1930s–1960s The Bridge Railway (center), and State Highway Engineer
Charles H. Purcell take the first train over the Bay Bridge, January 14, 1939 Construction of the Bridge Railway began on November 29, 1937, with the laying of the first ties. The first train was run across the Bay Bridge on September 23, 1938, a test run utilizing a Key System train consisting of two articulated units with California Governor
Frank Merriam at the controls. On January 14, 1939, the
San Francisco Transbay Terminal was dedicated. The following morning, January 15, 1939, the electric
interurban trains started in revenue service, running along the south side of the lower deck of the bridge. The terminal originally was supposed to open at the same time as the Bay Bridge, but had been delayed. interurban crossing the bridge Trains over the Bridge Railway were operated by the
Sacramento Northern Railroad (
Western Pacific), the
Interurban Electric Railway (
Southern Pacific) and the
Key System. Freight trains never used the bridge. The tracks left the lower deck in San Francisco just southwest of the end of 1st Street. They then went along an elevated viaduct above city streets, looping around and into the terminal on its east end. Departing trains exited on the loop back onto the bridge. The loop continued to be used by buses until the terminal's closure in 2010. The tracks left the lower deck in Oakland. The Interurban Electric Railway tracks ran along Engineer Road and over the
Southern Pacific yard on trestles (some of it is still standing and visible from nearby roadways) onto the streets and dedicated right-of-ways in Berkeley, Albany, Oakland and Alameda. The Sacramento Northern and Key System tracks went under the SP tracks through a tunnel (which still exists and is in use as an access to the
EBMUD treatment plant) and onto 40th Street. Due to falling ridership, Sacramento Northern and IER service ended in 1941. On September 13, 1942, a stop was opened at Yerba Buena Island to serve expanded wartime needs on the adjacent Treasure Island. Despite the vital role the railroad played, the last train went over the bridge in April 1958. The tracks were removed and replaced with pavement on the Transbay Terminal ramps and Bay Bridge. The Key System handled buses over the bridge until 1960, when its successor,
AC Transit, took over operations. It still handles service today, running to a new transbay terminal located in the same vicinity in San Francisco, the
Salesforce Transit Center.
Emperor Norton plaque and relocation In 1872, the San Francisco entrepreneur and eccentric
Emperor Norton issued three proclamations calling for the design and construction of a suspension bridge between San Francisco and Oakland via Yerba Buena Island (formerly Goat Island). A 1939 plaque honoring Emperor Norton for the original idea for the Bay Bridge was dedicated by the fraternal society
E Clampus Vitus and was installed at
The Cliff House in February 1955. In November 1986, in connection with the bridge's 50th anniversary, the plaque was moved to the
Transbay Terminal, the public transit and Greyhound bus depot at the west end of the bridge in downtown San Francisco. When the terminal was closed in 2010, the plaque was placed in storage. It was placed at the Salesforce Transit Center in September 2019 but vandalized in late 2020. In February 2021, it was removed from the center and restored. Now, it's displayed in a bar called Molloy's Tavern.
1960s–2010s Roadway retrofit Until the 1960s, the upper deck ( wide between curbs) carried three lanes of traffic in each direction and was restricted to automobiles only. The eastern approach to the bridge included a causeway landing for the "incline" section, and the construction of three feeder highways, interlinked by an extensive interchange, which in later years became known as "The
MacArthur Maze". A massive landfill was emplaced, extending along the north edge of the existing
Key System rail
mole to the existing bayshore, and continuing northward along the shore to the foot of Ashby Avenue in
Berkeley. The fill was continued northward to the foot of University Avenue as a causeway which enclosed an artificial lagoon, subsequently developed by the WPA as "
Aquatic Park". The three feeder highways were
U.S. Highway 40 (Eastshore Highway) which led north through Berkeley,
U.S. Highway 50 (38th Street, later MacArthur Blvd.) which led through Oakland, and
State Route 17 which ran parallel to U.S. 50, along the
Oakland Estuary and through the industrial and port sections of the city. The current approaches were constructed in the 1960s, as the original ones were not up to interstate highway standards and were designed mainly for local use.
