Beginning of construction Second Avenue Subway plans for Phase 1 were only allowed to proceed because New York voters passed a transportation bond issue on November 8, 2005, allowing for dedicated funding allocated for that phase. Its passage had been seen as critical to its construction, but the bond was passed only by a narrow margin, with 55 percent of voters approving and 45 percent disapproving. After warning that failure to pass the act would doom the project, MTA chairman
Peter S. Kalikow stated, "Now it's up to us to complete the job." On December 18, 2006, the
U.S. Department of Transportation announced that they would allow the MTA to commit up to $693 million in funds to begin construction of the Second Avenue Subway and that the federal share of such costs would be reimbursed with FTA transit funds, subject to appropriations and final labor certification. Preliminary engineering and a final tunnel design was completed by a
joint venture between
AECOM and
Arup. The first phase was originally supposed to include a core tunneling section between 62nd and 92nd Streets, as well as a spur from Third Avenue/63rd Street to Second Avenue/65th Street. The 96th Street station cavern, as well as existing tunnels, would allow the first phase's trackage to run from 62nd to 105th Streets. Before construction started, the MTA revised their plans so that the construction of the section between 62nd and 65th Streets was postponed. On March 20, 2007, upon completion of preliminary engineering, the MTA awarded a contract for constructing the tunnels between 92nd and 63rd Streets, a launch box for the
tunnel boring machine (TBM) at 92nd to 95th Streets, and access shafts at 69th and 72nd Streets. This contract, valued at $337 million, was awarded to S3, a joint venture of Schiavone Construction,
Skanska USA Civil, and J.F. Shea Construction. A ceremonial groundbreaking took place on April 12, 2007, At the time, it was announced that passengers would be able to ride trains on the new line by the end of 2013. Actual construction work began on April 23, 2007, with the relocation of utility pipes, wires, and other infrastructure. This process took 14 months, nearly double the MTA's anticipated eight months. In November 2007,
Mary Peters, the
United States Secretary of Transportation, announced that the Second Avenue Subway would receive $1.3 billion in
federal funding for the project's first phase, to be funded over a seven-year period. However, due to cost increases for construction materials and
diesel fuel affecting the prices of contracts not yet signed, the MTA announced in June 2008 that certain features of the Second Avenue Subway would be simplified to save money. One set of changes, which significantly reduces the footprint of the subway in the vicinity of 72nd Street, is the alteration of the 72nd Street Station from a three-track, two-platform design to a two-track, single island platform design, paired with a simplification of the connection to the Broadway Line spur. On May 28, 2009, the MTA awarded a $325 million contract to E.E. Cruz and Tully Construction Co., a joint venture and
limited liability company, to construct the
96th Street station box. Work on this contract began in July. In June 2009, the first of three contracts for the 86th Street station was awarded for the advance utility relocation work and construction of cut-and-cover shaft areas at 83rd and 86th Streets. Muck houses were built to store all the dirt and debris from the project. The tunnel boring machine was originally expected to arrive six to eight months after construction began, but the utility relocation and excavation required to create its "launch box" delayed its deployment until May 2010. On October 1, 2010, MTA awarded a $431 million contract to joint venture SSK Constructors for the mining of the tunnels connecting the 72nd Street station to the existing
Lexington Avenue–63rd Street station, and for the excavation and heavy civil structures of the 72nd Street station. A subsequent contract was awarded to Skanska Traylor Joint Venture for excavation of the cavern at the 86th Street station on August 4, 2011. In January 2011, MTA awarded Judlau Contracting a 40-month, $176.4 million contract to rebuild and enlarge the Lexington Avenue–63rd Street station.
Significant progress . Meanwhile, the tunnel boring machine dug at a rate of approximately per day. The machine finished its run at the planned endpoint under 65th Street on February 5, 2011. S3 partially disassembled the TBM and backed it out of the tunnel. It was repositioned in the east starter tunnel to begin boring again. Because the east side of Second Avenue has some soft ground not compatible with the Robbins TBM,
ground-freezing was undertaken to prepare the soil for the TBM. On March 28, 2011, S3, having completed its task of completing the west tunnel to 65th Street, began drilling the east tunnel, with the first being through soil frozen by S3 using calcium chloride solution fed through a network of pipes. The TBM drilling the east tunnel then negotiated the curve onto 63rd Street and broke through the
bellmouth at the existing
Lexington Avenue–63rd Street station. That bellmouth had been built in the late 1970s and early 1980s as part of the construction of the 63rd Street Line in anticipation of the construction of the Second Avenue line. This major milestone was celebrated with a big ribbon-cutting to mark the TBM breaking through to the existing bellmouth. The TBM had dug a total of for the east tunnel. It was located at 1628 Second Avenue between 84th and
85th Streets, near the line's 86th Street station. In the three years that followed, the center was visited over 20,000 times. The final contract, for architectural and mechanical and electrical work at 72nd, 86th, and 96th Street stations; rehabilitation of the Lexington Avenue–63rd Street station; and the Systems Contract (track, signals, and communications) for the entire Phase 1 area was awarded on June 1, 2013. On a July 2013 "report card" that indicated the progress of the subway by Congresswoman
Carolyn Maloney, the construction progress got a "B". Blasting for the station caverns was finished in November 2013, and the muck houses were taken down at around the same time. In the winter of 2013, many of the tracks and signal panels began to arrive at the construction site, to be installed on the line over the next few years. It was reported in November 2013 that one third of the tracks for the line had arrived, for the segments of track between 87th and 105th Streets.
