•
Jun 2019: Pillar construction work started on both the RRTS and the Meerut Metro by
Larsen & Toubro. •
May 2020: Bombardier Transportation, now acquired by
Alstom, won the contract for manufacturing 210 trains for the RRTS and the Meerut Metro. •
Feb 2021: The construction of the
Anand Vihar station of the RRTS just beside the
Anand Vihar Terminal railway station began. •
Apr 2021: Track laying started for the
Ghaziabad section of the corridor. •
Jun 2021: The first elevated section pier (namely for the
Sarai Kale Khan section) was constructed. •
Jun 2021: Construction work on the first part of the underground portion of began in
Anand Vihar. •
Jul 2021: The piers were completed for the
elevated stretch. •
Jul 2021: Alstom began manufacturing the 210 trains for the RRTS and the Meerut Metro. These are being manufactured in Alstom's plant in
Savli,
Gujarat. •
Mar 2022: The tunneling work for the underground section of the RRTS in Meerut began. •
Mar 2022: Paytm Payments Bank won the bid for becoming the financial institution responsible for the fare system, beating the
State Bank of India (SBI). •
Apr 2022: Roughly 25% of the corridor was completed. •
May 2022: Alstom manufactured and delivered the first train to the NCRTC from Savli, Gujarat. •
Aug 2022: First trial of the first trainset had been successfully completed. •
Feb 2023: The trial runs for the trains, including high-speed tests, had been completed, and now there were a total of six trains. The 17-km priority corridor from Sahibabad to Duhai was at its final stages of work, and was confirmed to be opened by mid-June 2023. The second stretch from Duhai to
Meerut South would be opened by the first quarter of 2024, and the entire corridor would become operational by March 2025. •
Aug 2023: The entire tunneling work of the RRTS was fully completed. •
Oct 2023: The priority corridor from Sahibabad to Duhai was inaugurated on 20 October 2023. •
Feb 2024: The NCRTC announced that the 25-km stretch from Duhai to Meerut South will become operational by March 2024, thereby increasing the operational length to 42 km. The RRTS and the Meerut Metro projects are both on track to be completed by June 2025. •
Mar 2024: Of the 25 km-long stretch from Duhai Depot to Meerut South, the 17-km stretch till
Modinagar North was inaugurated on 6 March 2024, thus bringing the current operational length to 34 km. The Meerut South station will be completed by the first half of May 2024. •
Aug 2024: Of the 25 km-long stretch from Duhai Depot to Meerut South, the 8-km section from Modinagar North to Meerut South was opened on 18 August 2024. Of the total 82 Km long corridor, more than 80 km has been completed, and the opening of the section from Sahibabad till Sarai Kale Khan is on track to be completed by December 2024. •
Jan 2025: A 13-km long stretch between Sahibabad and New Ashok Nagar was inaugurated on 5 January 2025, thus connecting Delhi with the corridor. •
May 2025: NCRTC has completed the installation of all 169 track km (TKM) of precast slab track. •
February 2026: Entire strech of the RRTS from Sarai Kale Khan to Modipuram becomes operational on 22 February 2026. == See also ==