Early planning platform area In 1973, the Overseas Technical Cooperation Agency (OTCA; predecessor of the
Japan International Cooperation Agency) presented a plan to construct five subway lines in Metro Manila. The study was known as the Urban Transport Study in the Manila Metropolitan Area. One of the five lines, Line 3, was planned as a line along
Epifanio de los Santos Avenue (EDSA), the region's busiest road corridor. The plan would have resolved the traffic problems of Metro Manila and would have taken 15 years to complete. Another study by JICA was presented in 1976 which included the five lines proposed in 1973. The study recommended heavy rail due to the rising population. The study integrated the previous 1973 OTCA study, the 1976 JICA study, and the 1977
Freeman Fox and Associates study, which was used as the basis for the
LRT Line 1. The Build-Lease-Transfer (BLT) agreement was signed on November 7. According to the agreements, the line would use light rail vehicles from the Czech and Slovak Federal Republics and will have a maximum carrying capacity of 450,000 passengers a day, or 150 million a year to be achieved, through 54 such vehicles operating simultaneously. The EDSA LRT III will run at grade, or street level, on the mid-section of EDSA for a distance of from
F.B. Harrison, Pasay, to North Avenue, Quezon City. The system will have its own power facility. It will also have thirteen (13) passenger stations and one depot on government property at North Avenue. The
Supreme Court had a case barring Eli Levin from implementing the project in March 1994, and the bids were ABB and
Mitsubishi Corporation, which also wanted to supply contracts. A consortium of local companies, led by Fil-Estate Management was later joined by
Ayala Land, and 5 others, later formed the
Metro Rail Transit Corporation (MRTC) in June 1995 and took over the EDSA LRT Corporation. The project then became known internally as the Light Rail Transit System (LRTS).
Construction and opening in 2001. On March 27, 1996, the unveiling marker was attended by President Ramos and others. A separate agreement was signed with ČKD Dopravní Systémy (ČKD Tatra, now part of
Siemens AG), the leading builder of trams and light rail vehicles for the
Eastern Bloc, on rolling stock. MRTC also retained the services of ICF Kaiser Engineers and Constructors to provide program management and technical oversight of the services for the design, construction management, and commissioning. During construction, the MRTC oversaw the design, construction, equipping, testing, and commissioning, while the DOTC oversaw technical supervision of the project activities covered by the BLT contract between the DOTC and MRTC. The DOTC also sought the services of
SYSTRA, a French consultant firm, with regards to the technical competence, experience and track record in the construction and operations. with all remaining stations opening on July 20, 2000, a little over a month past the original deadline, due to DOTC's inclusion of additional work orders such as the Tramo flyover in Pasay leading to
Ninoy Aquino International Airport. Initial ridership on the first section fell well below expectations. Passengers complained that the tickets were too expensive, with a maximum fare of . At the time, this was more costly than a comparable bus ride along the EDSA, or similar rail trips elsewhere on the LRTA and the PNR. Others complained of an excess of stairs, and a lack of connectivity between the stations and other modes of public transportation. The MRTC had projected a daily ridership of 300,000 passengers, but in the first month of operations, the system saw only 40,000 passengers daily. However, patronage steadily grew to an average of 109,000 per day in 2000, and 312,000 per day by 2003. To alleviate passenger complaints, the MRTC later reduced passenger fares to , as per the request of then-President Joseph Estrada and a subsequent government subsidy. During the line's construction in 2000, Pasay residents raised concerns about the line being constructed at ground level, resulting in the closure of several intersections along EDSA, forcing people to take long detours just to cross EDSA. Residents also complained that they were not properly consulted about the line's construction in their area. The MRTC stated that the segment could not be made as an elevated railway due to the
air rights above the LRT-1 already being awarded to the
Department of Public Works and Highways for a
flyover in 1996.
Overcrowding and maintenance problems MRTC projected a capacity breach in the system by 2002. By 2004, the line had the highest ridership of the three lines, with 400,000 passengers daily. By early 2012, the system was carrying around 550,000 to 600,000 commuters during weekdays and was often badly overcrowded during peak times of access during the day and night. It operated beyond its original designed capacity until 2019. In 2011, Sumitomo, through TES Philippines, issued a warning about the severe overcrowding situation of the line, in which a failure to immediately upgrade the systems would result in potential damage. Sumitomo's original maintenance contract was set to expire in June 2010, but was extended four times. On November 17, 2010, MRTC transferred its responsibility of maintaining the system to the DOTC. By the end of Sumitomo's extended contract in October 2012, the DOTC, under the leadership of its secretary
Jun Abaya, decided to procure a new maintenance firm. After the DOTC takeover, unloading incidents and train shortages became rampant. On the other hand, the government of Benigno Aquino III had been planning to buy the line from the MRTC; Representative
Edgar Erice of
Caloocan's 2nd congressional district accused the MRTC of neglecting and not improving the services of the line under its watch. Following a major train derailment on August 13, 2014, experts from the
Mass Transit Railway in
Hong Kong audited the MRT-3 two weeks after the incident. In November, the MTR reported that the line's performance was "unsatisfactory". The
Philippine Senate, in February 2016, released a report stating that Abaya and other DOTC officials "may have violated" the Anti-Graft and Corrupt Practices Act in relation to questionable contracts with the subsequent maintenance providers. In a Senate report on the results of the MTR audit, DOTC officials were reported to be involved in graft in relation to questionable contracts, especially those for the maintenance of the line. The DOTC tried to bid out a three-year maintenance contract in October 2014 and January 2015, but both biddings failed. Through a negotiated procurement, the Busan
joint venture, consisting of
Busan Transportation Corporation, Edison Development & Construction, Tramat Mercantile Inc., TMICorp Inc., and Castan Corporation was awarded the three-year contract by the DOTC. The contract started in January 2016 and was slated to end by January 2019. In 2017, DOTC's succeeding agency, the
Department of Transportation (DOTr) attributed the operation's disruptions of the rail system to the Busan joint venture, later known as
Busan Universal Rail, Inc. (BURI), with DOTr Transport Undersecretary for Rails Cesar Chavez noting 98 service interruptions and 833 passenger unloadings (or average of twice daily) as well as train derailments in April–June 2017. BURI insisted that the disruptions the railway line was experiencing is due to "inherent design and quality concerns" and not to poor maintenance or normal tear or wear. It said that glitches started occurring since 2000, a claim that MRTC dismissed when Sumitomo was maintaining the system. The maintenance contract was terminated on November 6, 2017.
