MarketSouth Coast Rail
Company Profile

South Coast Rail

South Coast Rail is a project to expand the MBTA Commuter Rail system into the South Coast region of Massachusetts, United States. The first phase opened on March 24, 2025, becoming part of the Fall River/New Bedford Line. It extended service from Middleborough via Taunton with branches to Fall River, and New Bedford. Six stations and two layover yards were constructed and 36.1 miles (58.1 km) of freight railroad track were rebuilt for passenger service.

Route
Phase 1 |alt=A high-level railway station platform with trains on both sides The project, primarily located in the South Coast region of Massachusetts, is split into two phases. Phase 1 opened on March 24, 2025, as part of the Fall River/New Bedford Line. It was an extension of the existing Middleborough/Lakeville Line using diesel-hauled trains. The Phase 1 routing splits from the Middleborough Main Line in downtown Middleborough, with Middleborough station replacing Middleborough/Lakeville station. It runs west along the Middleboro Secondary through Lakeville and Taunton to Cotley Junction, where it turns southeast onto the New Bedford Main Line and reaches East Taunton station. At Myricks Junction in Berkley it splits into two southern branches. The Fall River Branch follows the Fall River Secondary southwest through Freetown and Fall River, with stops at Freetown station and Fall River station. The New Bedford Branch follows the New Bedford Main Line southeast through Lakeville, Freetown, and New Bedford, with stops at Church Street station and New Bedford station. Total cost for the both phases was estimated as $3.4 billion in 2017 (equivalent to $billion in ). An trestle atop the embankment is proposed to allow animals to pass under the tracks and limit the disturbance to the existing ground. The trestle would use concrete box girders on piles spaced at , with a maintenance siding in the middle. ==Previous service==
Previous service
Expansion Previous passenger service to the South Coast ran over four different routes: via Mansfield, via Stoughton, via Randolph, and via Middleborough. The first rail line to reach the area was the Taunton Branch Railroad, which connected with the Boston and Providence Railroad (B&P) at Mansfield. It opened to Taunton in August 1836; a closely affiliated extension, the New Bedford and Taunton Railroad, opened to New Bedford in July 1840. The Middleborough and Taunton Railroad opened in July 1856; it connected with the New Bedford and Taunton at Cotley Junction south of Taunton. The rest of the line opened in 1846 from Myricks through Middleborough to South Braintree on the Old Colony Railroad, creating a second route from Fall River to Boston. The next year, owner Richard Borden founded the Fall River Line, which operated New York–Fall River steamship service. It connected with the "Boat Train" on the Fall River Railroad to provide New York–Boston through service. The Stoughton Branch Railroad opened in April 1845 from Stoughton to Canton Junction on the B&P. The New Haven merged in late 1968 into Penn Central, which merged into Conrail in 1976. Passenger service continued on the ex-B&P, including the Stoughton Branch, eventually becoming the Providence/Stoughton Line. ==South Coast Rail planning==
South Coast Rail planning
Restoration planning (1980s–2003) The Massachusetts Bay Transportation Authority (MBTA) was formed in 1964 to subsidize suburban rail service and build rapid transit extensions. Contraction of the New Haven's Boston commuter service largely ended after 1967; expansion of service frequency and area began in the late 1970s. In the 1980s, the restoration of the lines to New Bedford and Fall River was proposed. Since the routes via Mansfield and Randolph and the Middleborough–Myricks segment of the Middleborough route were abandoned and built over, three possible routes to the South Coast were placed under consideration: the Stoughton route, a route following the Northeast Corridor to near and then branching onto the Attleboro Secondary, and a route following the Middleborough Main Line to Middleborough then the Middleboro Secondary westwards. All three routes used the same lines from Taunton south to Fall River and New Bedford. By 1988, the MBTA was tentatively planning to extend service to Taunton via Stoughton. The first major study, completed in January 1990, concluded that the Stoughton Branch was the most viable route. The study was criticized for not considering other alternatives, including express buses. A May 1991 bond bill included $3million (equivalent to $million in ) for planning the extension. In 1991, the state agreed to build a set of transit projects as part of an agreement with the Conservation Law Foundation (CLF), which had threatened a lawsuit over auto emissions from the Central Artery/Tunnel Project (Big Dig). Among these projects was the "Old Colony Commuter Rail Line Extension", to