Formation The core of the Northern line evolved from two railway companies: the City & South London Railway (C&SLR) and the Charing Cross, Euston & Hampstead Railway (CCE&HR). The C&SLR was London's first electric hauled deep-level tube railway. It was built under the supervision of
James Henry Greathead, who had been responsible for the
Tower Subway. It was the first of the Underground's lines to be constructed by boring deep below the surface and the first to be operated by electric traction. The railway opened in November 1890 from
Stockwell to a now-disused station at
King William Street. This was inconveniently placed and unable to cope with the company's traffic so in 1900 a new route to
Moorgate via
Bank was opened. By 1907, the C&SLR had been further extended at both ends to run from
Clapham Common to
Euston. The CCE&HR, commonly known as the "Hampstead Tube", was opened in 1907 and ran from Strand (nowadays
Charing Cross) via Euston to
Camden Town with branches splitting to
Golders Green and Highgate (nowadays
Archway). It was extended south by one stop to Charing Cross (nowadays
Embankment) in 1914 to form an interchange with the
Bakerloo and
District lines. In 1913, the
Underground Electric Railways Company of London (UERL), owner of the CCE&HR, took over the C&SLR although they remained separate companies for some time.
Integration During the early 1920s a series of works were carried out to connect the C&SLR and CCE&HR tunnels to enable an integrated service to be operated. The first of these new tunnels between the C&SLR's Euston and CCE&HR's Camden Town stations had originally been planned in 1912 but was delayed by the
First World War. Construction began in 1922 and this first tunnel opened in 1924. The second connection linking the CCE&HR's Embankment and C&SLR's
Kennington stations opened in 1926. It provided a new intermediate station at
Waterloo to connect to
the main line station. The smaller diameter tunnels of the C&SLR were also enlarged to match the standard diameter of the CCE&HR and other deep tube lines. In conjunction with the works to integrate the two lines, two major extensions were undertaken: northwards to
Edgware in
Middlesex and southwards to
Morden in
Surrey. The Edgware extension used plans dating back to 1901 for the
Edgware and Hampstead Railway which the UERL's subsidiary, the
London Electric Railway, had taken over in 1912. It extended the CCE&HR line from its terminus at Golders Green to
Hendon Central in 1923 and to
Edgware in 1924. The line crossed open countryside and ran mostly on viaduct from Golders Green to
Brent and then on the surface, apart from a short tunnel north of Hendon Central. Five new stations were built to pavilion-style designs by
Stanley Heaps, stimulating the rapid northward expansion of suburban developments in the following years. The engineering of the Morden extension of the C&SLR from Clapham Common to Morden was more demanding, running in tunnel to
Morden station which was then constructed in a cutting and the line continued a bit beyond to the depot. The extension was initially
planned to continue to
Sutton over part of the route of the unbuilt
Wimbledon and Sutton Railway (in which the UERL held a stake) but agreements were made with
Southern Railway (SR) to end the extension at Morden, the SR building a surface line from Wimbledon to Sutton in the 1930s via South Merton and St. Helier. The tube extension itself opened in 1926 with seven new stations all designed by
Charles Holden in a modern style. Owing to the complicated nature of the resulting line, it became known as the Morden–Edgware line, although a number of alternative
portmanteau names were mooted in the fashion of the
Baker Street and Waterloo Railway becoming the Bakerloo line, such as "Edgmor", "Mordenware", "Medgeway" and "Edgmorden" lines. After the UERL and the
Metropolitan Railway (MR) became unified under the
London Passenger Transport Board (LPTB) in 1933, the MR's
Great Northern & City Railway subsidiary, which ran mostly underground from Moorgate to
Finsbury Park, transferred management to the Morden–Edgware line, branding itself as the Northern City line.
