Early attempts In the September 1919 session of the Imperial Legislative Council at
Shimla, a committee was set up by
W. E. Crum that recommended a metro line for
Kolkata (formerly
Calcutta). All the reports can be found in his 1921 book
Calcutta Tube Railways. However, in 1923, the proposal was not undertaken due to a lack of funds.
Planning Then the
Chief Minister of West Bengal,
Bidhan Chandra Roy, reconceived the idea of an underground railway for Kolkata from 1949 to 1950. A team of
French experts conducted a survey, but nothing concrete materialized. Efforts to solve the traffic problem by augmenting the existing fleet of public transport vehicles hardly helped, since roads accounted for only 4.2 percent of the surface area in Kolkata, compared with 25 percent in
Delhi and 30 percent in other cities. To find alternative solutions, the Metropolitan Transport Project (MTP) was set up in 1969. The MTP, with the help of
Soviet specialists, Lenmetroproekt and
East German engineers, prepared a master plan to provide five rapid-transit (metro) lines for the city of Kolkata, totaling a length of , in 1971. Three were selected for construction. These were: •
Dum Dum –
Tollygunge (Blue Line. Presently operates from
Dakshineswar to
New Garia) •
Bidhannagar –
Ramrajatala (Green Line. Presently truncated till
Howrah Maidan) •
Dakshineswar –
Thakurpukur (Divided into Blue Line:
Noapara to Dakshineswar and Purple Line:
Joka to
Eden Gardens) The highest priority was given to the busy north–south corridor between Dum Dum and Tollygunge over a length of ; work on this project was approved on 1 June 1972. A tentative deadline was fixed to complete all the corridors by 1991.
Construction North-South Metro Since it was India's first metro and was constructed as a completely indigenous process, a traditional
cut-and-cover method and driven
shield tunneling was chosen and the Kolkata Metro was more of a trial-and-error affair, in contrast to the
Delhi Metro, which saw the involvement of multiple international consultants. As a result, it took nearly 23 years to completely construct the underground railway. The foundation stone of the project was laid by
Indira Gandhi, the
Prime Minister of India, on 29 December 1972, and construction work started in 1973–74. Initially,
cut and cover along with
slurry wall construction to handle soft ground, was recommended by the
Soviet Union consultants. Later, in 1977, it was decided to adopt both shield tunneling and cut and cover methods for the construction of underpopulated areas, sewer lines, water mains, electrical cables, telephone cables, tram lines, canals, etc. The technology was provided by M/s NIKEX Hungarian Co., Budapest. In the early days, the project was led by the
Union Railway Minister from West Bengal,
A. B. A. Ghani Khan Choudhury, often against the prevailing socio-political stance of his contemporaries in the West Bengal government. From the start of construction, the project had to contend with several problems including insufficient funds (until 1977–1978), a shifting of underground utilities, court injunctions, and an irregular supply of vital materials. Despite all the hurdles, services began on 24 October 1984, with the commissioning of a partial commercial service covering a distance of with five stations served between Esplanade and
Bhowanipur (currently
Netaji Bhavan). The service was quickly followed by commuter services on another stretch in the north between
Dum Dum and
Belgachhia on 12 November 1984. The commuter service was extended to
Tollygunge on 29 April 1986, covering a further distance of , making the service available over a distance of and covering 11 stations. However, the services on the north section were suspended starting 26 October 1992, as this small, isolated section was little used. The
Blue Line was almost entirely built by cut and cover method, while a small 1.09 km stretch between Belgachia and Shyambazar was built using shield tunneling with compressed air and air locks, since the alignment crossed a railway yard (now
Kolkata railway station) and
Circular Canal. After more than eight years, the
Belgachhia–
Shyambazaar section, along with the Dum Dum–Belgachhia stretch, was opened on 13 August 1994. Another stretch from
Esplanade to
Chandni Chowk was commissioned shortly afterward, on 2 October 1994. The
Shyambazaar-
Shobhabazar–
Girish Park () and
Chandni Chowk–
Central () sections were opened on 19 February 1995. Services on the entire stretch of the Metro were introduced from 27 September 1995 by bridging the gap with
Mahatma Gandhi Road metro station in the middle. In 1999–2000, the extension of
Blue Line along an elevated corridor from Tollygunge to New Garia, with six stations, was sanctioned at a cost of . The section was constructed and opened in two phases,
Mahanayak Uttam Kumar to
Kavi Nazrul in 2009 and Kavi Nazrul to
Kavi Subhash in 2010. In the north, the line was extended till
Noapara from Dum Dum on 10 July 2013. The latest extension opened was the stretch from
Noapara to Dakshineswar on 23 February 2021.