be complete by the end of 1996. This included the Middleborough/Lakeville Line and Plymouth/Kingston Line, which opened in 1997, plus the 2007-opened Greenbush Line. Planning for service to the South Coast continued. The March 1995 Expanded Feasibility Study analyzed routes absent from the 1990 report. The 1965–1980 construction of the Braintree Branch had only left space for a single track (intended for freight use) on the Old Colony mainline through parts of Dorchester and Quincy. This limited the capacity required for reaching the South Coast via Middleborough: service could be operated to one of Fall River and New Bedford, but not both. In August 1996, Governor Bill Weld signed a bill giving $136million (equivalent to $million in ) to commuter rail expansion, while the state legislature directed the MBTA to further study alternatives. The 1997 Expanded Alternatives Analysis showed vastly increased costs — $407 million (equivalent to $million in ) via Attleboro, $410 million ($million) via Stoughton, or $436 million ($million) via Middleborough. Service via Middleborough would also require double-tracking on the Old Colony mainline at additional cost. The report recommended the Stoughton route as the most cost-effective due to its high ridership. A groundbreaking ceremony was held in October 1998 after a contract for bridge work in Fall River and New Bedford was awarded that month. Based on an analysis of South Station operations, the July 1999 Draft Environmental Impact Report concluded that the Stoughton route was the only viable route. It projected 4,325 daily riders with 20 trains per day to each of Fall River and New Bedford. In January 2000, following then-governor Paul Cellucci's reapproval, the state reported that construction would begin in late 2002 and last until 2004. The Phase 1 Alternatives Analysis Report, released in April 2008, narrowed 65 options (including unlikely modes like heavy rail metro and monorail) to five plausible alternatives: the Attleboro, Stoughton, and Middleboro routes, a mixture of Attleboro and Middleboro service, and express bus service. The Massachusetts Department of Transportation (MassDOT) released 18 potential station sites for the project in September 2008. In May 2008, MassDOT issued a formal request to the US Army Corps of Engineers to allow discharge of fill materials into wetlands — effectively starting the formal environmental review process. The agreement was signed on September 23, 2009. On June 11, 2010, the state and CSX completed the first phase of the agreement, including the transfer of the South Coast Rail lines to MassDOT. In a May 2009 interview, Commonwealth Treasurer Tim Cahill stated that "it is virtually going to be impossible" for the state to complete the project in 2016 as planned due to the recession, adding that federal funding was unlikely to be obtained because "[t]he federal government doesn't trust us anymore because of the Big Dig." The state released the South Coast Rail Economic Development and Land Use Corridor Plan, which called for substantial mixed-use transit-oriented development around stations, in June 2009. The Phase 2 Alternatives Analysis Report, which indicated electric or diesel service through Stoughton as the best choice, was released in September 2009. The Army Corps of Engineers released the Draft Environmental Impact Statement (DEIS) in March 2011. Concurring with previous documents it recommended that South Coast Rail be routed through Stoughton, citing in particular the need to add a billion-dollar fourth track from to to accommodate service through Attleboro. A state transportation funding bill passed in July 2013 mentioned South Coast Rail as deserving funding but did not specifically allocate money to the project. In September 2013, the Army Corps of Engineers released the Final Environmental Impact Statement. It made small changes to several station sites and selected locations for layover yards. The projected cost for electric service was revised slightly downward to $1.817 billion (equivalent to $billion in ). A spending bill passed in April 2014 allocated $2.3 billion (equivalent to $billion in ) for South Coast Rail. On June 18, 2014, MassDOT awarded a one-year, $12 million contract (equivalent to $million in ) – with up to $210 million (equivalent to $million in ) possible over 10 years – to a joint venture between Vanasse Hangen Brustlin, Inc. and HNTB for "program management, early design development, and environmental permitting". Project changes (2016–2021) In June 2016, the MBTA announced that the project cost had been revised to $3.42 billion (equivalent to $billion in ), with completion not expected until 2030. The substantial delay and increase in cost caused officials to consider alternate plans, including an interim service to New Bedford via Middleborough. Some local and regional officials objected to that plan, as it would have reduced service to