Northern Heights plan Following the formation of the LPTB, in June 1935 the organisation proposed the
New Works Programme, an ambitious plan to expand the Underground network in response to London's growing suburban population and to relieve congestion on the existing
steam-operated suburban lines. In the case of the Morden–Edgware, these were the
London and North Eastern Railway (LNER) suburban lines north of Highgate, built in the 1860s and 1870s by the
Edgware, Highgate and London Railway (EH&LR) and its successors, running from Finsbury Park to
Edgware via Highgate, with branches to
Alexandra Palace and
High Barnet. The Morden–Edgware line's project, known as the Northern Heights plan owing to the high ground in north London, involved
fourth-rail electrification of the surface lines and the
double-tracking of the single-line section between
Finchley (Church End) and Edgware. The Northern Heights plan also called for the construction of three new linking sections of track: between the Northern City line and new surface level platforms at Finsbury Park; a deep-level tunnel from Archway to
East Finchley; and a diversion of the Mill Hill branch to the LPTB's Edgware station. As a result of the project's name, the Morden–Edgware line was renamed as the Northern line on 28 August 1937. Work began on the initial stages of the extensions in 1936, as did that on Bushey Heath following its authorisation in 1937, with completion projected by 1941. The tunnelling northwards from Archway was the first element to be completed and an initial service to the rebuilt East Finchley station commenced on 3 July 1939, though trains skipped the deep-level platforms at Highgate until its fitout was completed by 19 January 1941. Further progress was disrupted by the start of the
Second World War in September 1939; however enough development had been made to complete the electrification of the High Barnet branch, over which tube services started on 14 April 1940, and the single-track LNER line to Edgware being electrified as far as
Mill Hill East, reopening as a tube service on 18 May 1941 to serve the nearby
Inglis Barracks. The partially-complete depot at Aldenham was converted into an aircraft factory, constructing
Handley Page Halifax bombers as part of the war effort. Other work on the extension that were eventually halted during the Second World War included the construction of a viaduct at
Brockley Hill and a tunnel near
Elstree South which started in June 1939, the laying of a second line as far as
Mill Hill (The Hale) and the construction of its second platform. Independent of the Northern Heights plan was an intention to introduce nine-car trains on the Northern line as a response to severe overcrowding. While several existing surface station platforms were lengthened to accommodate two additional cars, the deep-level platforms were not easily rebuilt, although Highgate's new platforms were built nine-car trains in mind, so
selective door operation was introduced whereby two cars of the train had its doors locked in the tunnel. Nine-car operations began in November 1937 between Edgware and Kennington via Charing Cross, with ten new
1938 Stock trains being fitted with selective door operation. By the start of the War, nine-car trains were discontinued and never revived. After the war, much of the area beyond Edgware was made part of the
Metropolitan Green Belt that largely prevented the anticipated residential development, thus the potential demand for services from Bushey Heath vanished. Although efforts were made to complete Aldenham Depot as an Underground facility, from December 1947 it was modified for use as a heavy repair works of
bus bodies, supposedly temporarily until Aldenham was required for railway purposes. Following the extension's cancellation, the depot was converted into an overhaul facility for buses, serving this purpose until 1986. The introduction of electric services to High Barnet and Mill Hill East undermined passenger numbers on the remaining LNER-operated lines. Consequently, passenger services to Mill Hill (The Hale) and Edgware, having been suspended in September 1939 to allow works to be completed, never resumed Tickets were still being sold to and from Mill Hill (The Hale) until the late 1960s, with passengers being directed onto
the 240 bus to connect with the Underground. Further proposals included building additional tunnels between Kennington and
Tooting Broadway to relieve congestion, with alternative duplication suggested between Golders Green and Waterloo. In the 1980s, an extension of the Northern line to
Peckham Rye and
Streatham Hill was proposed as part of a review of potential extensions of Underground lines. Between 1989 and 1992,
Angel tube station was rebuilt with a new northbound tunnel alongside the existing station platforms which were widened to become the new southbound platform, replacing the old narrow platforms which by then had become a safety hazard with increased passenger ridership. A similar project was undertaken at Euston in the 1960s in conjunction with the construction of the
Victoria line By the early 1990s, the line had deteriorated due to years of under-investment and the use of old
rolling stock, most of which dated back to the early 1960s. The line gained the nickname "Misery Line" due to its perceived unreliability. In 1995, a comprehensive refurbishment of the line began – including track replacement, power upgrades, station modernisation (such as
Mornington Crescent) and the replacement of older rolling stock with new
1995 Stock thanks to a
public–private partnership deal with
Alstom. The Northern line was originally scheduled to switch to
automatic train operation in 2012, using the same
SelTrac S40 system as used since 2009 on the
Jubilee line and for a number of years on the
Docklands Light Railway. Originally the work was to follow on from the Jubilee line so as to benefit from the experience of installing it there, but that project was not completed until spring 2011. Work on the Northern line was contracted to be completed before the
2012 Olympics. It was then undertaken in-house, and TfL predicted the upgrade would be complete by the end of 2014. The first section of the line (West Finchley to High Barnet) was transferred to the new signalling system on 26 February 2013 and the line became fully automated on 1 June 2014, with the Chalk Farm to Edgware via Golders Green section being the last part of the line to switch to ATO. Since the mid-autumn of 2016, a 24-hour "
Night Tube" service has run on Friday and Saturday nights from Edgware and High Barnet to Morden via the Charing Cross branch; service is suspended on the Bank branch during these times. Trains run every eight minutes between Morden and Camden Town and up to every 16 minutes on the Edgware and High Barnet branches. Labour disputes delayed the planned start date of September 2015. In January 2018, Transport for London announced that it would double the period during which it runs peak evening services in the central London section to tackle overcrowding. There would now be 24 trains per hour on both central London branches and the northern branches, as well as 30 trains per hour on the Kennington to Morden section between 5pm and 7pm.
Battersea extension Throughout the 2000s, no plans were considered for extending the Northern line, as the PPP contracts to upgrade the Underground did not include provision for line extensions. This prolonged period without an extension ultimately changed when the Northern line was extended to serve the redevelopment of
Battersea Power Station in 2021. Partially funded by private developers, the £1.2bn project extended the Charing Cross branch of the line for from
Kennington to
Battersea Power Station, with an intermediate stop at
Nine Elms. Approved by Wandsworth Council in 2010 and TfL in 2014, Provision has been made for a future extension to
Clapham Junction. ==Services==