Plans The idea of a general bypass around London was first proposed early in the 20th century. An outer orbital route around the capital had been suggested in 1913, and was re-examined as a motorway route in
Sir Charles Bressey's and
Sir Edwin Lutyens' The Highway Development Survey, 1937.
Sir Patrick Abercrombie's County of London Plan, 1943 and
Greater London Plan, 1944 proposed a series of five roads encircling the capital. The northern sections of the M25 follow a similar route to the
Outer London Defence Ring, a concentric series of anti-tank defences and pillboxes designed to slow down a potential German invasion of the capital during
World War II. This was marked as the D Ring on Abercombie's plans. Following the war, 11 separate
county councils told the
Ministry of Transport that an orbital route was "first priority" for London. Plans stalled because the route was planned to pass through several urban areas, which attracted criticism. The original D Ring through northwest London was intended to be a simple upgrade of streets. In 1951, Middlesex County Council planned a route for the orbital road through the county, passing through
Eastcote and west of
Bushey, connecting with the proposed
M1 motorway, but it was rejected by the Ministry two years later. An alternative route via
Harrow and
Ealing was proposed, but this was abandoned after the council revealed the extent of property demolition required. In 1964, the
London County Council announced the
London Ringways plan, to consist of four concentric motorway rings around London. The following year, the transport minister
Barbara Castle announced that the D Ring would be essential to build. The component parts of what became the M25 came from
Ringway 3 /
M16 motorway in the north and
Ringway 4 in the south. The Ringways plan was controversial owing to the destruction required for the inner two ring roads, (
Ringway 1 and
Ringway 2). Parts of Ringway 1 were constructed (including the
West Cross Route), despite stiff opposition, before the overall plan was postponed in February 1972. In April 1973, the
Greater London Council elections resulted in a
Labour Party victory; the party then formally announced the cancellation of the Ringways running inside Greater London. This did not affect the routes that would become the M25, because they were planned as central government projects from the outset.
Construction Fire Station at Tatling End on the A40 in July 1984, with the
Chiltern Main Line five-arch 1906
Chalfont Viaduct, originally built to straddle the
River Misbourne There was no individual
public inquiry into the M25 as a whole. Each section was presented to planning authorities in its own right and was individually justified, with 39 separate public inquiries relating to sections of the route. The need for the ministry to negotiate with local councils meant that more junctions with local traffic were built than originally proposed. A report in 1981 showed that the M25 had the potential to attract office and retail development along its route, negating the proposed traffic improvements and making Central London a less desirable place to work. None of the motorway was prevented from being built by objections at the public inquiries. However, as a consequence of the backlash against the Ringways, and criticism at the public inquiries, the motorway was built with environmental concerns in mind. New features included additional earth mounds, cuttings and fences that reduced noise, and over two million trees and shrubs to hide the view of the road. Construction of parts of the two outer ring roads, Ringways 3 and 4, began in 1973. The first section, between South Mimms and Potters Bar in Hertfordshire (junctions 23 to 24) opened in September 1975. It was provisionally known as the M16 and was given the temporary general-purpose road designation
A1178. A section of the North Orbital Road between
Rickmansworth and
Hunton Bridge was proposed in 1966, with detailed planning in 1971. The North Orbital Extension was given the go-ahead in January 1973, from Maple Cross. It was , and was to cost £6.5million. The road was constructed to motorway standards and opened on Thursday 26 February 1976, as a section of the
A405. It eventually became part of the M25's route. The
Prime Minister,
Margaret Thatcher, officially opened the M25 on 29 October 1986, with a ceremony in the section between junctions 22 to 23 (
London Colney and
South Mimms). To avoid the threat of road protesters, the ceremony was held a quarter of a mile from the nearest bridge. The total estimated cost of the motorway was around £1billion. It required of concrete, of
asphalt and involved the removal of of spoil. Upon completion, it was the longest orbital motorway in the world at . At the opening ceremony, Thatcher announced that had been constructed while the
Conservative Party were in office, calling it "a splendid achievement for Britain". A 58-page brochure was published, commemorating the completion of the motorway.