Capacity expansion were procured under the capacity expansion project. , which entered service in 2016. However,
several issues and controversies prevented the trains from mainline operations; CRRC Dalian agreed in 2018 to amend the train specifications to match the contract terms at no cost. Due to the trains undergoing the said adjustments, they were slowly introduced into regular operations, which led to the start of the gradual deployment on October 27, 2018. Aside from the procurement of the new trains, the capacity expansion project included the upgrading of the ancillary systems such as the power supply, overhead lines, the extension of the
pocket track near
Taft Avenue station and the modification of the turn back siding north of the
North Avenue station. The original plan also included the upgrading of the signaling system. These upgrades would only be realized as part of the line's rehabilitation. Plans were also laid to increase the number of cars in each train set, from the current three cars to four, which also increases the number of passengers being accommodated for each trip, from 1,182 to 1,576. This was first mentioned in 2013, during the bidding process for the new trains. Despite this, four-car operations were first tested in a Dalian train in May 2016. After the rehabilitation of the line which included the upgrading of the power supply, a dynamic test run for the use of four-car trains for regular operations was conducted on March 9, 2022. Regular four-car operations began on March 28, initially deploying two trains for daily operations, subsequently increased to four. Although full conversion was initially planned to be achieved by 2023, all trains soon reverted to the existing 3-car configuration. Four-car operations returned on April 21, 2025, with three four-car trains being deployed during peak hours, later increased to six by October 17. Plans were laid for full four-car operations in the long run, as well as the full deployment of the CRRC Dalian trains, to increase ridership capacity to 800,000 passengers.
Rehabilitation expressed its interest to rehabilitate the line. That same year, Metro Pacific submitted another proposal to rehabilitate, operate and maintain the line. These proposals however would be rejected by the government. Following the termination of the maintenance contract with Busan Universal Rail, Inc., the DOTr announced on November 29, 2017, that a government-to-government agreement between the Philippines and
Japan would be signed by the end of that year, paving the way for
Sumitomo Corporation to return as the maintenance provider. The project, partly funded by a loan from the
Japan International Cooperation Agency, It intended to rehabilitate and upgrade the existing systems and trains, for the line to return to its original high-grade design. On November 8, 2018, the Philippine and Japanese governments signed the loan agreement for the line's rehabilitation after both governments exchanged notes the previous day. The rehabilitation and maintenance contract was signed by the DOTr and Sumitomo on December 28. Originally scheduled to start in January 2019, delays in the implementation of the national budget for the 2019
fiscal year caused consequent delays, as around four billion pesos would be sourced from the government. On May 1, 2019, Sumitomo Corporation,
Mitsubishi Heavy Industries Engineering (MHIENG), Under the 43-month contract, rehabilitation works were to be done within 26 months. It covers the overhaul of all
MRTC Class 3000 vehicles, repairs on the escalators and elevators, rail replacement, upgrades on the signaling and communication systems, power supply, overhead systems, maintenance and station equipment. After the rehabilitation, a 17-month maintenance contract would be undertaken by the Japanese firms. to mark the completion of the rehabilitation project at
Quezon Avenue station. The rehabilitation was originally scheduled to be completed by July 2021. However, delays brought by the
COVID-19 pandemic caused revised timelines. The project was completed in December 2021, as announced by Transportation Secretary
Arthur Tugade on February 28, 2022. On March 22, President
Rodrigo Duterte and Secretary Tugade inaugurated the newly rehabilitated line at a completion ceremony held at
Shaw Boulevard station. but was extended for an additional two months. On May 26, 2023, a loan was signed by the governments of the Philippines and Japan and for the second phase of the project, covering the line's continued maintenance and its connection to the
North Triangle Common Station with the lines that would interchange at that station. Four days later, DOTr and Sumitomo signed a contract to extend the latter's maintenance until July 31, 2025. Under the extended contract, the existing three-car trains would be expanded to four cars to cater the increase in passenger demand. Additionally, the
pocket track near
Taft Avenue station was extended to accommodate longer four-car trains, with construction works taking place from November 2024 to April 2025. The program aims to increase the line's ridership capacity to 500,000 passengers a day. On September 12, 2025, the DOTr extended Sumitomo's contract again for an additional two years. JICA subsequently extended another loan worth , which was signed by both governments on February 4, 2026. ==Route==