Yerba Buena Tunnel reconstruction As originally completed, the upper deck was reserved for automobile traffic, and carried six lanes, each wide. After
Key System trains stopped running over the bridge in 1958, bids were opened on October 11, 1960, to rebuild the tunnel. The rebuild consisted of multiple stages of work: The impact to traffic during reconstruction of the tunnel was minimized mainly by working outside normal commuting hours and through the use of a portable steel bridge long and wide, designed to fit between the curbs of the existing upper deck. The bridge spanned the gap between the new upper deck and old upper deck, and the overall elevation change of caused drivers to slow to , resulting in traffic jams. The first accident caused by "The Hump", the nickname the bridge acquired after prominent warning signs advertising its presence, occurred just twelve minutes after it was first deployed on November 25, 1961. but "The Hump" was not dismantled until October 27, 1962. The
San Francisco Chronicle marked the occasion by quipping "[The Hump] produced more jams than Grandma ever made." After reconstruction, both the upper and lower decks featured of vertical clearance. Upper deck clearance is restricted by the tunnel portal, and lower deck clearance is restricted by the upper deck.
Rail removal seen from
Yerba Buena Island in 2011 Automobile traffic increased dramatically in the ensuing decades of the bridge's opening. This, among other things, resulted in the
Key System's decline. By the 1960s, having rails on the bridge had become obsolete and a detriment to traffic, as they carried nothing on them. Work began on removing the tracks in October 1963. After the work was completed, the Bay Bridge was reconfigured with five lanes of westbound traffic on the upper deck and five lanes of eastbound traffic on the lower deck. The Key System originally planned to end train operations in 1948, when it replaced its streetcars with buses, but Caltrans did not approve of this. Trucks had their ban lifted and were allowed on the top deck for the first time.
1968 aircraft accident On February 11, 1968, a
U.S. Navy training aircraft crashed into the cantilevered span of the bridge, killing both
reserve officers aboard. The
T2V SeaStar, based at
NAS Los Alamitos in
southern California, was on a routine weekend mission and had just taken off in the fog from nearby
NAS Alameda. The plane struck the bridge about above the upper deck roadway and then sank in the bay north of the bridge. There were no injuries among the motorists on the bridge. One of the truss sections of the bridges was replaced due to damage from the impact.
1986 cable lighting The series of lights adorning the westbound spans suspension cables were added in 1986, as part of the bridge's 50th-anniversary celebration, after lobbying by Caltrans engineer
Robert Halligan. The lighting, which was intended to be temporary, was later made permanent.
James Rolph Jr. designation The bridge was unofficially "dedicated" to
James "Sunny Jim" Rolph, Jr., but this was not widely recognized until the bridge's 50th-anniversary celebrations in 1986. The official name of the bridge for all functional purposes has always been the "San Francisco–Oakland Bay Bridge" and, by most local people, it is referred to simply as "the Bay Bridge". Rolph, a
Mayor of San Francisco from 1912 to 1931, was the
Governor of California at the time construction of the bridge began. He died in office on June 2, 1934, two years before the bridge opened, leaving the bridge to be named for him out of respect. a section of the upper deck of the eastern
truss portion of the bridge at Pier E9 collapsed onto the deck below, indirectly causing one death. The bridge was closed for just over a month as construction crews repaired the section. That same year, the bridge reopened to traffic on November 18.
