On February 8, 2005, with the site selection committee still deliberating, President Bush again endorsed placing the museum on the National Mall. The site selection committee did not issue its recommendation until January 31, 2006—a full 13 months late. It recommended the site west of the National Museum of American History. The area was part of the
Washington Monument grounds, but had been set aside for a museum or other building in the
L'Enfant Plan of 1791 and the
McMillan Plan of 1902. The
United States Department of State originally planned to build its headquarters there in the early 20th century, and the
National World War II Memorial Advisory Board had considered the parcel in 1995. On March 15, 2005, the Smithsonian named
Lonnie G. Bunch III to be the Director of the National African American Museum of History and Culture. The National Museum of African American History and Culture Council (the museum's board of trustees) sponsored a competition in 2008 to design a building with three stories below-ground and five stories above-ground. The building was limited to the site chosen by the site selection committee, had to be
LEED Gold certified, and had to meet stringent federal security standards. The cost of construction was limited to $500 million ($ in dollars). The competition criteria specified that the winning design had to respect the history and views of the Washington Monument as well as demonstrate an understanding of the African-American experience. The winning design was required to reflect optimism, spirituality, and joy, but also acknowledge and incorporate "the dark corners" of the African-American experience. The museum design was required to function as a museum, but also be able to host cultural events of various kinds. Hundreds of architects and firms were invited to participate in the design competition. Six firms were chosen as finalists: •
Devrouax+Purnell and
Pei Cobb Freed & Partners •
Diller Scofidio + Renfro, with
KlingStubbins •
Freelon Adjaye Bond/
SmithGroup •
Foster and Partners/
URS Corporation •
Moody Nolan, with
Antoine Predock •
Moshe Safdie and Associates, with Sulton Campbell Britt & Associates The design submitted by the
Freelon Group/
Adjaye Associates/
Davis Brody Bond won the design competition. The above-ground floors featured an inverted
step pyramid surrounded by a
bronze architectural scrim, which reflected an
Oba's crown as used in
Yoruba culture; specifically, these three stacked trapezoidal shapes were inspired by the top of an
Olowe of Ise sculpture which is now on display inside the museum. Under federal law, the
National Capital Planning Commission, the
United States Commission of Fine Arts, and the D.C. Historic Preservation Commission all have review and approval rights over construction in the metropolitan D.C. area. As the design went through these agencies for approval, it was slightly revised. The building was moved toward the southern boundary of its plot of land, to give a better view of the Washington Monument from
Constitution Avenue. The size of the upper floors were shrunk by 17 percent. Although three upper floors were permitted (instead of just two), the ceiling height of each floor was lowered so that the overall height of the building was lowered. The large, box-like first floor was largely eliminated. Added to the entrance on Constitution Avenue were a pond, garden, and bridge, so that visitors would have to "cross over the water" like slaves did when they came to America. The Smithsonian estimated in February 2012 that museum would to open in 2015. Until then, the museum would occupy a gallery on the second floor of the National Museum of American History. On June 10, 2013, media
magnate Oprah Winfrey donated $12 million (~$ in ) to the NMAAHC. This was in addition to the $1 million (~$ in ) she donated to the museum in 2007. The Smithsonian said it would name the NMAAHC's 350-seat theater after her. The
GM Foundation announced a $1 million (~$ in ) donation to the museum on January 22, 2014, to fund construction of the building and design and install permanent exhibits.