Middleborough/Lakeville station and potentially interfered with Plymouth/Kingston Line and Greenbush Line service. Design for the Stoughton route was 15% complete by that time. In March 2017, the state announced a revised plan intended to provide service sooner than 2030. The $1.1 billion Phase 1 (equivalent to $billion in ) would follow the Middleborough route and open in 2024; Phase 2 would follow the original route through Stoughton (including electrification) and open in 2029. By June 2017, the planned completion dates were changed to Phase 1 in 2022 and Phase 2 in 2030, with stations at and in Phase 1 rather than Phase 2 as proposed in March. The two-phase approach attracted criticism from several directions, including some of those who had previously advocated for the project as well as previous opponents. Stoughton, Easton, and Raynham officials continued their previous opposition to South Coast Rail. The Draft Supplemental Environmental Impact Report (DSEIR) was released in January 2018. It determined that a new station would be built at to replace Middleborough/Lakeville, and that East Taunton station would be built instead of Taunton station, as serving Middleborough/Lakeville or Taunton would require time-consuming reverse moves. Battleship Cove station was moved back to Phase 2. The 1,610 projected daily boardings at the non-Middleborough stations were 41% of the 3,960 projected for Phase 2, leading to criticisms from public officials about the cost effectiveness of the project. The Final Supplemental Environmental Impact Report was released in April 2018. Design work and permitting were largely complete by March 2019. In April 2019, the state announced that a funding plan and Army Corps of Engineers permits for the Phase 1 plan were in place and that the project would proceed "full speed ahead," with a target of late 2023 for revenue service. Projected cost was $1.047 billion (equivalent to $billion in ). A transportation bond bill that included $825 million (equivalent to $million in ) for Phase 1 was filed in July 2019 and passed in January 2021. == Phase 1 construction ==
Phase 1 construction
Early work Several elements of the project were constructed prior to the main construction phases. In February 2010, MassDOT received a $20 million TIGER grant (equivalent to $million in ) to replace three bridges in New Bedford built around 1907, for immediate freight use and future South Coast Rail service. The grant represented part of the $71.4 million (equivalent to $million in ) the state had applied for to fund the Fast Track New Bedford project, which would have also included a fourth bridge, construction of New Bedford station with an adjacent bus terminal, and pedestrian and bicycle access improvements. The MBTA awarded the contract in August 2010; the replacement bridges opened for Massachusetts Coastal Railroad freight use in November 2011. In 2013 and 2014, MassDOT replaced 42,000 ties along of the Fall River and New Bedford branches. A $18.4 million, two-year contract (equivalent to $million in ) was issued on October 22, 2014 for reconstruction of six grade crossings in Taunton, Freetown, and New Bedford. On November 25, 2014, a $42 million contract (equivalent to $million in ) was awarded for the replacement of three bridges (President Avenue, Brownell Avenue, and Golf Club Road) in Fall River plus the Wamsutta Street bridge in New Bedford. The bridges were completed in early 2017. Contracts Phase 1 was divided into eight major construction contracts. Land acquisition and three "early action" contracts began while design proceeded for other work. Contract No. 1 for 57 turnouts was awarded to Progress Rail on December 14, 2018. The $18.3 million contract (equivalent to $million in ) was awarded to J.F. White on March 6, 2019, with completion expected in June 2020. The $26.1 million contract (equivalent to $million in ) was awarded to J.F. White, with completion planned for November 2020. While MassDOT managed the early action contracts, oversight of the program was transferred to the MBTA in preparation for the start of Phase 1 construction in 2019. That April, the MBTA awarded a $62 million contract (equivalent to $million in ) to AECOM for program and construction management. A groundbreaking ceremony was held on July 2, 2019. Contract No. 6 included of track work on the Middleboro Secondary and New Bedford Secondary, four stations, the Wamsutta Layover, seven bridges, and associated infrastructure. It also included signal and communication systems for the whole project area. Contract No. 10 was for construction of a footbridge over Route 18 at New Bedford station. Contract No. 12 was for traffic mitigation during construction, including intersection and traffic signal modifications. The $8.5 million contract (equivalent to $million in ) was awarded to Newport Construction in early 2022. Replacement of a bridge carrying Route 24 over the New Bedford