2001 terrorism threat On November 2, 2001, in the aftermath of the
September 11 attacks, Governor
Gray Davis announced a threat of a rush hour attack against a West Coast suspension bridge (a group which includes the Bay Bridge and the
Golden Gate Bridge) some time between November 2 and 7, resulting in an increase of openly armed law enforcement patrols. A small fraction of drivers shifted to ferries and
BART. It was later revealed that crews had secretly been working under armed guard for several weeks to harden the suspension cable attachment points, which were vulnerable to cutting with common weapons and tools. An anchor room was filled with concrete, doors welded shut, and a
razor wire fence added. A blast wall was also added to defend against a potential
truck bomb. In the end, no attack occurred.
Emperor Norton naming campaign In November 2004, after a campaign by
San Francisco Chronicle cartoonist
Phil Frank, then-San Francisco District 3 Supervisor
Aaron Peskin introduced a resolution to the
San Francisco Board of Supervisors calling for the entire two-bridge system, from San Francisco to Oakland, to be named for Emperor Norton. On December 14, 2004, the Board approved a modified version of this resolution, calling for only "new additions"—i.e., the new eastern crossing—to be named "The Emperor Norton Bridge". Neither the City of Oakland nor Alameda County passed any similar resolution, so the effort went no further.
Western span retrofit (left, original eastern span) and bolted box beam retrofit (right, western span) The western section has undergone extensive
seismic retrofitting. During the retrofit, much of the
structural steel supporting the bridge deck was replaced while the bridge remained open to traffic. Engineers accomplished this by using methods similar to those employed on the
Chicago Skyway. The entire bridge was fabricated using hot steel rivets, which are impossible to heat treat and so remain relatively soft. Analysis showed that these could fail by shearing under extreme stress. Therefore, at most locations, rivets were replaced with high-strength bolts. Most bolts had domed heads placed facing traffic so they looked similar to the rivets that were removed.. This work had to be performed with great care as the steel of the structure had for many years been painted with
lead paint, which had to be carefully removed and contained by workers with extensive protective gear so that they would not be exposed to the toxic lead paint. Most of the beams were originally constructed of two plate -beams joined with lattices of flat strip or angle stock, depending upon structural requirements. These have all been reconstructed by replacing the riveted lattice elements with bolted steel plate and so converting the lattice beams into box beams. This replacement included adding face plates to the large diagonal beams joining the faces of the main towers, which now have an improved appearance when viewed from certain angles. Diagonal box beams have been added to each bay of the upper and lower decks of the western spans. These add stiffness to reduce side-to-side motion during an earthquake and reduce the probability of damage to the decking surfaces. Analysis showed that some massive concrete supports could burst and crumble under likely stresses. In particular, the Western supports were extensively modified. First, the location of the existing reinforcing bar is determined using magnetic techniques. In areas between bars, holes are drilled. Into these holes is inserted and glued an L-shaped bar that protrudes . This bar is retained in the hole with a high-strength
epoxy adhesive. The entire surface of the structure is thus covered with closely spaced protrusions. A network of horizontal and vertical reinforcing bars is then attached to these protrusions. Mold surface plates are then positioned to retain high-strength concrete, which is then pumped into the void. After removal of the formwork, the surface appears similar to the original concrete. This technique has been applied elsewhere throughout California to improve freeway overpass abutments and some overpass central supports that have unconventional shapes. (Other techniques such as
jacket and grout are applied to simple vertical posts; see the
seismic retrofit article.) The Western approaches have also been retrofitted in part, but mostly these have been replaced with new construction of reinforced concrete.
2007 Cosco Busan oil spill In 2007, a container ship then named the
Cosco Busan, and subsequently renamed the
Hanjin Venezia, collided with the Delta Tower fender, resulting in the
Cosco Busan oil spill.
