, one of three original subway stations in the Steinway Tunnel Initially, the IRT intended to use the tunnel for trolleys; Work began in 1913, with a regularly scheduled shuttle service beginning June 22. The planned metro route was to go from
Times Square through the tunnel over to Long Island City and from there continue towards
Flushing. The IRT was to operate this line, with the trackage east of
Queensboro Plaza to be shared by the
Brooklyn Rapid Transit Company (later the
Brooklyn–Manhattan Transit Corporation, or BMT). Meanwhile, the construction work continued on the planned route. To the east of the tunnel, the Hunters Point Avenue subway station went up to the level of the Hunterspoint Avenue LIRR station. Immediately east of it was a ramp up to the elevated subway towards
Queensboro Plaza. Hunters Point Avenue opened on February 15, 1916, and on November 5 of the same year, it was extended to Queensboro Plaza. Because the line did not have track connections to the rest of the IRT network, a provisional maintenance workshop was operated at the tunnel ramp until 1928. and
Times Square on March 14, 1927. When Belmont modified the IRT Flushing Line to extend to
Times Square and to
Flushing, it was found that the loops could not be used for the extensions. The loops on the Queens side of the tunnel were obliterated in the wake of new construction. The loop on the Manhattan side, however, is intact and occupied by maintenance rooms, although the ceiling third rail still exists in the loop. The line from Times Square to Flushing was completed in 1928, when the station at Flushing opened. The 50
"World's Fair"-type cars, used for the
1939 New York World's Fair, used the same type of gear boxes. In subsequent years, the tubes of the Steinway Tunnel were difficult to maintain: they were prone to flooding, and the tube walls were much narrower than other tunnels in the subway system, with almost no clearance on each side of the train. After a train got stuck in the tunnel in 1971, a passenger died of a heart attack. A fire broke out on a train in the tunnel in 1973, killing one passenger and trapping over a thousand in the middle of the tunnel, after the collapse of an archway. In 1991, the tubes were flooded to after a water main broke on the Manhattan side. The next year, an electrical fire in the tunnel melted several feet of steel rail, although the tunnel's exhaust fans were working properly. After
Hurricane Sandy-related storm surges flooded the tunnel in 2012, the tubes were rebuilt in a $29 million project that took place between 2013 and April 2016. To protect the tunnel from future flooding, two retaining walls will be installed on either side of the tunnel portal in Queens, and flex gates would be installed to prevent water from entering the tunnel. The project is estimated to cost $15 million, work was scheduled to begin in May 2021 and was still ongoing in 2024. ==References==