Secondary in East Taunton was originally planned to be Contract No. 5. Construction and opening By May 2021, Fall River Secondary work was 20% complete, while Middleborough Secondary/New Bedford Main Line work was 5% complete. Progress was at 35% and 18% by November 2021. In 2022, granite blocks from culverts and bridge abutments replaced during the project were dumped into Nantucket Sound off Yarmouth and Harwich to create artificial reefs. Overall project completion reached the halfway point in mid-2022. By August 2022, Fall River Secondary work was 81% complete, while Middleborough Secondary/New Bedford Main Line work was 53% complete. In the November 2022 election, both Fall River and New Bedford voted to join the MBTA funding district, a prerequisite for service. Substantial completion of the Fall River Secondary work was announced with a ribbon-cutting ceremony in December 2022; at that point, revenue service was still planned for late 2023. In September 2023, the MBTA indicated that revenue service would not begin until mid-2024. New Bedford Secondary work was 85% complete by that time. In April 2024, the MBTA acknowledged that a midyear opening was unlikely, but did not provide a new schedule. The delay was attributed to systems testing and the construction of East Taunton station both taking longer than expected. Test trains began operating on June 17, 2024. That month, the MBTA announced that the planned opening had been delayed again to May 2025. In July 2024, the MBTA indicated that weekend service would operate on the lines. Automatic train control testing on the South Coast Rail lines was completed in July 2024. Operations and maintenance shifted to Keolis on January 6, 2025, following the December 2024 completion of positive train control testing. On February 7, 2025, the MBTA announced that Phase 1 service would begin on March 24 pending final approval by the Federal Railroad Administration (FRA). MassDOT formally transferred ownership of the lines to the MBTA in late February. The FRA did not give final regulatory approval until March 21, 2025. Service began on March 24, 2025, as the Fall River/New Bedford Line. The Southeastern Regional Transit Authority did not modify its bus routes for the new stations, instead piloting a microtransit service. The months after the extension saw several service quality issues. Most were due to crew shortages and other temporary problems, though the MBTA also cited difficulty coordinating trains on the mostly-single-track line as a cause of performance issues. File:Culvert installation at Tarkiln Hill Road, October 2019.jpg|Culvert installation in New Bedford in October 2019|alt=A concrete culvert section being lowered into a trench File:Platform foundations for Middleborough station (1), December 2021.JPG|Middleborough station under construction in December 2021|alt=Foundations for a railway platform next to a rail line File:Setting ties for South Coast Rail, 2022.jpg|Ties being set for a new track in Berkley in 2022|alt=Workers using a machine to place wooden railway ties File:Ribbon cutting ceremony at Freetown station, December 2022.jpg|Dignitaries at the ribbon-cutting ceremony at Freetown station in December 2022|alt=A group of people cutting a ribbon at a train station File:East Taunton station, 2023.jpg|East Taunton station under construction in 2023|alt=Foundations for a railway platform and a partially-complete footbridge == Phase 2 plans ==
Phase 2 plans
The portion of the route between Stoughton and Taunton, proposed for construction in Phase 2, has proved the most controversial part of the project. While the cities of Taunton, Fall River, and New Bedford pushed for the project, the towns of Raynham and Easton objected to the Stoughton route beginning in the 1990s, citing concerns about pollution, traffic, and grade crossing safety. The two towns began legal action opposing the project in 1997; Stoughton joined in 2001. Their legal fight focused on potential impacts to the Hockomock Swamp. In his 2002 approval of the Final Environmental Impact Report, Secretary of Environmental Affairs Robert Durand mandated the construction of a trestle through the swamp to reduce impacts. Later planning included the trestle plan. In 2009, Stoughton officials indicated that they would seek for a tunnel to be built through the downtown area — as was done in Hingham on the Greenbush Line — with Stoughton station moved underground. A town committee found that the state was unlikely to fund such a plan. When plans for the phased approach were announced in 2017, Stoughton, Easton, and Raynham officials continued their previous opposition to the project. Whether Phase 2 of the project will ever be built is unclear. By mid-2024, MassDOT no longer indicated that it would be built by 2030. No funding for Phase 2 was included in the MBTA's FY 2026–2030 capital investment plan in 2025. ==Notes==
tickerdossier.comtickerdossier.substack.com