October 2009 eyebar crack, repair failure and bridge closure During the 2009
Labor Day weekend closure for a portion of the replacement, a major crack was found in an
eyebar, significant enough to warrant bridge closure. Working in parallel with the retrofit,
California Department of Transportation (Caltrans), and its contractors and subcontractors, were able to design, engineer, fabricate, and install the pieces required to repair the bridge, delaying its planned opening by only hours. The repair was not inspected by the
Federal Highway Administration, which relied on state inspection reports to ensure safety guidelines were met. On October 27, 2009, during the evening commute, the steel crossbeam and two steel tie rods repaired over
Labor Day weekend snapped off the Bay Bridge's eastern section and fell to the upper deck. This may have been due to metal-on-metal vibration from bridge traffic and wind gusts of up to , which resulted in one of the rods breaking off and caused one of the metal sections to come crashing down. Three vehicles were either struck by or hit the fallen debris, though there were no injuries. On November 1, Caltrans announced that the bridge would probably stay closed at least through the morning commute of Monday, November 2 after repairs performed during the weekend failed a stress test on Sunday.
BART and the
Golden Gate Ferry systems added supplemental service to accommodate the increased passenger load during the bridge closure. The bridge reopened to traffic on November 2, 2009. The pieces that broke off on October 27 were a saddle, crossbars, and two tension rods.
2010s–present Willie L. Brown, Jr., Bridge naming resolution In June 2013, nine state assemblymen, joined by two state senators, introduced Assembly
Concurrent Resolution No. 65 (ACR 65) to name the western crossing of the bridge for former California Assembly Speaker and former San Francisco Mayor
Willie Brown. Six weeks later, a grassroots petition was launched seeking to name the entire two-bridge system for Emperor Norton. In September 2013, the petition's author launched a nonprofit, The Emperor's Bridge Campaign — now known as
The Emperor Norton Trust — that advocates for adding "Emperor Norton Bridge" as an honorary name (rather than "renaming" the bridge) and that undertakes other efforts to advance Norton's legacy. The state legislative resolution naming the western section of the Bay Bridge the "Willie L. Brown, Jr., Bridge" passed the Assembly in August 2013 and the Senate in September 2013. A ceremony was held on February 11, 2014, marking the resolution and the installation of signs on either end of the section.
Eastern span replacement For various reasons, the eastern section would have been too expensive to retrofit compared to replacing it, so the decision was made to replace it. The replacement section underwent a series of design changes, both progressive and regressive, with increasing cost estimates and contractor bids. The final design included a single-towered
self-anchored suspension span starting at Yerba Buena island, leading to a long inclined viaduct to the Oakland touchdown. Separated and protected bicycle lanes are a visually prominent feature on the south side of the new eastern section. The
bikeway and pedestrian path across the eastern span opened in October 2016 and carry recreational and commuter cyclists between Oakland and Yerba Buena Island. The original eastern cantilever span had
firefighting dry standpipes installed. No
firefighting dry or
wet standpipes were designed for the eastern section replacement, although, the
firefighting wet standpipes do exist on the original western section visible on both the north-side upper and lower decks. The original eastern section closed permanently to traffic on August 28, 2013, and the replacement span opened for traffic five days later. The original eastern section was dismantled between January 2014 and November 2017. File:800px-EasternSFOBBSkyExt.jpg|Some new construction (2004) File:SFOBBESR-1787C-May15-2011.jpg|Substantial progress (2011) File:SFOBBESR-1787C-Oct-1-2013.JPG|The completed replacement and the old bridge (2013) File:San Francisco–Oakland Bay Bridge - Old and New bridges.jpg|Rest of old and new bridge (June 2015) File:ProposedSFOBBEasternSpanRecrop.jpg|Artist's simulation of final appearance after old span demolition
2013 public "light sculpture" installation On March 5, 2013, a public art installation called "
The Bay Lights" was activated on the western span's vertical cables. The installation was designed by artist
Leo Villareal and consists of 25,000
LED lights originally scheduled to be on nightly display until March 2015. However, on December 17, 2014, the non-profit Illuminate The Arts announced that it had raised the $4 million needed to make the lights permanent; the display was temporarily turned off starting in March 2015 in order to perform maintenance and install sturdier bulbs and then re-lit on January 30, 2016. In order to reduce driver distractions, the privately funded display is not visible to users of the bridge, only to distant observers. This lighting effort is intended to form part of a larger project to "light the bay". Villareal used various algorithms to generate patterns such as rainfall, reflections on water, bird flight, expanding rings, and others. Villareal's patterns and transitions will be sequenced and their duration determined by a computerized
random number generator to make each viewing experience unique. Owing to the efficiency of the LED system employed, the estimated operating cost is only US$15.00 per night. The lights were switched off permanently at 8 pm on March 5, 2023 – the 10th anniversary of the artwork. This was done due to their poor condition and increasing costs to maintain them properly. There is a plan to raise additional funds and install a new set of lights later in the year.
