Harlem–125th Street is the planned northern
terminal for
Phase 2 of the Second Avenue Subway. It would be built underneath 125th Street, below and perpendicular to the existing Lexington Avenue Line station. Phase 2 would stretch from
96th Street to 125th Street, with the next stations south being
116th Street and
106th Street. When opened, it will initially be served by the
Q train, with the
T providing service when phase 3 of the line is built.
Introduction of the station to plans A station at Lexington Avenue and 125th Street was not on the original Second Avenue Subway proposed as part of the
New York City Transit Authority's 1968
Program for Action; instead, a Second Avenue Subway station would be built at 126th Street and Second Avenue. The line was to be built in two phases—the first phase from 126th to 34th Streets, the second phase from 34th to Whitehall Streets. In March 2007, plans for the
construction of the Second Avenue Subway were revived. The line's first phase, the "first major expansion" to the New York City Subway in more than a half-century, included three stations in total and cost $4.45 to $4.5 billion, spanning from 105th Street and Second Avenue to 63rd Street and Third Avenue. Phase 1 opened on January 1, 2017, with the line's northern terminal at
96th Street. The second phase, between 125th and 96th Streets, was allocated $525 million in the MTA's 2015–2019 Capital Plan for planning, design, environmental studies, and utility relocation. This phase will complete the project's East Harlem section. The alignment will run under Second Avenue to 124th Street, before turning west on 125th Street. On October 18, 2016, the
de Blasio administration announced a rezoning plan for East Harlem. One of the three Special Transit Land Use (TA) districts is for the area of the 125th Street station. On November 21, 2016, the MTA requested that the Phase 2 project be entered into the Project Development phase under the Federal Transit Administration's New Starts program. On December 15, several elected officials for the area announced that they were seeking $6 billion of funding for Phase 2 of the line, including $2 billion from the federal government. These officials wished to secure funding from the
presidential administration of
Barack Obama before Obama's term ended on January 20, 2017. In their request for funding, they cited that they wanted to avoid an uncertain response from the
first administration of
Donald Trump and start construction on Phase 2 as soon as possible. Under the approved plan, the MTA would complete an environmental reevaluation by 2018, receive funding by 2020, and open Phase 2 between 2027 and 2029. In January 2017, it was announced that Phases 2 and 3, which are expected to cost up to a combined $14.2 billion, were on the Trump administration's priority list of 50 most important transportation projects nationwide.
Current plans In July 2018, the MTA released a supplemental environmental assessment for Phase 2 of the Second Avenue Subway. The updated report indicated that the 125th Street station would be relocated about west and below what had been proposed in the 2004 FEIS, to reduce impacts on nearby buildings. The proposed three-track station was reduced to two tracks. The modification would reduce flexibility, but would allow the section under 125th Street to be mined, rather than being constructed as cut-and-cover, thereby reducing impacts on nearby buildings. Simulations showed that a two-track layout could support the same level of service that the three-track layout could have provided: 28 trains per hour. To make up for the loss of the track, the tail tracks west of the station would be lengthened. and
switches to the east of the platforms. The July 2018 plans call for two tracks and one island platform, with switches both to the west and the east. The tail tracks would extend to
Lenox Avenue to allow for six trains to be stored, three per track. Extra transfer capacity to the existing Lexington Avenue Line station would be provided as part of the construction of the Harlem–125th Street terminal.
Construction progress The construction of the Second Avenue Subway was expected to improve quality of life around the existing subway station at Lexington Avenue, which was notorious for crime and drug use. In August 2025, the MTA board awarded a $1.97 billion contract to Connect Plus Partners, a
joint venture between Halmar International and
FCC Construction. The contract includes the construction of the 125th Street station shell, reconstruction of the existing tunnel near the 116th Street station, and new tunnels between Second Avenue–120th Street and Lenox Avenue–125th Street. Also in 2025, the MTA requested that the site of the Second Avenue Subway's 125th Street station be
rezoned to allow the construction of 684 apartments above the station entrance.
Second Avenue Subway Community Information Center A Second Avenue Subway Community Information Center for Phase 2, along 125th Street between Park and Madison Avenues, was originally planned to open in May 2017. The center's opening was delayed to September 18, 2017. ==Media==