Early years In the 1970s the station generation capacity had reduced to approximately 65% of the original rated capacity due to sediment build-up and wear on mechanical components. This led to the turbine runner being replaced along with improvements in sediment control at the canal intake and ongoing removal of sediments to reinstate the original performance.
Pump station In 2010, TrustPower (now
Manawa Energy) installed a river intake, fish screening, and pumping facilities to deliver the water from the Rakaia River to the RDR using some of the existing Highbank Power Station facilities. The Highbank Power Station site has been equipped with an array of six 1.5 MW pumps that allow it to take water from the Rakaia River and pump it up the power station penstock into the RDR. The water is then available for irrigators to use. TrustPower (now
Manawa Energy) generation manager Mike Kedian believed pumping water back through the penstock was a New Zealand first. Pumping water up hill is not without its challenges, and one of these is the volume and pressure of the water contained in the pipeline when being pumped. In order to protect the penstock from pressure fluctuations an air-chamber has been installed adjacent to the pump station to maintain pipeline pressure within acceptable bounds.
Generator and turbine replacement The original generation equipment was replaced in a project that commenced in November 2024 and is expected to be complete in May 2026. The original turbine and its
scroll case were removed from the power house and a new 29 MW turbine and generator were installed. Replacement of both generator and turbine enables more efficient generation of electricity using the available water, and is expected to increase output by 8 GWh per year. The project was estimated by Manawa Energy to cost NZ$30.5M. Along with the generator and turbine, other mechanical and electrical equipment on the site was replaced. During the outage for the replacement of the main units, the pump station for the Barrhill-Chertsey irrigation scheme was modified so that when not required for irrigation, the pumps could be used for generation, providing 5.8MW of generating output. Highbank Power Station is potentially exposed to a risk of out-of-phase synchronisation resulting from manual or automatic switching on the 66kV network. To manage this risk, the historic practice of EA Networks has been to avoid the use of automatic reclose on the 66kV network, and to ensure that the Highbank generator is disconnected before manually closing circuit breakers. These precautions add complexity to network operations and can delay restoration of circuits after a fault. EA Networks plans to install
phasor measurement units (or synchrophasors) on their 66kV network in 2025 to enable automatic re-closing of 66kV circuit breakers if the conditions for closure are suitable and will not produce an unacceptable out-of-phase synchronisation. ==See also==