Alexander Zuckermann Bike Path The pedestrian and bicycle route on the eastern section opened on September 3, 2013, and is named after Alexander Zuckermann, founding chair of the
East Bay Bicycle Coalition. This forms a transbay route for the
San Francisco Bay Trail. Until October 2016, the path did not connect to Yerba Buena and
Treasure Island sidewalks, due to the need to demolish more of the old eastern section before final construction. On May 2, 2017, public access was extended to seven days a week, 6 a.m. to 9 p.m., with occasional closure days for continued demolition of the old bridge foundations. This work was completed on November 11, 2017.
Yerba Buena Tunnel closure and repair On January 30, 2016, a chunk of concrete the size of an automobile tire fell from the tunnel wall into the slow lane of eastbound traffic on the lower deck of the Yerba Buena Tunnel, causing a minor accident. The concrete fell from where the upper deck is connected to the tunnel wall. Based on an examination of photographs, a professor from Georgia Tech postulated that water infiltration into the concrete wall had caused the reinforcing steel to corrode and expand, forcing a chunk of the tunnel wall out. A subsequent
California Department of Transportation (Caltrans) investigation identified 12 spots on both sides of the tunnel wall in the lower deck space that showed signs of corrosion-induced damage, but no immediate risk of further spalling. The apparent cause was rainwater leaking from upper deck drains. Caltrans engineers speculated that the Masonite pads had swelled due to rainwater infiltration, cracking the tunnel walls and allowing moisture into the reinforcing steel. Repairs to the degraded concrete started in February 2017. Drains and catch basins were replaced to reduce the likelihood of clogging, and fiberglass-reinforced mortar was used to patch removed concrete. The repairs, which required some daytime lane closures, were expected to last until June 2017.
2020 bus lane proposal In January 2020, the
AC Transit and
BART boards of directors supported the establishment of dedicated bus lanes on the bridge. In February 2020,
Rob Bonta introduced state legislation to begin planning bus lanes on the bridge.
Judge John Sutter Regional Shoreline On October 21, 2020,
Judge John Sutter Regional Shoreline park opened to the public. Located at the foot of the bridge, the opening of the park has led to easier access to the Alexander Zuckermann Bike Path due to improved parking and pedestrian access.
2016–2023 exit reconstructions In the 1960s era directional reconfiguration, there were three off-ramps added to Yerba Buena Island and Treasure Island: a single left-hand side exit in the western direction at the east end of the tunnel; a left-hand side exit in the eastern direction at the west end of the tunnel (originally signed as just "Treasure Island"); and a right-hand side exit in eastern direction at the east end of the tunnel (originally signed as just "Yerba Buena Island"). Meanwhile, the eastbound right-hand side off-ramp and on-ramp at the east end of the tunnel was demolished during the reconstruction of the eastern span of the bridge. A new on-ramp on this side was built with a dedicated merge lane, but the off-ramp's replacement was not completed until early-May 2023, well after the
bridge's bike path from the Oakland side to the island was fully completed. The eastbound left-hand side off-ramp and westbound on-ramp at the west end of the tunnel are then scheduled to close as early as late-May 2023, while the western span undergoes a seismic retrofit. ==Financing and tolls==