East-West Metro The master plan of the metro corridor was made in 1971 along with the North–South Corridor, connecting the office district of
Bidhannagar with the twin city and
transportation hub Howrah via another transport hub of the city,
Sealdah, and the
central business district Esplanade by an underwater metro line. It is a project, sanctioned in 2008 by Prime Minister
Manmohan Singh. The foundation stone was laid on 22 February 2009 and construction started in March 2009. The autonomous
Kolkata Metro Rail Corporation (KMRC) was formed to implement the project. The
Government of India (
Ministry of Urban Development) and
Government of West Bengal each had a half-share in it. Later, the Government of West Bengal pulled out from it, and the shares were transferred to the
Ministry of Railways. The realignment led to many other issues and delays. Some of the biggest issues were the H-piles under the Esplanade metro station and the Bowbazar mishap. Per the 1971 master plan, the East-West Corridor was supposed to pass under Central metro station, so the square foundational beams in Esplanade were not removed. Since the
tunnel boring machines cannot cut through steel, another small tunnel was dug using
New Austrian tunneling method (NATM) and the H-piles were cut manually. This extended the tunneling process by one and a half months. In September 2019, during the construction of the eastbound tunnel (from Esplanade to
Sealdah), a machine hit an
aquifer under Bowbazar, causing a major collapse in the area, delaying work in that section for several months. Around 80 houses were damaged and many buildings were declared unsafe, affecting more than 600 people. Later subsidence in the area was checked using grouting.
Expansion planning By 2011–2012, the
Railway Ministry had announced plans for the construction of five new metro lines and an extension of the existing north–south corridor. These were: •
Salt Lake –
Howrah Maidan (
Green Line or East–West Metro Corridor) •
Joka –
B.B.D. Bagh (
Purple Line. To be extended till
Eden Gardens) •
Noapara –
Barasat (
Yellow Line, via airport) •
Baranagar –
Barrackpore (
Pink Line) •
New Garia –
Dum Dum Airport (
Orange Line)
Major modification and interchanges A new four-platform
interchange station was constructed at Noapara and Kavi Subhash. This acts as an interchange station for Blue Line with
Yellow Line and
Orange Line respectively. After opening of Yellow Line, all four platforms are now operational, whereas, from 6 March 2024, all four platforms of Kavi Subhash were in operation, until 28 July 2025, when the Blue Line platforms were temporarily closed for reconstruction. on 31st March, 2025. The existing Esplanade metro station was upgraded and a subway was constructed to the new metro station to provide an interchange among Blue Line,
Green Line and future
Purple Line. Additional interchanges were built at
Salt Lake Sector-V (green line)-IT Centre (orange line) and
Jai Hind (Yellow line-Orange line) metro stations. In 2009–2010, Blue Line underwent upgrades of services and amenities and many stations were renamed after famous personalities by then Minister of Railways Mamata Banerjee.
Interchanges Salt Lake Sector V It Centre metro station 01.jpg|Salt Lake Sector-V (Green)-IT Centre (Orange) Kavi Subhash metro station during Hemanta Mukhopadhyay metro station to Netaji Bhavan metro journey 24.jpg|Kavi Subhash (Blue-Orange) Noapara metro station platforms 04.jpg|Noapara (Blue-Yellow) Esplanade metro station pics 10.jpg|Esplanade (Blue-Green) Jai Hind Metro Station (Nov 2024-Apr 2025) time lapse pics 30.jpg|Jai Hind (Yellow-Orange) == Network ==