carries MetroLink across the
Mississippi River between Missouri and Illinois on its lower-level rail deck. Construction on the initial MetroLink line from
St. Louis Lambert International Airport to the 5th & Missouri station in
East St. Louis began in 1990. The first segment opened on July 31, 1993, with 16 stations between
North Hanley and
5th & Missouri. The extension to
Lambert Airport Main opened on June 25, 1994. Three
infill stations have since been added to this alignment:
East Riverfront in 1994,
Lambert Airport East in 1998, and
Cortex in 2018. unit on the then-newly opened MetroLink system in 1993.About of the original alignment reused existing railroad right-of-way including historic
downtown tunnels. The capital cost to build the initial phase of MetroLink was $465 million, including $348 million from the
Federal Transit Administration (FTA). Construction on the
St. Clair County MetroLink extension from the 5th & Missouri station to the
College station in
Belleville began in 1998 and opened in May 2001. The extension added eight stations and seven park-ride lots. The total project cost was $339.2 million with $243.9 million paid by the FTA and $95.2 million paid by the
St. Clair County Transit District (via a 1/2 cent sales tax passed in November 1993). The entire project was funded by a $430 million Metro bond issue. Citing repeated delays and cost overruns, Metro fired and then sued its general contractor, Cross County Collaborative, in the summer of 2004. Metro sought $81 million in damages for fraud and mismanagement while the Collaborative counter-sued for $17 million for work that Metro hadn't paid for. On December 1, 2007, a jury awarded the Collaborative $2.56 million. seen from the Laclede's Landing platform.|leftOn October 27, 2008, Metro renamed the Lambert Airport branch the
Red Line and the Shrewsbury branch the
Blue Line. Blue Line service was also extended from its former terminus at
Emerson Park to
Fairview Heights. All trains have signs on the front and side that identify the train as a Red or Blue line train, and operators make live announcements identifying lines and stations. On June 15, 2019, MetroLink set its single-day ridership record when more than 100,000 people used the service to attend the parade after the
St. Louis Blues won the
2019 Stanley Cup playoffs. On July 26, 2022, a
flash flood shut down MetroLink for nearly 72 hours and caused roughly $40 million in damage. The flood damaged nearly of track bed, two elevators, two communications rooms, three signal houses and destroyed two MetroLink vehicles. Normal Red Line service resumed in September, but Blue Line service would run under restrictions for nearly two years. On July 31, 2023, Metro received $27.7 million in federal emergency disaster relief funding to help cover the cost of restoration. In March 2024, Blue Line platform and speed restrictions were lifted after repairs on the last signal house were completed. In May, Metro received a $196.2 million federal grant to purchase new light rail vehicles to replace the remaining SD-400 cars. Six months later, Bi-State's board approved a contract with
Siemens Mobility worth up to $390.4 million for as many as 55 new
S200 light rail vehicles with delivery expected to begin in 2027. In September 2024,
turnstiles began initial operation at four Illinois stations as part of Metro's
Secure Platform Plan. Seven Missouri stations are slated for completion by early 2025 with the remaining stations and an upgraded fare collection system expected to be in place by early 2026.
Chronology Opening dates of MetroLink segments and stations: == Lines ==