, and a similar correlation exists with conventional thermal plants running partly for district heating; meanwhile, causal analysis shows that export from Denmark typically occurs as a consequence of the
merit order effect, when large thermal plants have reserve capacities at times the spot market price of electricity is high. In any case, the export price is the intermediate between the prices of the two areas, so the exporting TSO (Energinet) uses the profit to relieve tariffs at around DKK 500 million per year. Wind power organisations state that Denmark exports power at a higher price than it imports at. == Economic conditions ==