Building design changes The design of the architectural scrim which surrounds the building was changed in September 2012. The proposed building itself was a box-like structure. The three-part corona of the building's design was created by a structure only minimally attached to the building. The exterior of this structure, whose frames lean outward to create the corona, consisted of a thin screen or "scrim" perforated by geometrical patterns based on historic iron grilles found in African-American communities in
Charleston, South Carolina, and
New Orleans, Louisiana. The original design proposed that the scrim be made of bronze, which would have made the museum the only one on the National Mall whose exterior was not made of limestone or marble. Cost issues forced the architects to change this to bronze-painted aluminum in September 2012. The change was approved by the Commission of Fine Arts, but the commissioners criticized the change for lacking the warm, reflective qualities of bronze. Noted architect
Witold Rybczynski also criticized the change: "The appeal of bronze is its warm golden sheen and the rich patina that it acquires over time, but uniformly painted surfaces lack these attributes, and over time they don't age, they merely flake. ... At the time of this writing, the African American museum risks compromising its original intention. In architecture, beauty sometimes really is only skin-deep." The Smithsonian then radically changed the landscaping of the under-construction museum in summer 2013. The original design for the museum planned a wetland with flowing creek, bridges, and native plants in this area. But cost considerations led the agency to eliminate it. At first, the Smithsonian proposed a low hedge. It brought this design to the Commission of Fine Arts in April 2013, which rejected it. The Commission expressed "great concern about the possible loss of the symbolic meaning that had been skillfully woven into the design of both the landscape and the building". In July, the Smithsonian replaced the hedge with a low dull black granite wall. The Commission of Fine Arts approved that redesign, and the Smithsonian brought it to the National Capital Planning Commission. As of August 2013, the NCPC was anticipated to approve it. Debate over the corona's finish continued into 2014 before being resolved. The Commission of Fine Arts repeatedly urged the architects to use bronze for the scrim, as it created a "shimmering, lustrous effect under many lighting conditions" and "conveyed dignity, permanence and beauty". Duranar paint was the first substitute proposed by the architects, but the commission members rejected it, noting that it had a "putty-like appearance under overcast conditions" and visually fell "far short of the beautiful poetic intention promised by the concept design".
Construction of the museum building The museum's
groundbreaking ceremony took place on February 22, 2012. President
Barack Obama and museum director Bunch were among the speakers at the ceremony. Guy Nordenson and Associates and Robert Silman Associates were the structural engineers for the project. The NMAAHC became the deepest museum on the National Mall. Excavators dug below grade to lay the foundations, although the building itself will be only deep. The museum is located at a low point on the Mall, and groundwater puts on the walls. To compensate, per minute of water were pumped out every day during construction of the foundation and below-grade walls, and a
slurry of cement and sand injected into forms to stabilize the site. Lasers continually monitored the walls during construction for any signs of bulging or movement. As the lower levels were completed, cranes installed a segregated railroad passenger car and a guard tower from the
Louisiana State Penitentiary on November 17, 2013. These items were so large that they could not be dismantled and installed at a later date. Instead, the museum had to be built around them. Robert Silman Associates oversaw the engineering of the below-grade structure and exhibit structural support. The steel was fabricated by SteelFab, Inc. While the below-grade floors were made of reinforced concrete, with columns supporting each floor above, the above-grade floors were primarily exhibit space and needed to be kept column-free. To support the upper floors, four massive walls, consisting of steel frames and cast-in-place concrete infill, were constructed. Design and fabrication of the steel members of the above-ground structure required extreme precision, as the steel elements penetrated one another at more than 500 places and some beams had several hundred bolt-holes in them. All structural steel elements also had to work almost perfectly with the
rebar and
rebar couplers so that elements would not run into one another and yet maintain structural integrity. A system of girders around the fifth above-ground floor supported the corona. Some of these girders were so complex they required more than 180 parts. The long-span
porch that covers the main entrance was built of long
plate girders and box columns (also made of plate). A long steel
camber beam at the midpoint helps support the porch roof. An elliptical monumental staircase runs continually between the above-ground floors. This staircase has no intermediate supports, and weighs in at more than . SteelFab fabricated more than of structural steel for the museum in conjunction with AIW, Inc. who fabricated the architecturally exposed, and ornamental steel and bronze metal work. SteelFab received an award from the Washington Building Congress for its work.
