Upon acquiring the subs, Maritime Command suggested that the subs would be operational by 2000. This included an 18-month systems check. Each sub would undergo a six-month Canadian Work Period (CWP). During the CWP, Canadian communications and fire control systems were installed. The first ship on the scene was the Irish patrol vessel , which suffered damage in the heavy seas and was forced to return to port. The British frigate arrived the following day to provide aid. Rescue efforts had been hampered by the poor weather. The three seriously injured crewmen were evacuated by
Montroses helicopter and flown directly to
Sligo, Ireland. One sailor died of his injuries shortly after arrival.
Chicoutimi was taken in tow on 7 October and arrived back at Faslane on 9 October.
Chicoutimi was transported to Halifax aboard the submersible heavy-lift vessel
Eide Transporter, arriving on 1 February 2005. The commissioning of the submarine was delayed until the assessment of the damage could take place. Following the assessment,
Chicoutimi was carried to Esquimalt aboard the submersible heavy-lift ship
Tern, arriving on 29 April 2009 to undergo a major refit. The submarine surfaced and made port without requiring aid. Repairs and a major refit kept the sub out of operational service until 2018.
Victoria emerged from the EDWP at the end of 2011. During the cruise,
Windsor was deployed to track five submarines from another nation that had entered the North Atlantic. Canada announced plans for a major life extension for the class on 7 April 2015, possibly to start in 2020. The estimated cost for the program would be between $1.5 and $2 billion CAN. , October 2017 On 3 September 2015,
Chicoutimi was commissioned into the Royal Canadian Navy at Esquimalt. However, the sub was restricted to shallow-water diving. In October 2015,
Chicoutimi was among the Canadian vessels sent to participate in a joint exercise with the
United States Navy.
Chicoutimi and
Victoria were taken out of active service in 2016 after hundreds of welds were found to not meet quality standards, affecting the ability of the subs to dive. They were docked at Esquimalt for several months.
Chicoutimi was repaired first, followed by
Victoria.
Victoria was used for training purposes until repairs were effected. In September 2017, Canada deployed
Chicoutimi on patrol in Asian waters, the first such deployment by a
Victoria-class submarine. During the deployment,
Chicoutimi marked the first visit to Japan by a Canadian submarine since 1968. The vessel returned to Canada on 21 March 2018 spending 197 days at sea, the longest deployment by a
Victoria-class submarine in Canadian service.
Life extension and replacement Under the
Justin Trudeau government's defence policy paper,
Strong Secure Engaged (2017), the operational life of each
Victoria-class boat was to be extended by one additional "life-cycle" (or by about eight years). This was designed to permit the operation of the fleet into about the early to mid-2030s. As of 2020 no decision had been taken on the actual replacement of Canada's submarines which were then already thirty years old. Analysis by the Naval Association of Canada indicated that the lead times, technical challenges and costs involved in submarine replacement would be significant were such a program to be initiated. According to John Ivison, Royal Canadian Navy personnel assessed six submarines that could be a potential replacement. They consist of the conventional , the
Type 212CD, the , the
KSS-III class, the
Isaac Peral class and the . On 10 July 2024, the Government of Canada announced the
Canadian Patrol Submarine Project (CPSP). Up to 12 conventionally powered submarines are to be acquired for the RCN. An RFI was issued by Public Services and Procurement Canada (PSPC) in September 2024. On 21 November, it was reported that the
Taigei class was no longer being considered. In August 2025, the government narrowed the choice down to the Type 212CD and the KSS-III. David Pugliese in the
Ottawa Citizen reported that former navy officers estimated the program costs would be around $100 billion with the first new submarines estimated to be ready by 2037. ==Boats in class==