Operational history The M25 was initially popular with the public. In the
1987 general election, the
Conservatives won in every constituency that the motorway passed through, in particular gaining
Thurrock from
Labour. Coach tours were organised for a trip around the new road. However, it quickly became apparent that the M25 suffered from chronic congestion. A report in
The Economist said it "had taken 70 years to plan [the motorway], 12 to build it and just one to find it was inadequate". Thatcher rebuked the negative response, calling it "carping and criticism". Traffic levels quickly exceeded the maximum design capacity. Two months before it opened, the government admitted that the three-lane section between junctions 11 and 13 was inadequate and that it would have to be widened to four. In 1990, the
Secretary of State for Transport announced plans to widen the whole of the M25 to four lanes. By 1993, the motorway, designed for a maximum of 88,000vehicles per day, was carrying 200,000. At that time, the M25 carried 15% of UK motorway traffic and there were plans to add six lanes to the section from junctions 12 to 15, as well as widening the rest of the motorway to four lanes. In parts, particularly the western third, that plan went ahead. Again, however, plans to widen further sections to eight lanes (four each way) were scaled back in 2009 in response to rising costs. The plans were reinstated in the agreed
Highways Agency 2013–14 business plan. In June 1992, the
Department for Transport (DfT) announced a proposal to widen the section close to Heathrow Airport to fourteen lanes by way of three additional link roads. That attracted fierce opposition from
anti-motorway protesters who were critical of the
Newbury Bypass and other schemes, but also from local authorities. Surrey County Council led a formal objection to the widening scheme, and it was cancelled shortly afterwards. In 1994, the Standing Advisory Committee on Trunk Road Appraisal published a report saying that "the M25 experience most probably does ... serve as an example of a case where roads generate traffic" and that further improvements to the motorway were counter-productive. In April 1995, the Transport Minister
Brian Mawhinney announced that the Heathrow link roads would be scrapped. installed gantry In 1995, a contract was awarded to widen the section between junctions 8 and 10 from six to eight lanes at a cost of £93.4million, and a
Motorway Incident Detection and Automatic Signalling (MIDAS) system was introduced from junction 10 to junction 15 in 1995, at a cost of £13.5M. That was extended to junction 16 in 2002, at a cost of £11.7M. The system consists of a distributed network of traffic and weather sensors,
speed cameras and
variable-speed signs, that control traffic speeds with little human supervision. It has improved traffic flow slightly, reducing the amount of start-stop driving. After Labour won the
1997 election, the road budget was cut from £6billion to £1.4billion. However, the DfT announced new proposals to widen the section between junction 12 (M3) and junction 15 (M4) to 12 lanes. At the
Heathrow Terminal 5 public inquiry, a Highways Agency official said that the widening was needed to accommodate traffic to the proposed new terminal, but the transport minister said that no such evidence had been given. Environmental groups objected to the decision to go ahead with a scheme to create the widest motorways in the UK, without holding a
public inquiry.
Friends of the Earth claimed the real reason for the widening was to support Terminal 5. The decision was again deferred. A ten-lane scheme was announced in 1998, and the £148million 'M25 Jct 12 to 15 Widening' contract was awarded to
Balfour Beatty in 2003. The scheme was completed in 2005, with dual-five lanes between junctions 12 and 14 and dual-six lanes from junctions 14 to 15. In 2007, junction 25 (A10/Waltham Cross) was remodelled to increase capacity. The nearby Holmesdale Tunnel was widened to three lanes in an easterly direction, and an additional left-turn lane added from the A10 onto the motorway. The total cost was £75million. Work to widen the exit slip-roads in both directions at junction 28 (
A12 / A1023) was completed in 2008. That was designed to reduce the amount of traffic queuing on the slip roads at busy periods, particularly traffic from the clockwise M25 joining the northbound A12. In 2018, a new scheme was proposed, because the junction had reached capacity, accommodating over 7,500vehicles per hour. The scheme involved building a two-lane link road between the M25 and the A12. The work was expected to be completed around 2021/22.
Widening In 2006, the Highways Agency proposed widening of the M25 from six to eight lanes, between junctions 5 and 6, and 16 to 30, as part of a Design, Build, Finance and Operate (DBFO) project. A shortlist of contractors was announced in October 2006 for the project, which was expected to cost £4.5billion. Contractors were asked to resubmit their bids in January 2008, and in June 2009 the new transport minister indicated that the cost had risen to £5.5billion and the benefit to cost ratio had dropped considerably. In January 2009 the government scrapped plans to widen the sections from junctions 5 to 7 and 23 to 27 and that hard shoulder running would be introduced instead. Widening to four lanes was reinstated in the 2013–14 Highways Agency Business Plan. In 2009, a £6.2billion M25 DBFO
private finance initiative contract was awarded to Connect Plus to widen the sections between junctions 16 to 23 and 27 to 30, and maintain the M25 and the Dartford Crossing for a 30-year period. Work to widen the section between junctions 16 (M40) and 23 (A1(M)) to dual four lanes started in July 2009 at an estimated cost of £580million. The junction 16 to 21 (M1) section was completed by July 2011 and the junction 21 to 23 by June 2012. Works to widen the junctions 27 (M11) to 30 (A13) section to dual four lanes also started in July 2009. The junction 27 to 28 (A12) section was completed in July 2010, and the junction 28 to 29 (A127) in June 2011, and the junction 29 to 30 (A13) section opened in May 2012. Work to introduce smart motorway technology and permanent
hard shoulder running on two sections of the M25 began in 2013. The first section between junctions 5 (A21/M26) and 7 (M23) started construction in May 2013 with the scheme being completed and opened in April 2014. The second section, between junctions 23 (A1/A1(M)) and 27 (M11), began construction in February 2013 and was completed and opened in November 2014. In December 2016, Highways England completed the capacity project at junction 30 (Thurrock) as part of the
Thames Gateway Delivery Plan. The £100million scheme included widening the M25 to four lanes, adding additional link roads, and improvements to drainage. Work began to widen the M25 and A3 around junction 10 in November 2022. The project is intended to limit congestion at the junction and allow traffic to proceed more safely. However, these plans caused concerns about the amount of woodland that would be required. In March 2024, National Highways announced the first all-day closure of the M25 in its operational history. The motorway was closed between junctions 10 and 11 from 15–18 March in order to remove a bridleway bridge. The road was closed completely for two other occasions that year, with a final two closures scheduled for 2025. ==Traffic==