Push for completion On February 24, 2016, the MTA allocated $66 million to speed up the construction of the first phase so that it could open in December. However, in June of that year, it was reported that contractors for the MTA were not expending extra resources to accelerate the last portion of Phase 1 construction, threatening the line's scheduled opening. The MTA had only completed 67% of testing, and the line required hundreds of equipment tests by October 2016 in order to be deemed operational. In a public meeting in May 2016, the MTA unveiled the first iteration of the
New York City Subway map that included the Second Avenue Subway and a rerouted Q service. At the meeting, the MTA also made several suggestions for service changes, including making the
N train express in Manhattan and replacing the Queens section of the Q, as well as the Manhattan local section of the N, with a reinstated
W train. On May 16, 2016, Congresswoman Maloney released another report card on the project. The overall grade improved from a "B" to an "A−", with the caveat that the December 2016 deadline be met. By July 2016, the first phase was 96.3% complete, with only systems testing, architectural finishes, streetscape restorations, and some equipment installations to be completed. However, news outlets reported that the Second Avenue Subway had a "significant risk" of a delayed opening. The test train for the subway line was not set to run until October 2016, despite the line being projected to open within two months of that date. Test trains began running through the new line on October 9, 2016 with weights to simulate rush hour loads, even though equipment installations at two stations, as well as a battery of tests, still needed to be completed in order for the line to be opened to passenger service. Shortly before the first test trains ran, the system's
track geometry car determined that the twin bores of the 63rd Street Connector were too narrow for trains consisting of cars (i.e. trains made of
R46s,
R68s, or
R68As) to enter the line. To accommodate trains of these longer cars, crews shaved down parts of the tunnel walls by mid-October 2016, in time for the test trains. Also in October, new subway signs and maps were erected systemwide in relation to Second Avenue Subway-related service changes. More than 1,300 signs were installed in over forty stations. By late October, the testing for elevators and fire alarms at 72nd Street still had not been completed, and the MTA said that there was a possibility that the subway could open with trains temporarily bypassing 72nd Street. This had been done before in September 2016, when subway trains in
Chelsea temporarily bypassed several stations along
23rd Street due to
bombings. There was a concern that 86th Street was also not completed, with three escalators not installed yet. The two stations were only conducting fourteen equipment tests a week, but there needed to be forty tests per week in order to ensure that the line would open on time. However, an engineer affiliated with the MTA stated that there was a possibility that the line could be delayed to 2017. In November 2016, an independent engineer on the project raised concerns, including whether the required fire safety testing could be completed by December 15. That engineer said that "unprecedented" work was required to complete the line by the year's end. December 31 was still the planned opening date, but there have been logistical and safety concerns about the line's opening on New Year's Eve. Following this, the MTA ordered that contractors finish all remaining construction on the Second Avenues Subway before December 31. Contractors were asked to work double shifts, with all remaining fire and equipment tests to be conducted on a 24-hour-per-day, 7-day-per week schedule so that the December 31 deadline could be met. By December 5, the opening date still had not been finalized, and there still remained a chance that the line would not open until 2017. Governor
Andrew Cuomo (son of former Governor Mario Cuomo, who had allocated funding to the line) was leading the push to open the subway before year's end. On December 10, Governor Cuomo visited two under-construction Second Avenue subway stations, later stating that he was "cautiously optimistic" that the line would open before the New Year. However, as of the MTA board's monthly meeting, which occurred two days after Cuomo's visit, the subway's opening date had still not been finalized.
The New York Times observed that Governor Cuomo's enthusiasm to open the line by December 31 stemmed from an incident that had occurred about a year and a half earlier, where officials at the MTA told him that they wanted to push the opening date back a year or two. However, several unidentified individuals have criticized Cuomo for these actions, saying that the increased involvement in the project served merely to improve his reputation. A day later, MTA chairman Thomas Prendergast stated that the three new stations would all open at the same time, even if that meant delaying the opening of the subway.
