Installed capacity By the end of July 2021, the total solar power installed capacity was about 19,400
MWp (of which nearly 9,300 MWp is
rooftop solar power), equivalent to about 16,500
MW, accounting for about 25% of the total installed capacity of all sources in the national power system. Generous FITs and supporting policies such as
tax exemptions are found to be the key proximate drivers of Vietnam's solar PV boom. Vietnam has a great potential to develop
solar power, especially in the central and more southern regions. The average number of
sunshine hours in the North ranges from 1,500 to 1,700 hours of sunshine per year. Meanwhile, the Central and Southern regions have higher average annual sunshine hours, from 2,000 to 2,600 hours/year. The average daily
solar radiation intensity in the north is 3.69 kWh/m2 and the south is 5.9 kWh/m2. The amount of solar radiation depends on the amount of cloud and the
atmosphere of each locality. From one region to another, there is significant variation in solar radiation. Radiation intensity in the South is often higher than in the North.
History According to the prime minister's 2016 energy plan, solar power was expected to reach 850 MW (0.5%) by 2020, about 4,000 MW (1.6%) in 2025 and about 12,000 MW (3.3%) by 2030. By the end of 2018, there were about 10,000 MW registered, of which 8100 MW was newly added to the plan, more than 100 projects signed
power purchase agreements, and two projects came into operation with a total capacity of about 86 MW. These projects were entitled to an electricity purchase price (
FIT) equivalent to 9.35 US¢/kWh for a period of 20 years under Decision 11/2017/QD-TTg of the Prime Minister. At that time, solar power accounted for 8.28% of the installed capacity of Vietnam's electricity system. Through the end of 2019, the center was expected to put into operation 13 more solar power plants, with a total capacity of 630 MW, bringing the total number of solar power plants in the whole system to 95.
Solar power plants A few large-scale solar power projects have been built in Vietnam: • In October 2020, the largest 450MW Trung Nam Thuan Nam solar power project in the country and Southeast Asia and the first 500kV transmission and
substation system invested by private enterprises was inaugurated after 102 days and nights of implementation. • In September 2019,
Dau Tieng solar power plant cluster officially connected to the
national grid with a capacity of 420 MW after more than 10 months of construction, providing about 688 million kWh per year. • In April 2019, 3 clusters of solar power plants of BIM Group (capacity of 330 MWP) in Ninh Thuan completed commissioning electricity to the national grid system, including BIM-1 power plant with capacity of 30 Mwp; BIM-2 with capacity of 250 Mwp and BIM-3 with capacity of 50 Mwp. The cluster of 3 solar power plants was invested more than 7,000 billion VND, installing more than 1 million
solar panels. • On November 4, 2018, after 9 months of construction,
TTC Krong Pa solar power plant with a capacity of 49 MW (69 MWp), and a total investment of more than VND 1,400 billion, which was built in
Gia Lai province, was commissioned successfully. • On September 25, 2018, Phong Dien Solar Power Plant in Thua Thien Hue province completed the commissioning of electricity to the national grid system. This is the first 35 MW solar power plant to be commissioned in Vietnam. It is expected that by 2019, this factory will expand more with the capacity of 29.5 MW with an area of 38.5 hectares, meeting a part of the demand for
electricity consumption in the future. Tra O lagoon solar power plant project (My Loi commune, Phu My district, Binh Dinh province), with a capacity of 50MWp, was expected to be deployed on a water surface area of around 60 hectares of the lagoon's 1,300 hectares in quarter-II of 2019. However, from mid-2018, during the implementation process, there was a fierce opposition from the local people, preventing investors from building projects due to some big concerns about affecting the ecological environment. These caused death of fish and shrimp under the
lagoon (because this is the main income source for the communes surrounding the lagoon) and the water source pollution problem. Hacom Solar solar power plant project (Phuoc Minh commune, Thuan Nam district, Ninh Thuan province), 50 MWp capacity, was started in April 2019. However, when constructing the factory, the investor (Hacom Solar Energy Co., Ltd) arbitrarily let the vehicles run through people's land. Local people stopped the container
trucks from transporting materials into the project and complained that the local authorities and the owner of the solar power plant had to meet with land-owners to negotiate compensation plans for the people because the project has violated people's land. == Biomass energy ==