Topping out of the museum occurred in October 2014. The entire steel superstructure and all above-ground concrete pouring was complete in January 2015. Glass for the windows and
curtain walls began to be placed that same month, with glass enclosure of the building complete on April 14, 2015. That same day, the first of the structure's 3,600 bronze-colored panels for the building's corona were installed. 35-year-old Ivan Smyntyna was rushed to a local hospital, where he later died. The building has a total of 10 stories (five above and five below ground). President Barack Obama would dedicate the museum, which would be followed by a week of special events. The museum would open for extended hours during that week to accommodate crowds and visitors. NMAAHC officials said that construction scaffolding around the exterior of the building should come down in April 2016, at which time some of the more dust-and-humidity resistant artifacts and displays could be installed. Installation of more delicate items would wait until the building's environmental controls had stabilized the interior humidity and removed most of the dust from the air. The museum identified 3,000 items in its collections which would form 11 initial exhibits. More than 130 video and audio installations would be installed as part of these exhibits. as well as a $1 million donation from
Wells Fargo. As of January 30, 2016, the museum still needed to raise $40 million toward its $270 million construction goal. David Rubenstein purchased both items in 2012. In late March 2016,
Microsoft announced a $1 million (~$ in ) donation to the museum. On March 27, the museum drew criticism for agreeing to include a small number of items from the career of actor
Bill Cosby in a planned exhibit about African Americans in the entertainment industry. Women who
have accused Cosby of sexual assault objected to the display. In response to the resulting controversy, the museum added the following sentence to its description of Cosby's career: "In recent years, revelations about alleged sexual misconduct have cast a shadow over Cosby's entertainment career and severely damaged his reputation." Google donated $1 million (~$ in ) to the museum in early September 2016. The technology firm had previously worked with the NMAAHC to create a 3D interactive exhibit which allows visitors to see artifacts in a close-up, 360-degree view using their mobile phone. The 3D exhibit was created by designers and engineers from the Black Googler Network. On September 16, 2016, violinist
Edward W. Hardy composed and performed
Evolution - Inspired by the Evolution of Black Music for the
Congressional Black Caucus at a
Google sponsored event in
Howard Theatre. This event was a part of the opening of the
Smithsonian National Museum of African American History and Culture. On September 23, 2016,
The Washington Post reported that
Robert F. Smith, the founder, chairman, and CEO of
Vista Equity Partners, had given $20 million (~$ in ) to the NMAAHC. The gift was second-largest in the museum's history, exceeded only by the $21 million donated by Oprah Winfrey.
Ava DuVernay was commissioned by the museum to create a film which debuted at the museum's opening on September 24, 2016. This film,
August 28: A Day in the Life of a People (2016), tells of six significant events in African-American history that happened on the same date, August 28. The 22-minute film stars
Lupita Nyong'o,
Don Cheadle,
Regina King,
David Oyelowo,
Angela Bassett,
Michael Ealy,
Gugu Mbatha-Raw,
André Holland and
Glynn Turman. Events depicted include
William IV's
royal assent to the
UK Slavery Abolition Act in 1833, the 1955 lynching of 14-year-old
Emmett Till in
Mississippi, the release of
Motown's first number-one song, "
Please Mr. Postman" by
The Marvellettes, Martin Luther King, Jr.'s 1963 "
I Have a Dream" speech, the landfall of
Hurricane Katrina in 2005 and the night then-senator
Barack Obama accepted the Democratic nomination for president at the
2008 Democratic National Convention. The bell came from the first Baptist church organized by and for African Americans, founded in 1776 in Williamsburg, Virginia, where at the time it was unlawful for blacks to congregate or preach. The opening ceremony also included a speech by
Muriel Bowser and a performance by
Angélique Kidjo. The total cost of the museum's design, construction, and installation of exhibits was $540 million ($ in dollars). By the time the museum's founding fundraising campaign had ended, the NMAAHC had raised $386 million ($ in dollars), 143 percent more than its goal of $270 million. . National Museum of African American History and Culture, Smithsonian Institution, Washington, DC ==Attendance and timed-entry ticketing==