Schedules for construction and opening The MTA and its contractors on the project met on a regular basis with the
Manhattan Community Board 8 Second Avenue Subway Task Force and
Manhattan Community Board 11 to report on construction progress and to seek input from the community. Estimated completion schedules slipped over time. When the bond issue to fund the construction was passed in 2005, the MTA said that the project would be done in 2012. This quick completion date was a part of the city's unsuccessful
2012 Summer Olympics bid; the Olympics were
hosted in London instead. In its 2008 capital improvement budget proposal, the MTA pushed back completion of Phase 1 to 2015, and in 2009, the MTA pushed it back again to 2016. Some publications had predicted a December 2016 opening. Others reported that the subway would not open until 2017. By May 2014, the agency was still targeting December 2016 as the completion date, and the project was still within its $4.45 billion budget, and still estimated to serve approximately 200,000 daily riders. with Horodniceanu describing earlier estimates as lacking "the precision required." After Governor Cuomo's intervention, the deadline was reset to December 31, 2016. The confirmed New Year's opening date was attributed to testing being completed at a faster pace than expected. There was another open house on December 30, this time at the 86th Street station. The entrance to the Lexington Avenue–63rd Street station at Third Avenue, which was completed as part of Phase 1, was also opened on that date. The ceremonial first train, with Governor Cuomo, Mayor
Bill de Blasio and other public officials, left 72nd Street on New Year's Eve shortly after 10:30 p.m., toward 96th Street. A party was held at the 72nd Street station. The next day, on January 1, 2017, the first train left from 57th Street heading uptown. The stations on the first phase opened at 11:45 a.m, and the first trains arrived at about noon. On opening day, the stations were crowded with passengers seeking to check out the new line. About 48,200 passengers entered the new stations on that day, excluding passengers who toured the line by entering at a station in the rest of the system. The line opened to generally positive acclaim. The 96th, 86th, 72nd, and 63rd Street stations featured new artwork by artists
Sarah Sze,
Chuck Close,
Vik Muniz, and
Jean Shin, respectively. On January 3, the first date on which the line began operating under a weekday schedule, some rush hour N trains started using the line. During the opening week of operation, trains were running every six minutes during peak hours, and there was no service between 10 p.m. and 6 a.m. Overnight service began on January 9, 2017.
Ridership pattern changes In January 2017, compared to January 2016, ridership on the Lexington Avenue Line at the
68th Street,
77th Street,
86th Street, and
96th Street stations decreased because of the opening of Phase 1. The main decrease in ridership was at the 86th Street station, where more than 28,000 of its 120,000 daily riders switched to using the Second Avenue Subway. Overall, the Second Avenue Line's three stations and the renovated Lexington Avenue–63rd Street station saw an average weekday ridership of more than 150,000 by the end of January. The 72nd Street station was the busiest of the line's new stations, with an average daily ridership of 44,000. By May 15, ridership had increased to 176,000 passengers a day, reducing overall usage on the Lexington Avenue Line by 26% while representing a 42% increase from the January ridership. Because of the increasing demand, Q service was increased by one downtown trip in the morning and by one uptown trip in the evening in November 2017. In addition, one R trip started running via the line to boost service. On July 13, 2018, the subway system's ridership totals for 2017 were released, showing that the opening of the line significantly decreased ridership at adjacent stations on the Lexington Avenue Line at 59th Street, 68th Street, 77th Street, 86th Street, 96th Street and 103rd Street. Ridership on the Lexington Avenue Line decreased by 28%, or 46,000 daily riders.
Controversies In February 2011, a lawsuit was filed by the Yorkshire Towers at 86th Street over the location of two proposed Second Avenue Subway entrances that were located right in front of the building but facing away from its semicircular driveway citing
quality of life issues. However, the lawsuit was later dismissed. In an unrelated 2012 controversy, some residents in the 72nd Street station area claimed to have come down with a "Second Avenue cough" caused by dust from construction, and local doctors saw that the
air quality of the area had decreased while nasal sicknesses had increased. The MTA tried to combat this by creating new structures and using other methods to reduce dust inhalation. The MTA prepared a report that said in the 86th Street station area "all monitored concentrations were below the established benchmark levels". The
New York Daily News alleged that the subway project was very unsafe. For example, on August 8, 2012, an explosion caused rocks to fly all over an intersection. causing a large explosion that sent debris into the air and broke windows of buildings in the area and damaged nearby sidewalks. In another instance, contaminated rocks were carried away from a construction site on 63rd Street, and the incident went unnoticed. but while he was extricated after four hours of rescue efforts, he nearly died after the incident. In response to noise complaints caused by blasting underground, the MTA limited blasting to before 7 p.m. each day. Before the restrictions, blasting had continued to as late as 10:30 p.m. every day, shaking buildings above the corridor. Several safety tests had been rushed in order to have the line technically open by the end of 2016. but the fire alarm systems at each station were deactivated around this time, requiring fire safety chiefs to be posted at each station. , some of these tests had yet to be completed even though the line had been opened for eight months. The
Federal Transit Administration only allowed the line to operate under a temporary safety certificate, with the permanent one expected for November of that year. In July 2017, as temperatures in the city rose, straphangers expressed complaints about the high temperatures of stations along the line, even though they were supposed to be climate-controlled. This was since the MTA had to get permission from the
City Health Department to cool the air, with a test ensuring no
Legionnaires' disease in the cooling towers, a precaution arising from
several deadly outbreaks in the city in previous years. The MTA had not conducted the test quickly enough, but after criticism, it received permission on July 7. Climate control was expected to be turned on by July 14. == 2016–present: Second phase ==